You are on page 1of 7

TAILING MINE FILTRATION PROJECT

Site Installation Civil, Structural, Mechanical & Piping (CSMP)


PT. Agincourt Resources
Rev. 0
Monday, 24 July 2023

DAILY PROGRESS REPORT


0. DAILY PROGRESS & MANPOWER Construction Phase

MANPOWER WORK HOURS RAINFALL RECORD

PLAN ACTUAL ACTUAL ACTUAL


DISCIPLINE/ACTIVITY

Day Shift Overtime Night Shift Day Shift Overtime Night Shift Day Shift Overtime Night Shift Start End Total Hours Remarks

Direct Labor * 141 110 1458

Skilled Worker (Source : Jakarta) 110 85 1213

Rebarman 25 23 253

Mason 20 18 198

Carpenter 25 24 264

Fitter 12 8 88

Boilermaker 8 4 44

Pipe Fitter 6 2 22

HDPE Piping 4 4 44 OTHER CONDITION

Welder Steel (SMAW+GTAW) 8 2 22


Total
Start End Remarks
Hours
Painter 2

Unskilled Worker (Source : Local) : Helper 31 22 245

Unskilled Worker (Source : Local) : Watchmen 3 3 33

Indirect * 68 56 598

Construction Manager 1 Total Hours :

Site Manager 1 1 11 Note :

Planner 1 1 11

Surveyor 3 2 22

Field Engineer/Project Engineer 1 1 11

HR Staff/Administration 2 1 11

HR/Administration 1 1 11

GA & Supporting 1 1 17

Administration 1 1 11

Civil Foreman 2 2 22

Civil Supervisor 1 1 11 EQUIPMENT ON SITE QTY

Civil QC Engineer 2 1 11

Civil Superintendent 1 Roughter Crane 50 Ton 1

QC Staff 2 2 22 Roughter Crane 90 Ton 1

Mechanical 6 1 8 Boomtruck 15 Ton 1

SMP Foreman 2 2 22 Concrete Pump 1

SMP Supervisor 1 1 11 Mixer Truck 01 1

SMP QC Engineer (WI qualification) 2 1 11 Mixer Truck 02 1

Scaffolding Inspector 1 Mixer Truck 03 1

Scaffolder 7 9 100 Mixer Truck 04 1

HSE Supervisor 1 Telehandler 1

Safety Officer 3 4 44 Tractor Head 6X6 1

Logistic and Warehouse 2 3 30 LV 01 (Pajero) 1

Rigger 3 4 44 LV 02 Double Cabin 1

Assisstant Deputy Construction Manager 2 1 11 LV 03 Double Cabin 1

Assistant CM 1 1 12 Generator 45 kVA 4

Electrician 2 2 22 Generator 165 kVA 1

Operator Crane 50T 1 1 11 Compressor 2

Operator Crane 90T 1 1 11 Stamper 4

Operator Telehandler 1 1 11 Light Tower 2

Operator Manlift 1 Total Equipment 26

Operator Boom Truck 1 1 12

Operator Trailer 1 1 11

Operator Concrete Pump 1 1 8

Driver Concrete Pump 1 1 8


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
Rev. 0
Monday, 24 July 2023

DAILY PROGRESS REPORT

Assistant Ops Concrete Pump 1 1 8

Operator Mixer Truck 4 4 32

PERI UP Supervisor 2

TOTAL 206 166 1811

1. CONSTRUCTION KEY QUANTITIES (*Plan Based on Work Completion Schedule - WCS)

DAILY CUMULATIVE
BALANCE %
ACTIVITY UNIT QTY Variance REMARKS
ACT. COMPLETE
Plan Actual Plan Actual

Overhead (Indirect)* Percent 100% Monthly Update

On Site Management and Control* Percent 100% Monthly Update

Construction

Civil Work Percent 100.00% 0.16% 0.12% 24.87% 11.19% 13.69% 88.81% 11.19%

Mechanical Work Percent 100.00% 1.52% 1.52% 100.00%

Piping Work Percent 100.00% 0.04% 1.40% 0.52% 0.88% 99.48% 0.52%

Structural Percent 100.00% 0.10% 3.10% 0.74% 2.36% 99.26% 0.74%

Plate Works Percent 100.00% 0.31% 0.31% 100.00%

Erected Tanks Percent 100.00% 0.02% 0.08% 0.08% 100.00%

Electrical Percent 100.00% 0.94% 0.94% 100.00%

Testing and Punch list Percent 100.00% 100.00%

Pre-commisioning Percent 100.00% 100.00%

Total Percent 0.32% 0.12% 32.23% 12.45% 19.78% 12.45%

2. MAJOR HIGHLIGHT

Monday, 24 July 2023 Tuesday, 25 July 2023

ACTIVITY UNIT QTY ACTIVITY UNIT QTY

A. Civil A. Civil

Ongoing Swith Room anchor installation Continue Swith Room anchor installation

Ongoing chipping & finishing EMB footing Continue chipping & finishing EMB footing

Ongoing finishing Transformer Bay footing Continue finishing Transformer Bay footing

Dismantle & cutting precasted SF column rebar Continue dismantle & cutting precasted SF column rebar

Precast Fire Water Filtration Water Servie slab rebar Continue Precast Fire Water Filtration Water Servie slab rebar

B. Structure : B. Structure :

Pre-assembly Tailing transfer service & Pipe Rack Continue Pre-assembly Tailing transfer service & Pipe Rack

C. Mechanical : C. Mechanical :

D. Piping : D. Piping :

Mobilize HDPE piping material Continue Mobilize HDPE piping material

Joint pipe HDPE Field Pipeng & Fitting Ø OSU 400 PN10 Joint 78 Continue Joint pipe HDPE Field Pipe & Fitting Ø OSU 400 PN10

Joint pipe HDPE Field Pipeng & Fitting Ø PSL 400 PN25 Joint 42 Continue Joint pipe HDPE Field Pipe & Fitting Ø PSL 400 PN25

Joint pipe HDPE Field Piping Ø WPR 160 PN10 Joint 73 Continue Joint pipe HDPE Field Piping Ø WPR 160 PN10

Joint pipe HDPE Field Piping Ø PSL 160 PN10 Joint 10 Continue Joint pipe HDPE Field Piping Ø PSL 160 PN10

Joint pipe HDPE Field Piping Ø WFR 90 PN10 Joint 75 Continue Joint pipe HDPE Field Piping Ø WFR 90 PN10

Joint pipe HDPE Field Piping Ø WPO 63 PN10 Joint 70 Continue Joint pipe HDPE Field Piping Ø WPO 63 PN10

Joint pipe HDPE Field Piping Ø PSL 355 PN10 Joint 31 Continue Joint pipe HDPE Field Piping Ø PSL 355 PN10

E. Logistic : E. Logistic :

Unloading Rebar, tools & equipment to TMF area Continue Unloading Rebar, tools & equipment to TMF area

F. Scaffold : F. Scaffold :

Install PERI UP footing GL 1-5 Continue install PERI UP footing GL 1-5

G. Others G. Others

Online & offline Training Online & offline Training

Concern :

Overall progress minus -19.78% Base on updated Schedule R

Need Civil to give way to SMP team

Prepared by : Checked By : Acknowledged By :

Project Control Site Manager


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Monday, 24 July 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

GENERAL ACTIVITIES

General Pre-start meeting TBM pagi di Pad A


CIVIL

Ongoing Switch Room anchor installation Transformer bay finishing after concreting

Install Switchroom anchor Reinforce switchroom pedestal formwork support


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Monday, 24 July 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Install Switchroom formwork, reinforce support, install anchor Dismantle formwork support

Cuting stopcor wall emg Ciping wall emg

Finishing EMB south footing Install bottom waler Switchroom pedestal support

Switchroom Aktifity Dismantle precasted column on pad C

Fabricate spacer, on pad C workshop Dismantle formwork support


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Monday, 24 July 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Finishing EMB footing Pabrikasi mal angkur

Pilah rebar peminggang wall Repair ties

Install Fire water pump slab Buang puing area bekfil emg

Buat kotak untuk penampungan sampah tmf Fabricate waste bin for TMF area
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Monday, 24 July 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

EMB footing Manual Backfill Backfiil manual area EMB

Bending cakar ayam finis Fabricate waste bin for TMF area
Piping

Joint 09 HDPE pipe dia PSL 160 Joint 08 HDPE pipe dia PSL 160

Continue fitting HDPE pipe Joint 10 HDPE pipe dia PSL 160
Structure
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Monday, 24 July 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Continue sort out & pre assembly TFP Continue sort out & pre assembly TFP

Continue sort out & pre assembly TFP Continue sort out & pre assembly TFP
Prepared by : Approved by :

Project Control

You might also like