TAILING MINE FILTRATION PROJECT


Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
Rev. 0
Date : April 8th, 2023

DAILY PROGRESS REPORT


0. DAILY PROGRESS & MANPOWER Construction Phase
MANPOWER WORK HOURS RAINFALL RECORD
PLAN ACTUAL ACTUAL ACTUAL
DISCIPLINE/ACTIVITY
Night Night Night
Day Shift Overtime Day Shift Overtime Day Shift Overtime Start End Total Hours Remarks
Shift Shift Shift
Direct Labor * 8 6 66
Skilled Worker (Source : Jakarta) 8 6 66
Rebarman 1 1 11
Mason 1 1 11
Carpenter 1 1 11
HDPE Piping 2 2 22
Fitter 1
Pipe Fitter
Fitter 1
Pipe Fitter
Boilermaker 1 1 11
Welder Steel (SMAW+GTAW)
Painter
OTHER CONDITION
Unskilled Worker (Source : Jakarta)
Start End Total Hours Remarks
Helper
Skilled Worker (Source : Local)

Unskilled Worker (Source : Local)

Indirect * 24 19 209
Construction Manager Total Hours :
Deputy Construction Manager 1 1 11 Note :
Planner 1 1 11
Surveyor 1 1 11
Field Engineer/Project Engineer 1 1 11
HR Staff 2 1 11 EQUIPMENT ON SITE QTY
Civil Foreman 1 1 11
Civil Supervisor 1 1 11 Roughter Crane 50 Ton 1
Civil QC Engineer 1 1 11 Roughter Crane 90 Ton 1
Civil Superintendent Boomtruck 15 Ton 1
QC Staff Concrete Pump 1
Mechanical Mixer Truck 12 1
SMP Foreman 1 1 11 Mixer Truck 13 1
SMP Supervisor 1 1 11 Telehandler 1
SMP QC Engineer (WI qualification) Tractor Head 6X6 1
Scaffolding Inspector LV 01 (Pajero) 1
Scaffolder LV 02 Double Cabin 1
HSE Supervisor 1 1 11 LV 03 Double Cabin 1
Safety Officer 1 Total Equipment 11
Logistic and Warehouse 1
Rigger 1
Driver 2 2 22
Electrician 2 2 22
Operator Crane 2 2 22
Operator Telehandler 1 1 11
Operator Manlift
Operator Boom Truck 1
Operator Trailer 1 1 11
Operator Concrete Pump
Operator Mixer Truck

TOTAL 32 25 275

2. MAJOR HIGHLIGHT
Saturday, 08 April 2023 Sunday, 09 April 2023
ACTIVITY UNIT QTY ACTIVITY UNIT QTY
A. Civil A. Civil
Prepare to mobilize heavy equipment from Quarry to TMF site Prepare to mobilize heavy equipment from Quarry to TMF site
Produce concrete decking Produce concrete decking
Create TMF site office base concrete Create TMF site office base concrete
B. Structure : B. Structure :

C. Mechanical : C. Mechanical :

D. Piping : D. Piping :

E. Logistic : E. Logistic :

F. Scaffold : F. Scaffold :

G. Others G. Others
Online & offline Training Continue online & offline Training

Concern :

Prepared by : Checked By : Acknowledged By :

Project Control Site Manager


Page 2 of 2

MILLING CAPACITY EXPANSION PROJECT


Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Date : April 8th, 2023

DAILY PHOTOGRAPH

PHOTOGRAPH

GENERAL ACTIVITIES

Take-5 sosialization

CIVIL

Stripping Concrete pad formwork Stripping Concrete Formwork for office base

Continue produce concrete decking & pad Ready to use Concrete pad

Others

Training PTW for batch 2 manpower Training WAH for batch 2 manpower

Training Simper Familiarisation TMF area

Practice Training Simper Practice Training Simper


Prepared by : Approved by :

Project Control