Day Shift Overtime Night Shift Day Shift Overtime Day Shift Overtime Night Shift Start End Total Hours Remarks
Shift
Rebarman 25 23 253
Mason 20 18 198
Carpenter 25 24 264
Fitter 12 5 55
Boilermaker 8 4 44
Pipe Fitter 6 2 22
34
Indirect * 66 53 559
HR Staff/Administration 2 1 11
HR/Administration 1 1 11
Civil Foreman 2 2 22
Civil QC Engineer 2 1 11
Operator Trailer 1 1 11
PERI UP Supervisor 2 1 8
DAILY CUMULATIVE
BALANCE %
ACTIVITY UNIT QTY Variance REMARKS
ACT. COMPLETE
Plan Actual Plan Actual
Construction
Civil Work Percent 100% 0.24% 0.15% 16.2% 9.3% 6.9% 91% 9.27%
Piping Work Percent 100% 0.01% 0.00% 0.44% 0.32% 0.12% 99.68% 0.32%
2. MAJOR HIGHLIGHT
A. Civil A. Civil
Continue PERI UP to complete 60 unit GL 15-11 unit 60 Complete PERI UP to complete 60 unit GL 15-11
Finishing EMB Shear Key formwork Complete Finishing EMB Shear Key formwork
Install LC formwork conduit pipe line 3rd layer LC conduit pipe line 3rd layer
Install stirr up on starter bar column Continue Install stirr up on starter bar column
B. Structure : B. Structure :
C. Mechanical : C. Mechanical :
D. Piping : D. Piping :
Joint pipe HDPE Field Pipeng & Fitting Ø OSU 400 PN10 Joint 34 Continue Joint pipe HDPE Field Pipeng & Fitting Ø OSU 400 PN10
Joint pipe HDPE Field Pipeng & Fitting Ø PSL 400 PN25 Joint 28 Continue Joint pipe HDPE Field Pipeng & Fitting Ø PSL 400 PN25
Joint pipe HDPE Field Piping Ø 160 PN10 Joint 68 Continue Joint pipe HDPE Field Piping Ø 160 PN10
Joint pipe HDPE Field Piping Ø 90 PN10 Joint 68 Continue Joint pipe HDPE Field Piping Ø 90 PN10
Joint pipe HDPE Field Piping Ø 63 PN10 Joint 62 Continue Joint pipe HDPE Field Piping Ø 63 PN10
Joint pipe HDPE Field Piping Ø 355 PN16 Joint 9 Continue Joint pipe HDPE Field Piping Ø 355 PN16
E. Logistic : E. Logistic :
Unloading Rebar, tools & equipment to TMF area Continue Unloading Rebar, tools & equipment to TMF area
F. Scaffold : F. Scaffold :
G. Others G. Others
Concern :
DAILY PHOTOGRAPH
PHOTOGRAPH
GENERAL ACTIVITIES
Install electrical cable below for conduit Excavate TMF pipe rack footing
Inspection EMB shear key with PT.AR Inspection EMB shear key with PT.AR
Piping
DAILY PHOTOGRAPH
PHOTOGRAPH
Joint 32 HDPE dia 400 PN 10 Install north side EMB Shear Key
Project Control