Night
Day Shift Overtime Night Shift Day Shift Overtime Day Shift Overtime Night Shift Start End Total Hours Remarks
Shift
Rebarman 25 23 253
Mason 20 18 198
Carpenter 25 24 264
Fitter 12 5 55
Boilermaker 8 4 44
Pipe Fitter 6 2 22
34
Indirect * 66 53 556
HR Staff/Administration 2 1 11
HR/Administration 1 1 11
Civil Foreman 2 2 22
Civil QC Engineer 2 1 11
Operator Trailer 1 1 11
PERI UP Supervisor 2 1 8
DAILY CUMULATIVE
BALANCE %
ACTIVITY UNIT QTY Variance REMARKS
ACT. COMPLETE
Plan Actual Plan Actual
Construction
Civil Work Percent 100% 0.72% 0.02% 17.2% 9.3% 7.9% 91% 9.30%
Piping Work Percent 100% 0.01% 0.00% 0.45% 0.33% 0.12% 99.67% 0.33%
2. MAJOR HIGHLIGHT
A. Civil A. Civil
Continue PERI UP to complete 60 unit GL 15-11 unit 60 Complete PERI UP to complete 60 unit GL 15-11
Install stirr up on starter bar column Continue Install stirr up on starter bar column
B. Structure : B. Structure :
C. Mechanical : C. Mechanical :
D. Piping : D. Piping :
Joint pipe HDPE Field Pipeng & Fitting Ø OSU 400 PN10 Joint 41 Continue Joint pipe HDPE Field Pipeng & Fitting Ø OSU 400 PN10
Joint pipe HDPE Field Pipeng & Fitting Ø PSL 400 PN25 Joint 30 Continue Joint pipe HDPE Field Pipeng & Fitting Ø PSL 400 PN25
Joint pipe HDPE Field Piping Ø 160 PN10 Joint 68 Continue Joint pipe HDPE Field Piping Ø 160 PN10
Joint pipe HDPE Field Piping Ø 90 PN10 Joint 68 Continue Joint pipe HDPE Field Piping Ø 90 PN10
Joint pipe HDPE Field Piping Ø 63 PN10 Joint 62 Continue Joint pipe HDPE Field Piping Ø 63 PN10
Joint pipe HDPE Field Piping Ø 355 PN16 Joint 11 Continue Joint pipe HDPE Field Piping Ø 355 PN16
E. Logistic : E. Logistic :
Unloading Rebar, tools & equipment to TMF area Continue Unloading Rebar, tools & equipment to TMF area
F. Scaffold : F. Scaffold :
G. Others G. Others
Concern :
DAILY PHOTOGRAPH
PHOTOGRAPH
GENERAL ACTIVITIES
DAILY PHOTOGRAPH
PHOTOGRAPH
Joint 11 HDPE dia 355 PN 16 Continue mobilize & fit up HDPE pipe
Prepared by : Approved by :
Project Control