TAILING MINE FILTRATION PROJECT

Site Installation Civil, Structural, Mechanical & Piping (CSMP)


PT. Agincourt Resources
Rev. 0
Date : May 02th, 2023

DAILY PROGRESS REPORT

0. DAILY PROGRESS & MANPOWER Construction Phase

MANPOWER WORK HOURS RAINFALL RECORD

PLAN ACTUAL ACTUAL ACTUAL


DISCIPLINE/ACTIVITY

Night Day Night Night


Day Shift Overtime Overtime Day Shift Overtime Start End Total Hours Remarks
Shift Shift Shift Shift

Direct Labor * 144 42 462

Skilled Worker (Source : Jakarta) 110 42 462

Rebarman 25 11 121

Mason 20 8 88

Carpenter 25 8 88

Fitter 12 3 33

Boilermaker 8 4 44

Pipe Fitter 6 2 22

HDPE Piping 4 4 44

Welder Steel (SMAW+GTAW) 8 2 22

Painter 2

OTHER CONDITION

Unskilled Worker (Source : Jakarta)


Start End Total Hours Remarks
Helper

Skilled Worker (Source : Local) 15:55:00 16:30:00 00:35:00 Lightning Level 2

Unskilled Worker (Source : Local) 34

34

Indirect * 63 41 436

Construction Manager 1 1 11 Total Hours : 00:35:00

Site Manager 1 1 11 Note :

Planner 1 1 11 Blasting at purnama Pit, all worker evacuate from

Surveyor 2 2 22 TMF area

Field Engineer/Project Engineer 1 1 11

HR Staff 3 2 22 EQUIPMENT ON SITE QTY

Civil Foreman 2 2 22

Civil Supervisor 1 1 11 Roughter Crane 50 Ton 1

Civil QC Engineer 2 1 11 Roughter Crane 90 Ton 1

Civil Superintendent 1 1 11 Boomtruck 15 Ton 1

QC Staff 2 1 11 Concrete Pump 1

Mechanical 6 Mixer Truck 01 1

SMP Foreman 2 2 22 Mixer Truck 02 1

SMP Supervisor 1 1 11 Telehandler 1

SMP QC Engineer (WI qualification) 2 1 11 Tractor Head 6X6 1

Scaffolding Inspector 1 LV 01 (Pajero) 1

Scaffolder 7 3 33 LV 02 Double Cabin 1

HSE Supervisor 1 1 11 LV 03 Double Cabin 1

Safety Officer 3 2 22 Generator 45 kVA 3

Logistic and Warehouse 2 1 11 Compressor 1

Rigger 3 2 22 Total Equipment 15

Driver 3 2 22

Electrician 2 2 22
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
Rev. 0
Date : May 02th, 2023

DAILY PROGRESS REPORT

Operator Crane 2 2 22

Operator Telehandler 1 1 11

Operator Manlift 1

Operator Boom Truck 1 1 11

Operator Trailer 1 1 11

Operator Concrete Pump 3 3 24

Operator Mixer Truck 4 2 16

TOTAL 207 83 898

2. MAJOR HIGHLIGHT

Tuesday, 02 May 2023 Wednesday, 03 May 2023

ACTIVITY UNIT QTY ACTIVITY UNIT QTY

A. Civil A. Civil

Assembly foundation rebar to Pad C GL 09-10-11 Continue Assembly foundation rebar to Pad C GL 09-10-11

Completion formwork grid 13 - 11 Continue completion formwork grid 13 - 11

Complete Install chair bar to foundation grid 15 - 13 Install chair bar to foundation grid 13 - 11

Start instal chair bar grid 11 - 9

B. Structure : B. Structure :

C. Mechanical : C. Mechanical :

D. Piping : D. Piping :

Prepare welding test piece HDPE pipe Continue Prepare welding test piece HDPE pipe

Prepare roller tools to connect HDPE pipe Continue prepare roller tools to connect HDPE pipe

E. Logistic : E. Logistic :

Unloading tools & equipment to TMF area Continue Unloading tools & equipment to TMF area

F. Scaffold : F. Scaffold :

G. Others G. Others

Online & offline Training Online & offline Training

Produce office furniture & site facilities Continue produce office furniture & site facilities
Concern :
Cast In plate, Embeded plate, Wall rebar not yet arrive at TMF

Discrepency between SCH-R and BOQ EMK (Concrete choke station, Service Trench)

Mechanic for each heavy equipment (Crane 50T brake-down)

Available 2 unit mixer truck from 4 unit required

Need civil manpower inline with rebar material delivery

Prepared by : Checked By : Acknowledged By :

Project Control Site Manager


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Date : May 02th, 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

GENERAL ACTIVITIES

General Pre-start meeting Internal EMK TBM

Safety Reward Internal EMK TBM


CIVIL

Continue install rebar grid 9-10-11 Continue install rebar grid 9-10-11

Continue install rebar grid 9-10-11 Continue install rebar grid 9-10-11
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Date : May 02th, 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

fabrication rebar bender tools Bending ties rebar

Continue produce concrete decking Mobilize starter bar to TMF


Piping

Fabricate support for HDPE roller Fabricate support for HDPE roller
Site Establishment

Finishing toilet Add concrete base PAD C


Prepared by : Approved by :