TAILING MINE FILTRATION PROJECT

Site Installation Civil, Structural, Mechanical & Piping (CSMP)


PT. Agincourt Resources
Rev. 0
Date : May 21th, 2023

DAILY PROGRESS REPORT

0. DAILY PROGRESS & MANPOWER Construction Phase

MANPOWER WORK HOURS RAINFALL RECORD

PLAN ACTUAL ACTUAL ACTUAL


DISCIPLINE/ACTIVITY

Night Day Overtim Night Overtim Night


Day Shift Overtime Day Shift Start End Total Hours Remarks
Shift Shift e Shift e Shift

Direct Labor * 144 38 418

Skilled Worker (Source : Jakarta) 110 38 418

Rebarman 25 13 143

Mason 20 8 88

Carpenter 25 10 110

Fitter 12 2 22

Boilermaker 8 2 22

Pipe Fitter 6

HDPE Piping 4 2 22 OTHER CONDITION

Welder Steel (SMAW+GTAW) 8 1 11


Total
Start End Remarks
Hours
Painter 2

Unskilled Worker (Source : Local) 34

34

Indirect * 65 22 242

Construction Manager 1 1 11 Total Hours :

Site Manager 1 Note :

Planner 1 1 11 Blasting at purnama Pit, all worker evacuate from

Surveyor 2 1 11 TMF area

Field Engineer/Project Engineer 1

HR Staff 3 1 11 EQUIPMENT ON SITE QTY

Civil Foreman 2 1 11

Civil Supervisor 1 Roughter Crane 50 Ton 1

Civil QC Engineer 2 Roughter Crane 90 Ton 1

Civil Superintendent 1 1 11 Boomtruck 15 Ton 1

QC Staff 2 1 11 Concrete Pump 1

Mechanical 6 Mixer Truck 01 1

SMP Foreman 2 1 11 Mixer Truck 02 1

SMP Supervisor 1 1 11 Mixer Truck 03 1

SMP QC Engineer (WI qualification) 2 1 11 Mixer Truck 04 1

Scaffolding Inspector 1 Telehandler 1

Scaffolder 7 5 55 Tractor Head 6X6 1

HSE Supervisor 1 LV 01 (Pajero) 1

Safety Officer 3 1 11 LV 02 Double Cabin 1

Logistic and Warehouse 2 1 11 LV 03 Double Cabin 1

Rigger 3 1 11 Generator 45 kVA 4

Driver 3 1 11 Generator 165 kVA 1

Electrician 2 1 11 Compressor 2

Operator Crane 2 1 11 Total Equipment 20

Operator Telehandler 1

Operator Manlift 1

Operator Boom Truck 1 1 11

Operator Trailer 1

Operator Concrete Pump 3

Operator Mixer Truck 4


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
Rev. 0
Date : May 21th, 2023

DAILY PROGRESS REPORT

PERI UP Supervisor 2

TOTAL 209 60 660

2. MAJOR HIGHLIGHT

Saturday, 20 May 2023 Sunday, 21 May 2023

ACTIVITY UNIT QTY ACTIVITY UNIT QTY

A. Civil A. Civil

Assembly foundation rebar GL -06-05-04 Continue Assembly foundation rebar GL -06-05-04

Start Install formwork GL 13-11 Continue joint survey GL 1,2,3,4,5

Repair formwork for nect pouring Repair formwork for nect pouring

Instal bottom rebar GL 4,3 & Column P3A Continue start bottom rebar GL 4,3 & Column P3A

Assembly PERI UP panel Continue assembly PERI UP panel

B. Structure : B. Structure :

C. Mechanical : C. Mechanical :

D. Piping : D. Piping :

Mobilize HDPE piping material Continue Mobilize HDPE piping material

Joint pipe HDPE filtration feed reach 11 joint 8 Continue Joint pipe HDPE filtration feed

E. Logistic : E. Logistic :

Unloading tools & equipment to TMF area Continue Unloading tools & equipment to TMF area

F. Scaffold : F. Scaffold :

Manpower complete 7

G. Others G. Others

Online & offline Training Online & offline Training

Produce office furniture & site facilities Continue produce office furniture & site facilities

Concern :

Cast In plate, Embeded plate, not yet arrive at TMF

PERI UP material not yet complete

Concreting water stop material for Filtration building not enough (25 meter more)

Local hire need to joint

Potential night shift to catch up schedule


Prepared by : Checked By : Acknowledged By :

Project Control Site Manager


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Date : May 21th, 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

GENERAL ACTIVITIES

General Pre-start meeting Internal EMK TBM


CIVIL

Start install top rebar GL 5 Continue PERI wall panel assembly

Continue install rebar GL 4-5 Install water stop GL 13

Chipping pedestal P6 GL 15 Repair formwork


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Date : May 21th, 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Joint surver after concreting GL 15-13 Joint surver after concreting GL 15-13
Piping

Ongoing pipe HDPE welding Joint preparation HDPE pipe

HDPE pipe joint no 12 Ongoing fit up HDPE pipe


Prepared by : Approved by :