Day Shift Overtime Night Shift Day Shift Overtime Day Shift Overtime Night Shift Start End Total Hours Remarks
Shift
Rebarman 25 23 253
Mason 20 18 198
Carpenter 25 24 264
Fitter 12 5 55
Boilermaker 8 4 44
Pipe Fitter 6 2 22
Indirect * 68 54 567
HR Staff/Administration 2 1 11
HR/Administration 1 1 11
GA & Supporting 1
Administration 1 1 11
Civil Foreman 2 2 22
Civil QC Engineer 2 1 11
Operator Trailer 1 1 11
PERI UP Supervisor 2 1 8
DAILY CUMULATIVE
BALANCE %
ACTIVITY UNIT QTY Variance REMARKS
ACT. COMPLETE
Plan Actual Plan Actual
Construction
Civil Work Percent 100% 0.24% 0.06% 19.2% 9.4% 9.8% 91% 9.40%
Piping Work Percent 100% 0.01% 0.01% 0.49% 0.36% 0.13% 99.64% 0.36%
2. MAJOR HIGHLIGHT
A. Civil A. Civil
Install rebar footing Switch Room Continue install rebar footing Switch Room
B. Structure : B. Structure :
C. Mechanical : C. Mechanical :
D. Piping : D. Piping :
Joint pipe HDPE Field Pipeng & Fitting Ø OSU 400 PN10 Joint 50 Continue Joint pipe HDPE Field Pipe & Fitting Ø OSU 400 PN10
Joint pipe HDPE Field Pipeng & Fitting Ø PSL 400 PN25 Joint 33 Continue Joint pipe HDPE Field Pipe & Fitting Ø PSL 400 PN25
Joint pipe HDPE Field Piping Ø 160 PN10 Joint 68 Continue Joint pipe HDPE Field Pipe & Fitting Ø 160 PN10
Joint pipe HDPE Field Piping Ø 90 PN10 Joint 68 Continue Joint pipe HDPE Field Pipe & Fitting Ø 90 PN10
Joint pipe HDPE Field Piping Ø 63 PN10 Joint 62 Continue Joint pipe HDPE Field Pipe & Fitting Ø 63 PN10
Joint pipe HDPE Field Piping Ø 355 PN16 Joint 17 Continue Joint pipe HDPE Field Pipe & Fitting Ø 355 PN16
E. Logistic : E. Logistic :
Unloading Rebar, tools & equipment to TMF area Continue Unloading Rebar, tools & equipment to TMF area
F. Scaffold : F. Scaffold :
G. Others G. Others
Concern :
DAILY PHOTOGRAPH
PHOTOGRAPH
GENERAL ACTIVITIES
Brushing & cleaning Shear Key rebar Brushing & cleaning Shear Key rebar
SDL 08 semua rebar D25 sama D 29 bang Start assembly bottom rebar footing EMB
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
DAILY PHOTOGRAPH
PHOTOGRAPH
LC Transformer Bay
Piping
DAILY PHOTOGRAPH
PHOTOGRAPH
Laydown & fit up HDPE pipe Laydown & fit up HDPE pipe
Join 17 Dia 355 PN16 PE100 Laydown & fit up HDPE pipe
Join 49 Dia 400 PN10 PE100 Join 50 Dia 400 PN10 PE100
Prepared by : Approved by :
Project Control