TAILING MINE FILTRATION PROJECT

Site Installation Civil, Structural, Mechanical & Piping (CSMP)


PT. Agincourt Resources
Rev. 0
Date : May 30th, 2023

DAILY PROGRESS REPORT

0. DAILY PROGRESS & MANPOWER Construction Phase

MANPOWER WORK HOURS RAINFALL RECORD

PLAN ACTUAL ACTUAL ACTUAL


DISCIPLINE/ACTIVITY

Night Day Overtim Night


Day Shift Overtime Day Shift Overtime Night Shift Start End Total Hours Remarks
Shift Shift e Shift

Direct Labor * 144 76 836

Skilled Worker (Source : Jakarta) 110 76 836

Rebarman 25 22 242

Mason 20 17 187

Carpenter 25 20 220

Fitter 12 5 55

Boilermaker 8 4 44

Pipe Fitter 6 2 22

HDPE Piping 4 4 44 OTHER CONDITION

Welder Steel (SMAW+GTAW) 8 2 22


Total
Start End Remarks
Hours
Painter 2

Unskilled Worker (Source : Local) 34

34

Indirect * 65 54 564

Construction Manager 1 1 11 Total Hours :

Site Manager 1 1 11 Note :

Planner 1 1 11 Manhour use for Recyn Project :

Surveyor 2 3 33 From 8th May to 30th May : 4158 hours

Field Engineer/Project Engineer 1 1 11

HR Staff 3 2 22

Civil Foreman 2 2 22

Civil Supervisor 1 1 11 EQUIPMENT ON SITE QTY

Civil QC Engineer 2 2 22

Civil Superintendent 1 1 11 Roughter Crane 50 Ton 1

QC Staff 2 1 11 Roughter Crane 90 Ton 1

Mechanical 6 1 8 Boomtruck 15 Ton 1

SMP Foreman 2 2 22 Concrete Pump 1

SMP Supervisor 1 1 11 Mixer Truck 01 1

SMP QC Engineer (WI qualification) 2 1 11 Mixer Truck 02 1

Scaffolding Inspector 1 1 11 Mixer Truck 03 1

Scaffolder 7 7 77 Mixer Truck 04 1

HSE Supervisor 1 1 11 Telehandler 1

Safety Officer 3 2 22 Tractor Head 6X6 1

Logistic and Warehouse 2 1 11 LV 01 (Pajero) 1

Rigger 3 3 33 LV 02 Double Cabin 1

Driver 3 3 30 LV 03 Double Cabin 1

Electrician 2 2 22 Generator 45 kVA 4

Operator Crane 2 2 22 Generator 165 kVA 1

Operator Telehandler 1 1 11 Compressor 2

Operator Manlift 1 Total Equipment 20

Operator Boom Truck 1 1 11

Operator Trailer 1 1 11

Operator Concrete Pump 3 3 24

Operator Mixer Truck 4 4 32


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
Rev. 0
Date : May 30th, 2023

DAILY PROGRESS REPORT

PERI UP Supervisor 2 1 8

TOTAL 209 130 1400

1. CONSTRUCTION KEY QUANTITIES (*Plan Based on Work Completion Schedule - WCS)

DAILY CUMULATIVE
BALANCE %
ACTIVITY UNIT QTY Variance REMARKS
ACT. COMPLETE
Plan Actual Plan Actual

Overhead (Indirects)* Percent 100% Monthly Update

On Site Management and Control* Percent 100% Monthly Update

Construction

Concrete Work MH 176,392 882 649 26,247 17,960 8,287 158,432 10.2%

Mechanical Work MH 14,907 14,907

Piping Work MH 18,664 21 231.44 -231 18,433 1.24%

Structural Steel MH 66,497 66,497

2. MAJOR HIGHLIGHT

Tuesday, 30 May 2023 Wednesday, 31 May 2023

ACTIVITY UNIT QTY ACTIVITY UNIT QTY

A. Civil A. Civil

Install stirrup column C1, C2a, C3 Continue 'Install stirrup column C1, C2a, C3

Prepare pouring foundation GL 11-08 m3 Prepare pouring foundation GL 11-08

Completing formwork foundation GL 11 - 08 Completing formwork foundation GL 11 - 08

Next pouring foundation plan 30th May 2023

B. Structure : B. Structure :

C. Mechanical : C. Mechanical :

D. Piping : D. Piping :

Mobilize HDPE piping material Continue Mobilize HDPE piping material

Joint pipe HDPE filtration feed Ø 400 reach 17 joint Joint 17 Continue 'Joint pipe HDPE filtration feed Ø 400

Joint pipe HDPE filtration feed Ø 160 reach 29 joint Joint 29 Continue 'Joint pipe HDPE filtration feed Ø 160

Joint pipe HDPE filtration feed Ø 90 reach 23 joint Joint 23 Continue 'Joint pipe HDPE filtration feed Ø 160

Joint pipe HDPE filtration feed Ø 63 reach 27 joint Joint 27 Continue 'Joint pipe HDPE filtration feed Ø 160

E. Logistic : E. Logistic :

Unloading tools & equipment to TMF area Continue Unloading tools & equipment to TMF area

F. Scaffold : F. Scaffold :

Manpower complete 7

G. Others G. Others

Online & offline Training Online & offline Training

Concern :

Cast In plate, Embeded plate, anchor for pedestal not yet arrive at TMF

Prepared by : Checked By : Acknowledged By :

Project Control Site Manager


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Date : May 30th, 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

GENERAL ACTIVITIES

General Pre-start meeting Internal EMK TBM


CIVIL

Continue PERI wall panel assembly Install handrail GL 8-9-10-11-12.

Cleaning foundation GL 11-08


Piping

Joint 05 pipe HDPE OSU 400 Continue Fit up HDP Epipe


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Date : May 30th, 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Joint 16 HDPE pipe dia 90 Joint 17 HDPE pipe dia 90

Joint 18 HDPE pipe dia 90 Joint 19 HDPE pipe dia 90

Joint 20 HDPE pipe dia 90 Joint 21 HDPE pipe dia 90

Joint 22 HDPE pipe dia 90 Joint 05 pipe HDPE OSU 400


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Date : May 30th, 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Joint 23 HDPE pipe dia 90


Prepared by : Approved by :

Project Control