You are on page 1of 1

EPCC FOR SEWAGE SYSTEM REFURBISHMENT

DAILY PROGRESS REPORT


UBF MAINTENANCE SDN. BHD. PETRONAS CHEMICALS POLYETHYLENE SDN BHD
Project No. : PJM2278/18 Date : 7-Nov-18
Project Title : EPCC FOR SEWAGE SYSTEM REFURBISHMENT Report No. : UBF/PCPSB/2291-18/DPR-001
Location : UBFM YARD & PCPSB PLANT ` Client : PCPSB
Weather : Fine Working Hour : 9 (0800-1800)

No. Of M.Hrs M.Hrs M.Hrs No. Of M.Hrs M.Hrs M.Hrs


PMT Manpower
Man. Today Prev. Acc. Man. Today Prev. Acc.
Project Manager 0 0 0 0 Work Leader 1 9 112 121
Project Engineer 1 8 80 88 Fitter 1 9 56 65
Electrical Engineer 0 0 0 0 Welder 0 0 0 0
QA/QC Engineer 1 8 40 48 Semi Skill 4 36 240 276
Site Safety Supervisor 1 8 80 88 Fire Watcher 1 9 160 169
Site Supervisor 1 8 80 88 Scaffolder 6 54 0 54
Scaffolding Inspector 0 0 0 0 Electrician 0 0 48 48
Scaffolding Supervisor 1 8 16 24

Total 13 117 616 733


Total 5 40 296 336 Grand Total (PMT + Manpower) 18 157 912 1069
Qty Qty Qty Qty Qty %
Equipment & Machinery Daily Usage Qty Today Progress Status
Total Total Today Prev. Acc. Done
Boomtruck 12T 1 1
Site Activities
Lorry 3T 1 0
Welding Set 2 0
T-503 Bagging Area
Portable Genset 2 1
Air Compressor 1 0 Disconnect Cable LGTH 5.00 0.00 5.00 5.00 100.00%
Grinder 2 0 Demolish Existing Piping NOS 4.00 0.00 4.00 4.00 100.00%
Electrical Jack Hammer 2 1 Demolish Existing Pump NOS 2.00 0.00 2.00 2.00 100.00%
Pneumatic Jack Hammer 2 0 Hacking Work M2 4.00 0.00 4.00 0.50 12.50%
High Pressure Washer 1 0 Scaffolding Erection M3 121 0.0 121.00 0.0 0.00%

Qty Qty Qty Qty %


Progress Status
Total Today Prev. Acc. Done
T-850 PCP Area
Shop Activities
Disconnect Cable LGTH 10.00 0.0 10.0 10.0 100.00%
Structure Fabrication PCS 121.00 0.00 0.00 121.00 100.00% Demolish Existing Piping NOS 4.00 0.0 4.0 4.0 100.00%
Piping Fabrication DI 106.00 0.00 0.00 106.00 100.00% Demolish Existing Pump NOS 2.00 0.0 2.0 2.0 100.00%
NDT JOINT 147.00 0.00 0.00 147.00 100.00% Hacking Work M2 18.00 5.0 2.0 7.0 38.89%
Hot Dipped Galvanized PCS 121.00 0.00 0.00 121.00 100.00% Scaffolding Erection M3 593.00 346.0 0.0 346.0 58.35%
Blasting Painting 227.00 25.00 0.00 131.00 57.71%

Today Activities (Shop) Today Activities (Site)


1 Blasting painting work for structure materials. 1 Scaffolding erection for cable laying at T-850 PCP Area.
2 Hacking work for existing pump foundation at T-850 PCP Area.

Tomorrow Activities (Shop) Tomorrow Activities (Site)


1 Continue blasting painting work for structure materials. 1 Continue scaffolding erection for cable laying at T-850 PCP Area.
2 Mobilize scaffolding materials to construct shelter at both areas.
3 Continue hacking work for existing pump foundation at T-850 PCP Area.
4 Hacking work for sump cover at T-503 Bagging Area.

Issue/Remarks (Shop) Issue/Remarks (Site)


1 Air compressor, hose and pneumatic jack hammer were inspected and
mobilized to T-850 PCP Area.

Prepared by : Mohd Aideel Ikraam bin Mansor Checked / Verified by : Ahmad Tazdari