TANK INSTALLATION

DAILY REPORT
PTW n°: CW 00908 Date : 1-May-21
1. Manpower
Personnel On bord in all facilities
POB EPF EFR DGH1 Stand-By Total Incl STB
SAHRAOUI 4 0 0 4
Personnel
Indirect
0 0 0
0 0
0 0
SAHRAOUI 4 0 0 4
Personnel

0 0 0
Direct

0 0
0 0
0 0
Total 8 0 0 0 8
2. Qualifications
Working Stand-By Working Stand-By rental (day) number
Qualification EPF EFR EPF EFR Qualification EPF EPF EFR

1 Labour 4
Team leader
supervisor 1 Backhoe Driver 0
Topographer 1 concrete mixer driver 0
HSSE supervisor 1

3. Activities

Location JC N° Prog % JC Description Activity Description

EPF 1.1 50% Tank foundations (Area1) setting out, excavation , lean concrete, rebars installation, formwork, pouring
concrete

setting out, excavation , lean concrete, rebars installation, formwork, pouring


EPF 1.2 50% Tank foundations (Area2) concrete

EPF 1.3 5% Bund wall ground beam (Area1) setting out, excavation , lean concrete, rebars installation, formwork, pouring
concrete

EPF 1.4 0% Bun wall brick works (Area1) brick wall construction

EPF 1.5 5% Bund wall ground beam (Area2) setting out, excavation , lean concrete, rebars installation, formwork, pouring
concrete

EPF 1.6 0% Bun wall brick works (Area2) brick wall construction

Performed Activities
- Rebars installation for Area 1- Formwork preparation for area 1