Professional Documents
Culture Documents
This subject outlines the procedure for cutting out a section of pipeline when
required. As a standing rule, cold equipment is used at TNPI if cutting into a line
that has been operational.
Cold cuts are performed on the pipeline in order to remove a section of pipe for
new installations of piping or equipment, rerouting the pipeline or to replace
defective pipe sections. No electrical or hot equipment is used.
Before cold cutting can be done, the pipeline section must be shut down, isolated
and drained or purged of product Once the pipeline has been cut open, any
trapped product has been drained and removed and the atmosphere has tested
safe, you can continue with the next portion of the work using power equipment
and/or torches.
Cold cutting on the pipeline will usually be only one part of a larger scope of
work. This procedure, along with procedures covering the other aspects of the
scope of work, such as work area protection and co-ordination of multiple crews
will have to be considered when doing a risk assessment and developing a
written plan or Job Specific Execution Plan.
REFERENCES
ASSOCIATED DOCUMENTS
DEFINITIONS
The Cold Cutting equipment used to cut pipelines are a much larger version of
the simple tool used by plumbers to cut copper pipe.
Competent or Qualified
An appointed, authorized or designated person who has knowledge and
understanding, through experience and training on specific equipment that
is sufficient to meet all job requirements as determined by the employer.
PROCEDURE DETAILS
Site Preparation:
1. The job coordinator will:
a. specify the location at which the cut out is being performed
b. arrange for the required section of pipeline to be exposed
c. schedule downtime through the Products Movement department
d. arrange for isolation of section of line with four nearest block
valves (two each upstream and downstream)
e. arrange for purging of the line or drain down as appropriate.
f. prepare a Job Specific written plan and complete a Risk
Assessment as required.
2. Prepare work site and arrange for equipment to be on site in advance
of the cut out date.
3. Review procedures and job specific execution plan and tour site(s) to
understand specific job requirements.
4. Excavate if required and fence the site if it is to be left unguarded.
Ensure excavation is wide, deep and long enough for adequate work
access. At the cut out points, ensure there is adequate clearance
below the pipeline for the cutter to work. Take into consideration water
accumulation and removal when excavating, prepare excavation
accordingly.
PROCEDURE
Applicable Responsible
Yes/No Person
1)_____ ENSURE all pre-planning is complete.
a. _____ ENSURE all appropriate site preparations are
complete and all required tools and equipment are
available such as:
i. EXCAVATION is complete (COMPLETE Ground
Disturbance Checklist.)
ii. ISOLATIONS (4 valves if possible) is complete.
(COMPLETE Lockout List.)
iii. DRAIN DOWN or PURGING is complete
iv. EQUIPMENT is in place including required
firefighting equipment for contingency plans
v. HOLD a tailgate meeting with all personnel
involved.
ENSURE Safety Supervisor (Safety Watch) is available as per:
Safety Manual: ENSURE all required PPE is being used
ENSURE the atmosphere in the excavation(s) is being continuously
monitored.
ENSURE communication is completed involving all other parties.
2)_____ POSITION tarps and drip tubs under proposed
section(s) of pipe to be cut.
a. _____ ENSURE proper bonding and grounding.
Sometimes it is necessary to cut the piping back further. If this is required, the preferred method
is cold cutting. Hot cutting can be done, but not until the appropriate gas testing is completed.