Professional Documents
Culture Documents
Pipework Maintenance
439
440 Handbook of Piping Design
prevailing conditions i.e. line pressure, temperature, flow medium and pipe material. In a temporary
repair the leak can be sealed in many ways by using specially designed clamps (as shown in Fig.
15.1) of various types to suit varying conditions of repair. The leak may remain suppressed as long
as the gasket withstands line conditions. This temporary repair can be converted to permanent repair
if the clamps are welded in position.
For repairing leaks around threaded joints, the clamp is used in two halves and secured to the pipe
against the leaking joints by clamping bolts while a set of thrust bolts force a ring against a soft
synthetic rubber seal so that the rubber seal goes into the threads, thus stopping the leaks. Many other
similar clamps can be designed with gasket sealing arrangement according to the site requirement.
The portion of the leaking pipe is removed first. Then the fitting is slid over the ends of the pipes to
be joined and secured by tightening clamps and thrust screws. This is made permanent by welding at
the extreme circumferential ends (Ref: Fig. 15.2).
This method has now established its use in running pipeline most efficiently. In gas lines and steam
supply lines it has proved most successful. Therefore, it has become a standard method of repair.
The process involves direct injection of a compound which forms a strong moulding between
flange faces causing the joint leak. The compounds used in this process are thermosetting materials
having characteristics such that they soften when warm and then cure under subsequent heating to
form a tough and permanent seal. This process can be used not only for pipe joint reparis but also for
repair of pin-holes, leaking valve glands and bonnets, etc.
Pipework Maintenance 441
New branch connections are often required in industries. Shut-down of main lines for making branch
connections causes production losses. Therefore, branch connections without shuting down the main
line is of paramount importance. This is generally met by adopting ‘Under-pressure drilling using
specially designed drilling machines available with different cutter sizes.
The technique involves welding of a short branch line to the main line at a location from which
branch has to be taken. The drilling machine is then mounted over the connection fitted with a gate
valve. The drilling operation is then done under full line pressure and the cut-out piece is retained by
the machine. It is removed after completion of drilling operation.
Chemical Cleaning
A large number of chemicals used as cleaners attack on foreign matter such as bacteria and thus
clean the inside surface of the pipe which is fed with the chemical through power or hand operated
mobile units.
Pipework Maintenance 443
Rodding
Minor blockages of drain and sewers are cleared by hand rodding. The equipment consists of
smaller diameter rods and hand ratchet or power operated rod rotator. Power rodding is used for
clearing heavy blockages in water, gas and other pipe lines subjected to hard deposits.
The tools described in connection with repair and cleaning operations are also required by mainte-
nance staff. Additional equipments required are:
(1) Welding and gas cutting machines
(2) Mobile cranes, hand winches, etc.
(3) Electronic/ultrasonic instrucmetns for locating underground pipeline, measuring wall thickness
and detecting leaks in it.
(4) Drilling and tapping machines.
(5) Various pullers, extractors, jacks, etc.
(6) Dewatering pump-set
(7) Walkie-talkie set.
Since a very few moving parts are involved in a pipeline, it does not require much attention. Still
one should not take it for granted that he will get a troublefree operation. The valve glands, flange
joints, etc. may leak; the supports and clamps may get loosen and start vibrating; the pipe may get
corroded internally or externally within a very short time of its commissioning. Therefore, it is
necessary that a scheduled inspection be carried out on the items which may give trouble and a
444 Handbook of Piping Design
logbook maintained for taking necessary preventive maintenance. For every process pipe a check
list may be prepared and hung in the office of maintenance incharge. A check list for such operation
may be prepared as shown in Table 15.1
The jobs carried out in connection with preventive maintenance must be recorded in log book
for future reference. In a pipeline, generally maintenance of leaking valves is a major problem.
Therefore, standard practices followed for replacement of gland packing or gasket of a flanged
joint must be noted serially, operation-wise under a heading ‘Valve Maintenance’, ‘Replacement
of gland packing in running line’; Repair of flange joints, etc. and hung in the office of maintenance
incharge for future guidance of the maintenance staff.