Professional Documents
Culture Documents
:
FOR HOIST & O/H CRANE PAGE : OF
min L=L-A
L < 50' A=3 / 16"
SPAN max Nominal Span L > 50' <100' A=1 /4" 1 / 4" IN 20' - 0"
L=L+A L> 100' A=3 / 8"
+B
STRAIGHTNESS I B = 3 / 8" 1 / 4" IN 20' - 0"
-B
+c
-C
SPAN
D L < 50' D ± 3 / 16"
RAIL-TO-RAIL L > 50', 100' D=±1 /4" 1 / 4" IN 20' - 0"
L >100' D=± 3 /8"
2. Inspection
Straight- Right
ness Left
Right
Elevation
Left
Rail- to- Rail
Remarks
Name
Signature
Date
Form No. : ITR-MCR-001
INSPECTION AND TEST REPORT REPORT NO. :
FOR HOIST & O/H CRANE PAGE : OF
Inspection Result
No. Item to be Checked Remarks
Accept Reject
Tolerance :
Name
Signature
Date
Form No. : ITR-MCR-002
INSPECTION AND TEST REPORT REPORT NO. :
FOR HOIST & O/H CRANE PAGE : OF
Inspection Result
No. Item to be Checked Remarks
Accept Reject
### All restraining devices and braces used for shipment are removed
Bolt and clamps at span, track and rails are correctly torque
7
as requested by the specification
Tolerance :
Name
Signature
Date