Professional Documents
Culture Documents
:
FOR PAD LEVEL
PAGE : OF
(VERTICAL EQUIPMENT)
Tolerance :
0o
8
8 1
Anchor bolt Projection Pad Elev.: Dwg
Dwg :
2
Actual : See table
below 7
270o
90o
Actual : See table
below
3
6
Foundation 4
5
Pad Elevation
No Elevation No Elevation BCD: 180o
1 16 Dwg:
2 17 Actual:
3 18
4 19 Bolt Dimension Check
5 20 No Projection No Projection
6 21 1 11
7 22 2 12
8 23 3 13
9 24 4 14
10 25 5 15
11 26 6 16
12 27 7 17
13 28 8 18
14 29 9 19
15 30 10 20
Name
Signature
Date
Form No.: ITR-MSE-001
INSPECTION AND TEST REPORT REPORT. NO. :
FOR ANCHOR BOLT
(VERTICAL EQUIPMENT) PAGE : OF
Note :
Name
Signature
Date
Form No. : ITR-MSE-002
INSPECTION AND TEST REPORT REPORT. NO. :
FOR PAD
(HORIZONTAL EQUIPMENT) PAGE : OF
Note :
Name
Signature
Date
Form No. : ITR-MSE-003
INSPECTION AND TEST REPORT REPORT. NO. :
FOR PAD LEVEL
(HORIZONTAL EQUIPMENT) PAGE : OF
Dwg:
Act.:
Pad Elevation
No Elevation No Elevation
1 16
2 17
3 18
4 19 Bolt Dimension Check
5 20 No Projection No Projection
6 21 1 11
7 22 2 12
8 23 3 13
9 24 4 14
10 25 5 15
11 26 6 16
12 27 7 17
13 28 8 18
14 29 9 19
15 30 10 20
Tolerance :
Note : Anchor Box Dimension (If applicable)
Inspection Result : □ Accept □ Conditionally Accept □ Reject
Inspection by Subcontractor Contractor Client
Name
Signature
Date
Form No. : ITR-MSE-004
INSPECTION AND TEST REPORT REPORT. NO. :
FOR ANCHOR BOLT
(HORIZONTAL EQUIPMENT) PAGE : OF
Fixed Side
C D
C/Point Drawing Actual Result Remarks
Sliding Side F
A B A
B
C
D
E
E E G F
G
Note :
Name
Signature
Date
Form No. : ITR-MSE-005
INSPECTION AND TEST REPORT REPORT. NO. :
FOR ELEVATION OF HORIZONTAL
VESSEL PAGE : OF
LEVELING WORK
00
Elevation 'X'
Elevation 'X1' Elevation 'X'
Dwg.
Actual: See table
270 900 below
1800
Name
Signature
Date
Form No. : ITR-MSE-006
INSPECTION AND TEST REPORT REPORT. NO. :
FOR ELEVATION OF H/EXCHANGER PAGE : OF
Ele.'X3' 0° Elecation'X2-X2'
Ele.'X2' Dwg
Actual:See table
270° 90° below
Elecation'X2-X2'
Ele.'X1' Dwg
Ele.'X' Actual:See table
270° 90° below
180°
Note :
1. Check nozzle orientation is correct as per the drawing.
2. Check washer wedding is correct as per the drawing.
Inspection Result : □ Accept □ Conditionally Accept □ Reject
Name
Signature
Date
Form No. : ITR-MSE-007
INSPECTION AND TEST REPORT REPORT. NO. :
FOR PLUMB OF VERTICAL
EQUIPMENT PAGE : OF
0°
270°
90°
Note :
1. Check nozzle orientation is correct as per the drawing.
2. Check washer wedding is correct as per the drawing.
Name
Signature
Date
Form No. : ITR-MSE-008
INSPECTION AND TEST REPORT REPORT. NO. :
FOR PLUMB OF VERTICAL VESSEL
(LUG TYPE) PAGE : OF
h 270˚ 90˚
Note :
Name
Signature
Date
Form No. : ITR-MSE-009
INSPECTION AND TEST REPORT REPORT. NO. :
FOR ELEVATION OF
MISCELLANEOUS EQUIPMENT PAGE : OF
Tolerance :
Note :
Name
Signature
Date
Form No. : ITR-MSE-010
INSPECTION AND TEST REPORT REPORT. NO. :
FOR EQUIPMENT INTERNAL PAGE : OF
Tolerance :
Name
Signature
Date
Form No. : ITR-MSE-011
INSPECTION AND TEST REPORT REPORT. NO. :
FOR FINAL INSPECTION
(STATIONARY EQUIPMENT) PAGE : OF
Check the welding, PWHT,NDE have been carried out property and
11
fully documented (If applicable)
Name
Signature
Date
Form No. : ITR-MSE-012A
INSPECTION AND TEST REPORT REPORT. NO. :
FOR FINAL INSPECTION
(STATIONARY EQUIPMENT) PAGE : OF
14 Check the equipment for internal per check list and drawing
Check the earth bosses are connected and in electrical contract with
15
the shell
Name
Signature
Date
Form No. : ITR-MSE-012B
INSPECTION AND TEST REPORT REPORT. NO. :
FOR GROUTING WORK PAGE : OF
3 Formworks
5 Grouting Works
7 Cube sample
a.) 3 Days
b.) 7 Days
c.) 28 Days
Tolerance :
Note :
Name
Signature
Date
Form No. : ITR-MSE-013
INSPECTION AND TEST REPORT REPORT. NO. :
FOR FIRE PROOFING PAGE : OF
- remove grease.oil,scale
Surface
2 -wire mesh
Preparation
-intervals between pins
3 Key coat
6 Top coating
7 Others
Tolerance :
Note :
Name
Signature
Date
Form No. : ITR-MSE-014
INSPECTION AND TEST REPORT REPORT. NO. :
FOR TRAY SUPPORT RING
(ONE-PASS TRAY) PAGE : OF
One-pass Tray
One-Pass Tray
case 1 Downcomer
Downcomer case 2 case 3
Measurement
Measurement Point
Point
Unit : mm
Measurement Measurement
Measure Deviation Measure Deviation
Point Point
1 6
2 7
3 8
4 9
5 10
Tolerance (mm) :
Inside Diameters of column Accep.Tolerance Inside Diameters of column Accep.Tolerance
2.5 and under 2 Over 2.5 & up to 5.5 6
Over 2.5 & up to 5.5 4 Over 8.5 6
Note :
Name
Signature
Date
Form No. : ITR-MSE-015
INSPECTION AND TEST REPORT REPORT. NO. :
FOR TRAY SUPPORT RING
(TWO-PASS TRAY) PAGE : OF
Two-pass Tray
Unit : mm
Measurement Measurement
Measure Deviation Measure Deviation
Point Point
1 6
2 7
3 8
4 9
5 10
Tolerance (mm)
Inside Diameters of column Accep.Tolerance Inside Diameters of column Accep.Tolerance
2.5 and under 2 Over 2.5 & up to 5.5 6
Over 2.5 & up to 5.5 4 Over 8.5 6
Note :
Name
Signature
Date
Form No. : ITR-MSE-016
INSPECTION AND TEST REPORT REPORT. NO. :
FOR TRAY SUPPORT RING
(FOUR-PASS TRAY) PAGE : OF
Four-pass Tray
Case 1 Case 2
Measurement Measurement
Measure Deviation Measure Deviation
Point Point
1 6
2 7
3 8
4 9
5 10
Tolerance (mm)
Inside Diameters of column Accep.Tolerance Inside Diameters of column Accep.Tolerance
2.5 and under 2 Over 2.5 & up to 5.5 6
Over 2.5 & up to 5.5 4 Over 8.5 6
Note :
Name
Signature
Date
Form No. : ITR-MSE-017
INSPECTION AND TEST REPORT REPORT NO.:
FOR TRAY INSTALLATION (2PASS TRAY WITH
SIDE DOWNCOMERS-EVEN NO.) PAGE: OF
Name
Signature
Date
Form No.: ITR-MSE-018
INSPECTION AND TEST REPORT REPORT NO.:
FOR TRAY INSTALLATION (2PASS TRAY WITH
SIDE DOWNCOMERS-ODD NO.) PAGE: OF
Name
Signature
Date
Form No.: ITR-MSE-019