PROJECT AND LOCATION: ZOSCO JOB No:

Replacement of the Oil Metering Facilities with the Associated R-1383 ZOS
Contract No:
Works at Es-Sider Terminal R-1383
Report No.:
08
DAILY PAINTING INSPECTION REPORT SHEET:
1 of 2
JOB DESCRIPTION:
Grit Blasting and application of first coat
ITEM:
36” Pipes, Qty 1
DOCUMENT / DRAWING REFERENCES:
STARTING DATE: Tuesday July 12, 2022
FINISHING DATE: Tuesday July 12, 2022

1. CLIMATIC CONDITIONS 2. SURFACE PREPARATION


TIME 09:00 AM 12:00 PM Description SA2 SA2.5 SA3
AIR TEMP. (°C) 28.3 °C 32.5 °C Surface Cleanliness X
Abrasive Specification
SURFACE TEMP. (°C) 35.9 °C Type: Copper Slag, Grade: 0.5 –2.5mm
RELATIVE HUMIDITY: ROFILE CHECK, Replica tape (Accepted |
%
60.5 % 44.4 % Not accepted)
Accepted
Bresle Patch / Chloride Test
DEW POINT (°C) 19.9 °C 18.8 °C (Accepted | Not accepted)
Accepted

3. COATING
WET
THK. TOTA
MANUFACTURER’S SHADE BATCH APPLICATIO DFT PREV. COAT(S DRY THK. L
DESCRIPTION NO. NO. N METHOD COAT(S) ) COAT(S) DFT
45705 19880 231121339 Airless spray 200-280 140-170
98750 222025298

8450 222016005

VISUAL INSPECTION:

OTHER TESTS / INSTRUMENT USED: DFT METER (for dry film thickness measurements), Wet Film Thickness Gauge,
DEWPOINT METER, Profilometre: Replica tape.

4. DAILY BLASTING EQUIPMENT CHECK


ITEM CONDITION REMARKS / ACTION

-Compressor Good
-Airless painting machine Graco.
-Blasting machine Air blast

CONCLUSION:

ZOSCO Quality Representative PC Quality Representative WOC Quality Representative

:Name :Name :Name

:Function :Function :Function

:Signature Date: :Signature Date :Signature Date:

FORM No. ZOS-QM-F01


PROJECT AND LOCATION: ZOSCO JOB No:
Replacement of the Oil Metering Facilities with the Associated R-1383 ZOS
Contract No:
Works at Es-Sider Terminal R-1383
Report No.:
08
DAILY PAINTING INSPECTION REPORT SHEET:
2 of 2

FORM No. ZOS-QM-F01