You are on page 1of 2

Customer Contract

Location #
Project
Contractor
AREVA T&D Site test record RELAY TEST Doc. Ref.

MBCI01- PILOT WIRE DIFF. RELAY


1. GENERAL DATA AND INFORMATION:
Circuit Ref. Designation
Panel No. Serial No.
Make Model No.
Dwg & Sh No. Aux. Voltage
Flag Type No. of Contacts
Stabilizing resistor

2. MECHANICAL CHECKS AND VISUAL INSPECTION:


ITEM DESCRIPTION CHECKED
1 Inspect for any physical damage or defects.
2 Verify connections as per approved drawings.
3 Check that serial no. of relay matching with serial no. of case.
4 Relay CT shorting function checked.
5 Test switch checked for correct function.
6 Final set value of stabilizing resistor is set.

3. ELECTRICAL TESTS:
3.1 RELAY BURDEN:
Nominal DC
Condition Relay DC voltage Relay DC current Remarks
current
No operation 15mA
175mA for 48/54V
Operation
90mA for 110/125V

3.2 PICK UP TEST:


(Operation Values Without Pilots) ---Setting: Rpp = 5x100, Ks = 1, Kt = 20, N = 3.
Operating Calculated Actual Operating Value (A) Time at 5 x Pickup in mS
Phase
Value Value (A) Pick-up (A) Reset (A) Pick-up (mS) Reset (mS)

R–N 0.5 x 19% In

Y–N 0.5 x 25% In

B–N 0.5 x 33% In

R–Y 0.5 x 80% In

Y–B 0.5 x 100% In

B-R 0.5 x 44% In


Note: pickup current should be +/- 10% of calculated value.

Test performed by Test witnessed by Date of test


AREVA T&D
Name MUSTAFA HAJI

Signature
Customer Contract
Location #
Project
Contractor
AREVA T&D Site test record RELAY TEST Doc. Ref.

MBCI01 – PILOT WIRE DIFF. RELAY


3.2 PICKUP TEST (CONN..):
(Operation Values Without Pilots) ---Setting: Rpp = 5x100, Ks = 1, Kt = 20, N = 6.
Operating Calculated Actual Operating Value (A)
Phase
Value Value (A) Pick-up (A) Reset (A)
R–N 0.5 x 12% In

Y–N 0.5 x 14% In

B–N 0.5 x 17% In


Note: pickup current should be +/- 10% of calculated value.
3.3 TIMIG TEST:
Current Actual Operating Time at Multiples of KT in milliseconds
Phas
=5x
e 3 6 14 20 40
Pick-up
R– Typical 300 90 65 50 30
N Actual

4. FUNCTIONAL TEST:

Item Description Checked

1 All output contacts resistance measured.


2 LED operation checked.

Test performed by Test witnessed by Date of test


AREVA T&D
Name MUSTAFA HAJI

Signature