Professional Documents
Culture Documents
Doc
METHOD STATEMENT FOR
No.
REFRIGERANT COPPER PIPE
INSTALLATION
Rev.:
Date:
Page:
TABLE OF CONTENTS
1.0 PURPOSE:........................................................................................................................................ 3
2.0 SCOPE:............................................................................................................................................. 3
3.0 LOCATION:....................................................................................................................................... 3
4.0 REFERENCES:................................................................................................................................. 3
5.0 DEFINITIONS/ABBREVIATIONS:.................................................................................................... 3
6.0 RESPONSIBILITY............................................................................................................................. 4
7.0 MATERIALS/EQUIPMENT:............................................................................................................... 5
8.0 WORK PERMITS............................................................................................................................... 5
9.0 SEQUENCE OF WORKS & METHODOLOGY.................................................................................5
10.0 HEALTH, SAFETY AND ENVIRONMENTAL ASSESSMENTS.......................................................6
11.0 QUALITY ASSURANCE AND CONTROL........................................................................................ 7
12.0 JOB HAZARD ANALYSIS................................................................................................................ 7
1.0 PURPOSE:
Document Title
Doc
METHOD STATEMENT FOR
No.
REFRIGERANT COPPER PIPE
INSTALLATION
Rev.:
Date:
Page:
2.0 SCOPE:
.
3.0 LOCATION:
4.0 REFERENCES:
5.0 DEFINITIONS/ABBREVIATIONS:
6.0 RESPONSIBILITY
The primary responsibility of carrying out all the activities mentioned in this method statement
rests with the site in charge unless mentioned otherwise.
Will directly supervises site team and has full control over site foremen and equipment and is
responsible to control the site quality during the work progress.
6.6 SURVEYOR
Will be responsible for survey of the whole project
7.0 MATERIALS/EQUIPMENT:
Drill machine
Hammer
Measuring Tape
Level Instrument
Copper Pipe Cutter
Flaring Tool kit & Manifold Gauges
Vacuum Pump
Screw Driver
Crimping Tool
Rivet Gun
All necessary work permits will be obtained prior to the commencement of any activity at site and
will remain valid throughout the entire duration of the operation.
9.0 PROCEDURE
Apply vapor barrier coating on thermal insulation surfaces as adhesive for canvas cloth. If
found any leak, apply second coat.
The insulated copper pipe should then glass coated and identification marking for copper
piping shall be made.
RFI should be raised and relevant inspection shall be made for QP QA/QC Engineer.
Applying Flux: The flux used for brazing copper joints are different in composition from
soldering fluxes. They cannot and should not be used interchangeably.
Brazing Flux: Brazing flux are water based. Similar to soldering fluxes, brazing fluxes
dissolves and remove residual oxides from the metal surfaces, they protect the metal
surfaces from deoxidation during heating and they promote the wetting of the surfaces to be
joined by the brazing filler metal. Fluxes also provides the craftsman with an indication of
temperature. If the outside of the fitting and the heat affected area of the tube are covered
with flux, it prevents oxidation and greatly improve the appearance of the joints
Brazing Filler Metals: There are two general types of brazing filler metal used for joining
copper tube; BcuP (Brazing-copper-Phosphorus) and Bag (Brazing-Silver). These brazing
filler metals are classified according to their components.
BaCuP Filler Metals: BaCuP Filler metals are preferred for joining copper tubes and
fittings. The phosphorus in these filler metals act as a fluxing agent and the lower
percentage of silver makes them relatively low-cost filler metal. When using copper tub,
wrought copper fittings and BCUP brazing filler metals, fluxing is an option due to the self-
fluxing action of the phosphorus present in all component of the brazed joints
Heating: Oxy/fuel torches are generally used brazing because of the higher temperature
required. Due to recent innovation in air/fuel torch tip design, they can now be used on a
wider variety of size for soldering and brazing. When working with high temperature, safety
precaution must be followed and care must be taken to protect both the technician and the
material being used. For the heating operation, first preheat the tube and then the tube and
fitting. When the brazing filler metal starts to melt, apply these of the fitting socket to help
draw the brazing filler metal in by capillary action
Applying Brazing Filler Metal: One thing remembers to allow the heat of the joint to melt
the filler metal, Do not melt the filler metal with the torch. The melted filler metal will be
drawn into the joint by capillary action. It is very important that the flame be in continuous
motion and should not be allowed to remain on any one point long enough to burn through
the tube or fitting. When the joints are complete, a continuous filler should be visible
completely around the joint. If the filler metal fails to flow, or has the tendency to ball-up, it
indicates oxidation on the melted surfaces or insufficient heat on the part to be joined. If the
Filler metal refuse to enter the joint and tend to flow over the outside of either part of joint, it
indicated that this part is overheated or that part is under-heated.
Cooling and Cleaning: When the joint is complete, allow to be cool naturally. Flux residues
can be removed by washing with hot water and brushing with a stainless-steel wire brush.
Before commencing any work, it shall be ensured that all permits are valid until the completion of
activity.
Scaffolding access shall be provided to the excavation area.
All staff and workmen shall wear Personal Protective Equipment.
Tool box meetings shall be conducted on every day before the start of the work.
Both Safety Officer and Worksite Supervisor to be present at site, full time.
Experienced personnel shall be deployed for the work.
In a situation where the work involves night shift, Contractor will ensure that there are no
obstructions to the work & appropriate site clearance and lighting is available to carry out the
scheduled works.
Document Title
Doc
METHOD STATEMENT FOR
No.
REFRIGERANT COPPER PIPE
INSTALLATION
Rev.:
Date:
Page:
Muster point shall be free from all form of obstruction and shall have enough lighting during the
period of work. All work access must be free from obstruction. Alarm system shall be in good
condition. Emergency plan and evacuation shall be included in daily Tool box talk. First aid
facilities shall always be available. Periodic test or practice of emergency evacuation shall be
conducted.
Emergency contact details for key personnel who have specific roles or responsibilities under the
emergency plan, for example fire wardens, floor wardens and first aid officers.
Contact details for local emergency services, for example police, fire brigade and poison
information Centre shall be displayed at all notice boards
Emergency signage shall be provided and shall be self-explanatory.
Sufficient lighting shall be provided for all operations, no exceptions are to be made. Any personnel
working outside the illuminated area shall be directed to return to a lighted area or the operation
shall be stopped.
All work vehicles, including heavy equipment like wheel loader, compactor, backhoe loader, etc. are
required to have working headlights and taillights respectively. Vehicles without appropriate
lighting should be kept out from working.
Due to limited visibility at night, a signaller should be mandatory for all reversing operations.
Any stockpiles or equipment parked in the construction area should be delineated with safety
cones.
No worker shall be required or knowingly permitted to work in unsafe place, unless for the purpose
of making it safe and then only after proper precautions have been taken to protect the employee
while doing such work.
Construction areas, rest areas and storage areas etc. shall be illuminated.
Proper sign boards, lighting, barricades shall be made available at site for smooth workflow.
All personnel shall be cautioned while working near the pipes/cables.
Temporary sheds shall be provided to workers while working at site.
All equipment shall be provided with reverse horns.
Health and safety risk assessments shall be as per attached JHA.
Personal Protective Equipment (PPE) Requirement
Hard hat
Safety Shoes
Safety Eye glasses
Hand gloves
High visibility vest.
Red, green flags
Document Title
Doc
METHOD STATEMENT FOR
No.
REFRIGERANT COPPER PIPE
INSTALLATION
Rev.:
Date:
Page:
Coverall