You are on page 1of 13

jabāconsult

jabā Management Consultants

PROJECT PROGRESS REPORT


As of October 17, 2018

Project Name: TIM HORTONS VISTA MALL STA. ROSA


Address: Santa Rosa – Tagaytay Rd, Don Jose, Sta. Rosa, Laguna

Project Team:
Project Owner: TH COFFEE SERVICES PHILS, CORP.
Ar. Joseph LemuelRaz, Jr. (Project Director)
Ar,Michelle Ferrer (Project Engineer)
Ar. Alvin Tejada (APTCS)

Designer: MEONADA DESIGN


Ar. Jose Mari Meonada

Project Management: JABA MANAGEMENT CONSULTANTS


Engr. Noel Gazmen (Project Manager)

General Contractor: Aytonaby Inc.


Gene Thomas Pascual

Supply Chain Rossinee Collado


Technical Buyer – Supply Chain

Mechanical Contractor: TBA

Aircon Contractor: SAMSUNG


Louie

Data/Tel Contractor: TBA

GAS Contractor: Island Gas

3/F #7 Santan St. Samama Phase 2 Brgy. Napindan, Taguig City 1630
Tel. No.: (02) 624 0476 • Mobile No.: 0917 8603399/ 0920 9584487
jabāconsult
jabā Management Consultants

RAW MILESTONE DATES


Construction Period: September 24, 2018 to November 7, 2018
Construction Duration: 45 days
Completion Date: November 7, 2018
To Date Construction Days: 24 days
OSM Deliver Schedule: See attached file
Walk-in Chiller Delivery: TBA
Midway Punchlist: TBA
Testing and Commissioning: TBA
Final Punchlist: TBA
Joint Inspection with LL: TBA
Turnover to THCSP: TBA

Note: Punchlist schedule to be finalized


Since ACU and Exhaust/Freshair ducts are still unknown to when will it mobilize, delay will drag the construction
duration to 55 Days.
With the additional Ceiling design, this will not be fabricated yet due to the unavailability of the installed FCU units
of the Air-conditioning units.
For Back of the house wall tiles at wet areas cannot be installed yet due to the pending Wall Mounted FCU
(unavailability of Samsung Contractor) Drain location.

PROGRESS ACCOMPLISHMENT:
See attached Project Gantt Chart

EXECUTIVE SUMMARY:
Item Issue/ Update Status/ Remarks
Fitout Works c/o Aytonaby Chalk Line Approved by MND
Double wall Hollow Blocks at
perimeter area, see pictures
Materials Hollow Blocks, Cement, Sand, Re
bars
Building Permit For Architectural Blue Prints not yet signed by TH
For MEPF Mechanical permits still pending o
the signature
Electronics permits not yet Signed
Building Permits Forms At hand, Electronics permits at TH
Barangay Permits Autorization Letter of TH, given last
10/09/2018 – Done
Certificate of Tenancy, hard copy
given 10/10/2018 – Done
Demolition works Entrance at All Day Done, With framing already
Board up at Mall Side Tarpaulin still in used Done. 10/1/2018
Cement Plastering On Progress At 90%
Column Board up On Progress Already with framing
Tiling works Mall Entrance Side On going
3/F #7 Santan St. Samama Phase 2 Brgy. Napindan, Taguig City 1630
Tel. No.: (02) 624 0476 • Mobile No.: 0917 8603399/ 0920 9584487
jabāconsult
jabā Management Consultants

MEPF
Samsung have an ocular on Friday,
September 28, 2018
Mechanical - ACU No Contractor Yet
Quotation submitted by Samsung
10/17/2018.
No DP yet on the contractor.
Mechanical – Exhaust/Fresh air Metrophil Mobilization Still unknown.
No Update on TH and Supply Chain
Pending Approval of TH
Feeder Line ( Quotation at PHP
Change Request already at TH, for
Electrical c/o Aytonapy 945,000,000.00 )
Signature
Blueprints Electrical plans already on site.
Unitized Panel For finalization c/o Mic & Jad
Key Plans for Electrical Location was finalized as per
October 2, 2018 email of Ar. Mic.
Site Visit on 10/18/2018 c/o Loui
Cold Room ( Walk In Freezer &
AJC No Update on Delivery and
Chiller )
Installation
Structured Cabling, CCTV and BGM JPCA To start mobilization on 10/19/2018
Plumbing Waste & Soil 80 % done
Water Line 50 % done
Gas c/o Island Gas for supply and install ( To be visit on
10/18/2018 )
Sprinkler c/o Aytonaby Blueprint at the Site
Fdas c/o Torque Builders Fdas plan already emailed, waiting
for quotation.

BULLETIN(S) AND CHANGE ORDER(S):


Items Details Remarks
Chalk line Less 1 on the seats at Banquette See attached approval
seats
Construction meeting Every Wednesday of the week Attendance are as follows:
a. TH Project Engineer
b. Aytonapy
c. Jaba
d. Mechanical Contractor
e. Freshair/Exhaust
Contractor.
f. IT Contractor.
Blueprints of MEPF Updated Plans is still at Designer Already with Aytonaby.
Building Permits Mechanical Permit Not yet Signed. No Mechanical
contractor yet given by TH
Electronics Permit Not yet signed,
Main entrance door flooring Floor level at mall area as By Ar, Mic
reference.
Flooring Covering Plan
Speaker Location Acknowledge by Aytonaby and for
Key Plans
Emergency lights Location installation.
Flytraps
3/F #7 Santan St. Samama Phase 2 Brgy. Napindan, Taguig City 1630
Tel. No.: (02) 624 0476 • Mobile No.: 0917 8603399/ 0920 9584487
jabāconsult
jabā Management Consultants

Wall Finishes
Ceiling Design See pictures below Additional Works, for Quotation.
Electrical Outlets Relocation for Managers See attached photo
Room.
Main Entrance Door Relocation of Main glass door will As per Ar. Mic
not push through. Minimize
additional cost

PROGRESS PHOTOS:

Peninsula Area

3/F #7 Santan St. Samama Phase 2 Brgy. Napindan, Taguig City 1630
Tel. No.: (02) 624 0476 • Mobile No.: 0917 8603399/ 0920 9584487
jabāconsult
jabā Management Consultants

Managers Room

3/F #7 Santan St. Samama Phase 2 Brgy. Napindan, Taguig City 1630
Tel. No.: (02) 624 0476 • Mobile No.: 0917 8603399/ 0920 9584487
jabāconsult
jabā Management Consultants

Chiller Area

Comfort Room

3/F #7 Santan St. Samama Phase 2 Brgy. Napindan, Taguig City 1630
Tel. No.: (02) 624 0476 • Mobile No.: 0917 8603399/ 0920 9584487
jabāconsult
jabā Management Consultants

Oven Side

Glass Door for All Day.

3/F #7 Santan St. Samama Phase 2 Brgy. Napindan, Taguig City 1630
Tel. No.: (02) 624 0476 • Mobile No.: 0917 8603399/ 0920 9584487
jabāconsult
jabā Management Consultants

Column Board up

3/F #7 Santan St. Samama Phase 2 Brgy. Napindan, Taguig City 1630
Tel. No.: (02) 624 0476 • Mobile No.: 0917 8603399/ 0920 9584487
jabāconsult
jabā Management Consultants

Electrical

Electrical Feeder line access

3/F #7 Santan St. Samama Phase 2 Brgy. Napindan, Taguig City 1630
Tel. No.: (02) 624 0476 • Mobile No.: 0917 8603399/ 0920 9584487
jabāconsult
jabā Management Consultants

Plumbing

3/F #7 Santan St. Samama Phase 2 Brgy. Napindan, Taguig City 1630
Tel. No.: (02) 624 0476 • Mobile No.: 0917 8603399/ 0920 9584487
jabāconsult
jabā Management Consultants

Mall side entrance

3/F #7 Santan St. Samama Phase 2 Brgy. Napindan, Taguig City 1630
Tel. No.: (02) 624 0476 • Mobile No.: 0917 8603399/ 0920 9584487
jabāconsult
jabā Management Consultants

Ceiling Design

3/F #7 Santan St. Samama Phase 2 Brgy. Napindan, Taguig City 1630
Tel. No.: (02) 624 0476 • Mobile No.: 0917 8603399/ 0920 9584487
jabāconsult
jabā Management Consultants

3/F #7 Santan St. Samama Phase 2 Brgy. Napindan, Taguig City 1630
Tel. No.: (02) 624 0476 • Mobile No.: 0917 8603399/ 0920 9584487

You might also like