ONGOING TSS WORKS CIRCLE WISE

Sr. Name of Date of Likely date of Status


No Transmission Line award / completion
Contractual
completion
date
TS CIRCLE PANCHKULA
NIL
TS CIRCLE KARNAL
NIL
TS CIRCLE ROHTAK
1. Creation of 132 KV 2 08.10.18 / 04.02.19 Stub setting: 5/7 No.
phase line on D/C 04.02.19 Tower erection: 5/7 No.
towers from 132 KV Stringing: 0/ 1.566 KM
S/Stn. GSS Chandi to  Route of the work approved
132 KV S/Stn. TSS by the competent authority
Kharanti.
Stub setting of TL No 3, 4,
W.O. No: 65/218
dated 08.10.2018 5, 6 and 7 Completed.
Contractor: M/s  Erection work of TL No 3, 4,
Himani Enterprises. 5, 6 and 7 Completed
Dist: Rohtak  Work at TL No 1 and 2 was
Funding: Deposit work started with the help of
Police & Distt Administration
but has been stopped by
land Owner and Kisan
Union in lieu of demand of
higher compensation.
 Naib Tasildar Meham is
appointed as Duty
magistrate by DC Rohtak.
TS CIRCLE FARIDABAD
NIL
TS CIRCLE GURUGRAM
2. 132 kV S/C line from 17.06.16/ 31.03.2019 Progress:
220 kV S/Stn. Lula 16.07.17  Foundation- 47/47
Ahir to 132 kV TSS on  Erection-41/47.
D/C towers at  Stringing- 0.03/10.64 KM.
Jatusana (Between gantry and TL-1)
Turnkey contractor:
M/s Arcon Engicon Impediment:
Ltd.  Inadequate manpower &
Contract awarded on: resources with the firm.
17.06.2016  In spite of several
Funding agency: correspondences from
REC-150 Xen/SE/CE TS & meetings,
Length of line: 10.625 the progress has been
Km. dismally slow.
No of location: 47 MOM: Director Projects
Nos. (24.11.2016), CE TS
Cost (In Lacs): 520.00 (09.08.2016, 4.01.2017,
Planning Code 18.03.2017, 31.03.2017,
1D2181* 13.1.2019), CE/TS &
CE/MM (17.12.2018).

 Part /short material about


10% is balance.
TS CIRCLE HISAR
3. Construction of 2 07.09.16/ 31.03.2019 Stub setting:- 90/118
phase 132 kV S/C line 06.06.17 Tower erection:- 53/118
on D/C towers with 0.4 Stringing: Nil
Sq ACSR conductor Work allocated to M/s Fedders
from 132 kV S/Stn., Lioyd Ltd. vide contract No –
Kalanaur to 132 kV HDP-2145 & 2146/ REC-159 /
TSS Manheru. XEN / Project (TL) dated
Funding : REC-159 26.08.2016.
District: Bhiwani
Contractor: M/S Work progress remained
Fedders Lloyd Ltd. intermittent and remained
Line length – 30 Km stopped for 3 to 4 months and
Total Location – 126 work was restarted by the firm
Cost (In Rs. Lacs): on dated 24.04.2018. Work is
1090 slow on part of M/s Fedders for
Planning Code want of construction material
1D2832* and labour issues.
Presently the work is totally
held up from last 3 months.
M/s Fedder in meeting dated
17.12.2018 has assured to
restart the work in 1st week of
Jan 2019 but firm yet not
start the work.
Case has been sent by the
field office for termination of
work.
4. LILO of 132kV line 04.05.18/ 15.02.2019 Stub setting:- 07 / 07 No
from 220kV BBMB 03.02.19 Tower erection:- 0 / 07 No
Hisar – 132kV Hansi Stringing: 0 / 1.2 KM
Ckt - 1 at 132kV TSS (conductor)
Satrod and raising 0/ 1.8 KM (Cable)
and shifting of 132kV
BBMB Hisar – Hansi Work is very slow on part of the
Ckt – 2. Contractor. Being perused
Funding : Deposit regularly for timely completion
work of RVNL (REC- as per schedule.
204)
District : Hisar
Contractor : M/s
Aquarian Enterprises
Line length – 3.237
KM
Cost(In Rs. Lacs) :
503.00

5. LILO of 132kV Bhuna 15.05.18/ 31.03.2019 The route of laying


– Ukala line at 132kV 14.02.19 underground cable re-
TSS Uklana. submitted by the contractor on
Funding : Deposit 12.12.2018 and same has been
work of Railway approved on dated 21.12.2018
(REC-201) & sent for consent of Railways
District : Fatehabad and same has been consented
Contractor : M/s by Railway authorities and
Raychem RPG received on dated 23.01.2019.
Line length – 1.40 + Further, it was intimated by the
0.77KM firm that 50% material of
Cost(In Rs. Lacs) : Gantry tower & stub has been
161.00 received at site, left out
material and cables will be
supplied by 15.02.2019.
Supply through solid T-OFF has
been given to Railways on
dated 29.08.2018.