OVERNMENT OF TELANGANA

KRIGATION & CAD DEPARTMENT


To:
Sri.P.Madhusudhan Reddy, B.E,
From: M/s.Standard Infratech India Pvt Ltd
Plot No 10&46, MIG2,
ExecutiveEngineer,
Sangareddy. gth Phase, KPHB Colony, Hyderabad
Irigation Division No. 1,

EE/B/SRDDBHD/ 45
Dated: 24/202|L.
Lr. No.
Check dam across Manjeera River
Sir.
Sub:- Minor Irrigation NSP-Construction of
Letter for delay in execution of work -
near, Panyala (V), Hathnoora (M) -
Reg.
Dt: 06.02.2019 of Superintending
Ref: 1. L.S.Agreement No. 47/2018-19,
Engineer, Irrigation Circle, Sangareddy
Lr.No.EEIB/SRD/DB/HD/DI/1169, Dt:1.10.2019.
2. T.O.
3. Your Letter Dt:05.10.2019 to this office.
4. T.0. Lr.No.EE/IB/SRD/DB/HD/309, Dt:12.06.2020.
5. Your Letter Dt:22.06.2020 to this office.
******
Manjeera
It is to submit that, the work "Construction of Check dam across
you vide
River near, Panyala (V), Hathnoora (M" agreement was concluded by
reference 1" cited for an amount of Rs.68.09 Lakhs with a stipulated period for
completion of the work by 9 months i.e.upto 06.11.2019. But as on today you have
completed only 45% of the work and now the work is in stand still condition. Through
reference 2nd &4th reference cited, already notices was issued toyou to start the work
within three days but you have not resume the work.

Hence a final notice is herewith issued and instructed to resume the balance
work immediately, and complete the work immediately, otherwise action will be
initiated as per codal rules.
Yours faithfully,

Executive Enginêer.4l2o2 I
ele Irrigation Division No.1,
1) Copy submitted to
Superintending Engineer, Irrigation
Sangareddy,
of information and
necessary action. Circle, Sangareddy for favour
2) Copy toDy.Executive Engineer,
I.B.Sub-Division, Sangareddy for information,