Budget works ongoing

AS Details TS Details Work Arrangement Work Status


Sl.No Name of work Amount T.S No. Agt.No & Date Agreed. PAC Name of Current Stats of work Physical
Contractor Progress (%)

Vallikunnu LAC
1 Improvements and and providing BM & BC 175 ORDER SE(K) 09/2019- 16143863 Jabir Usman Culvert and drain completed, GSB ,WMM BM 75%
works to Idimuzhikkal -Agrasala Parakkadavu No.KTY/2018- 20 Dtd: completed.BC rectification pending. Awaited for
road (Reach-II) road between km 1/150 and 3/000 2019/2018/10620D 20/05/2019 favorable weather condition. Work delay due to
in Vallikkunnu LAC ated:18-01-2019 rain.
2 Budget Work 2018-19: Improvements and 100 ORDER EE(M)289/201 8595968 Abdul BM completed and BC 70m pendind due to ROW 90%
providing BM & BC works to Idimuzhikkal- No.KTY/2018- 8-19 dtd Kareem.K.K work in progress. To be completed after rain.
Agrasala- Parakkadavu road (Reach II) between 2019/2018/3354Da 25.02.2019 Awaited for favorable weather condition. Work
km 0/000 to 1/150 in Vallikkunnu LAC ted:12-01-2019 delay due to rain.
Kondotty LAC
3 Budget Work 2018-19: Improvements and 200 MNJ/2018-19 SE(K)237/2018 1,84,87,723 Jabir usman Drainage and cross drain works ,GSB,WMM,BM 80%
providing BM & BC works to Murivayikkal- /2018/7475 -19 Dated 6-03- completed . BC pending. Awaited for favourable
Vallikkad road between km 0/000 and 2/250 in 2019 weather condition. Work delayed due to rain.
Kondotty LAC
4 Providing BM & BC surfacing and other 75 MNJ/2018- EE(M)288/201 6785442.47 Jabir Usman Drainage and cross drain works 80%
improvement works to Murivayikkal Vallikkad 19/2018/10522 8-19 dtd completed .GSB,WMM,BM completed. BC
road between Km 2/250 and 3/200 in Kondotty 25.02.2019 pending. Awaited for favourable weather
LAC condition.
5 Improvements and providing BM & BC Works to 500 RE Work arranged. Pipe line pending. _
Kottappurani Kakkancheri road between _TS/RD/2021/1773 SE(K)52/2021 Ms
KM 0/000 and 5/300 in kondotty LAC _5_1 Dated: 31-05- -22 dated: MALABAR
2021 13.09.2021 39802388 TECH
6 Improvements and providing BM and BC to 200 ORDER SE(K)117/2020 16479217 Aranjikkal Drain, Culvert, Retaining wall works 57%
Mangattumuri- Cherumuttam - Valiyaparamba No.RdDnMNJ/202 -21 dtead 03- Group of Completed.Profile Correction works completed
road b/w km 0/450 and 2/750 0-2021/RD/2020/9 02-2021 constructions shifting utilities completed. Pipe line laying
54Dated:08-10- pending
2020

Ernad LAC
7 Improvements and providing BM and BC works 1200 RdDnMNJ/2020- SE(K)148/2020 96471156 Thrimathy out of 20 Culvert reconstruction,15 was 19%
to SH - 65 Parappanagadi Areacode road between 2021/RD/2020/531 -21 dated 26- Contracting completed ,3 are on going and two are pending
Ekkaparamba and Areacode kn km 28/670 to dated 24-10-2020 02-2021 company due to water logging .Around 1100.00 m of drain
41/060 (excluding km 31/500 to km 32/330) in is completed .450.00 m of retaining wall works
Ernad LAC also completed.Drain and retaining wall works
are ongoing,
Survey work for boundary demarkation also in
progress
FLOOD WORKS 2020-21

Amount
Name of
Sl No LA Constituency Name of work (Rs. in Agreement no & date Agreed PAC Present Status
Contractor
lakhs

Side protection wall damaged in omanoor kuzhimanna road EE (M) 87/2020-21


1 Eranad 25 1824192.48 Abdul Kareem KK work completed
Km 8/000 to 9/000 Dated.19-02-2021

Side protection wall damaged in teacherpadi-muthuvallor road EE(M)73/2020-21 Work started, stream flow is hindering
2 Eranad 25 1723488.79 Abdul Kareem KK
km 0/000 to 0/500 Dated:10/02/2021 the work progress

Re construction of damaged culvert in teacherpadi-muthuvallor EE(M)72/2020-21


3 Eranad 25 1824655.36 Basheer K work completed
road at km 0/050 Dated:10/02/2021

Side protection wall damaged inPonnad Vazhakkad Road in EE(M)25/2021-22 dated


4 Kondotty 25 1877440 Abdul Kareem KK Work completed
between Km 1/200 29-06-2021

Side protection wall damaged inVettukad olavattoor AEE(T)39/2020-21


5 Kondotty 12 500816 Rasak work completed
mundumuzhi Road in between Km 6/100 to 6/400 5/11/2020
Partial construction of Culvert and Drainage in Kondotty
EE (M) 70/2020-21
6 Vallikkunnu Tirurangadi Diversion Road route-2 between km 0/450 to 20 1882333.49 Abdul Kareem KK work completed.
Dated.01-02-2021
1/850
Flood Damage Works 2020-21: Providing side protection work
AS accorded , submitted for
7 Kondotty at Km 1/200 to km 1/800 of Ponnad vazhakkad road in 30
nomenclature change
Kondotty LAC
DETAILS OF NON PLAN WORK 2021-2022
Non Plan works Ongoing
Amount
(Rs. in Agreed PAC Name of
Sl No LA Constituency Name of work lakhs Agreement no & date Contractor Present Status
FDR-2021-22-Reconstruction of retaining wall in farook
Collage vazhakkad road between ch 4/950 and 5/700-
General Civil Work-at kondotty lac
EE(M)36/2021-22 Muhammad
1 Kondotty 15.5 Dated:08/09/2021 1064615 Shameem T started
FDR-2021-22-ReConstruction of retaining wall in
Vettukad Olavattur Mundumuzhy road btwn km 3/700 & Muhammad
EE(M)35/2021-22
2 Kondotty 4/200-General Civil Work-at kondotty Lac 25 Dated:08/09/2021 1711214 Shameem T on progress
Urgent side protection work between km 0/800 and 1/300
of Pallippuraya-Puthiyedathuparambu road in Kondotty 1708960 Muhammad Abdul
EE(M)51/2021-22
3 Kondotty LAC 25 Dated:01/10/2021 Basheer Agreement executed
Protection Works to Mangattumuri cherumuttam yet to be submitted for
4 Kondotty valiyaparamb road between 0/600 and 2/540 25 TS
M/s.SALMANUL
Urgent Construction of Culvert at 0/400 of Mangattumuri AEE(T)49/2021-22 dt 488522.21 HARIS
5 Kondotty Cherumuttam Valiyaparambu road 5 23/09/2021 on progress
Urgent Drainworks to murivazhikkal-vallikkad road AEE(T)50/2021-22 dt 485484 M/s.Mohammed
6 Kondotty between km 1/700 and 2/100-General Civil Work 5 25/09/2021 Shabas C T completed
Road safety Work 2020-21 (Non Plan Work ) :Providing
Sign boards to kondotty -vazhakkad road ( From km
10+600 to 17+100) and Farook College-Vazhakkad Road AEE(T)/40/2021-22 dt 667654
7 Kondotty (From km 4+300 to 11+720 8.45 13/07/2021 Niyazi Haneefa ongoing
Sri. Basheer.K
DETAILS OF NON PLAN WORK 2020-21
Amount Koodamthodi
LA (Rs. in Name
houseof
Sl No Constituency Name of work lakhs Agreement no & date Agreed PAC Contractor
Vavoor Present Status
SLTF 2020-21 : Surface rectification works of service road at Cheekode.(PO)
Ugrapuram of Areecode Vazhakkad road between 19/000 and
19/500 at Eranad Lac EE(M)76/2020-21 dated Malappuram,Pin:
1 Ernad 25 16/02/2021 2163249.6 673645 work completed
Providing BM & BC and other improvements works to Feroke M/s PMR
K.K.
College Vazhakkad road between 1/500 to 4/300 Construction
P.M.R
Aboobacker Survey sketch awaited.Dranage works and Protection work are in progress.30 %
SE(K)144/2020-21 dated: Company,
Haji,, PMR of work is completed , Surfacing work canm be completed only after JJM pipe
CONSTRUCTI
2 Kondotty 300 24-02-2021 23378821.6 Arcade,
ONS
PWD trenches were restored. Survey completed. eMB pending
Melmuri,
Contractor,
SLTF 2020-21 : Urgent Water logging rectification works to Alathoorpadi,
Padinharayil
Feroke College Vazhakkad road between Km 11/400 and 11/700 EE(M)100/2020-21 dated Malappuram
House
3 Kondotty at Kondotty LAC 25 24-02-2021 2446338 676517
M/s PMR ,
Kodangad Culvert &b drain completed. Gsb and wmm alaying work on progress
Construction
Kondotty (PO) -
SLTF 2020-21 : Urgent BT repair and maintanance Works to AEE(T)18/2021-22 Company,
673638PMR BT Work Completed, for Surfacing with Interlocks at mundumuzhy jn Gsb
4 Kondotty Kondotty Vazhakkad road 10/600 - 17/100 10 dt.28/06/2021 968698.84 Arcade,
Malappuram laying work on progress
Melmuri,
M/s PMR
SLTF 2020-21 : Urgent work for Restoration of traffic due to Alathoorpadi,
Construction
collapsed culvert at 6/200 and drainage work in Feroke College EE(M)102/2020-21 dated Malappuram
Company, PMR
5 Kondotty Vazhakkad road between km 2/800 and 11/400 in Kondotty LAC 25 24-02-2021 2228547 676517
Arcade, Work in progress 30% work completed
Melmuri,
SLTF 2019-20 : Urgent flood damage rectification work between Alathoorpadi,
Km 0/670 and Km 2/500 of Faroke College Vazhakkad road in EE(M)105/2020-21, dated Malappuram
6 Kondotty Kondotty LAC 25 25-02-2021 2447080 P.P.676517
Noushad work in progress
Ali, PWD
SLTF 2020-21 Rectification Works between km 3/700 and 4/490
Contractor
of kannamvettikkav - puthupadam-Ayikarappadi-kakancheri road
Pulikkal
7 Vallikkunnu in Vallikunnu lac 45 MT
Palekode(H) Submitted LETTER OF ACCEPTANCE
Nediyiruppu
SLTF 2020-21 : Eviction works to various roads under roads AEE(T)03/2021-22 (PO) 673 638,
10 Vallikkunnu section kondotty in kondotty, vallikunnu,eranad,malappuram lac s 5 Date :17-06-2021 352452 Kondotty Work in progress. Eviction in process
SLTF 2020-21 :Rectification Works between km 0/000 and 0/450
of Diversion road to kondotty -thirurangadi road route II in EE(M)108/2020-21 dated
11 Vallikkunnu Vallikunnu lac 25 26-02-2021 2232078 Zubair work completed

SLTF 2020-21 : Rectification Works between km 7/650 and 8/100


of Kohinoor Puthurpallikkal kumminiparambu Tharayittal road in M s MALABAR
12 Vallikkunnu Vallikunnu LAC 25 2424897 TECH Submitted LETTER OF ACCEPTANCE

SLTF 2020-21 : Rectification Works between km 2/800 and 3/200


of kannamvettikkav - puthupadam- Ayikarappadi- kakancheri road MALABAR
13 Vallikkunnu in Vallikunnu lac 25 2450158 TECH Submitted LETTER OF ACCEPTANCE
SLTF 2020-21 : improvements Works to Idimuzhikkal - Agrasala
- Parakadavu road (Reach I) btwn km 3/000 and 4/500 in EE(M)83/2020-21
14 Vallikkunnu Vallikunnu LAC 25 Dated:17/02/2021 1925288 KABIR NAHA Work started. Drain in progress

SLTF 2018-19 (Flood damage): Providing BM &BC surfacing


from km 3/000 to km 3/500 in Idimuzhikkal-Agrasala-Parakadavu BM work completed . BC work half portion completed. 80 % completed.Road
15 Vallikkunnu road (Reach II) 30 3293665 marking works are pending