Attendance:
NWSDB
T Suthakaran - PM (CE)
A D N C Madushanka - Engineer (CE)
K D S T Silva - Engineer (CE)
Madusha Tissera - Engineer (CE)
Noufal - Engineer (CE)
Contractor
M S Pinto - DPM
Jung byoung ok - Construction Team Leader
Youmg Ho Bay - Design Manager
E S Mark - Design Engineer
S. Vigneshwaran - Engineer
D Chamara - Engineer
Indunil Samarakkody - Engineer
E M D A Jayathilaka - Engineer
A A M Rizan - Engineer
Page 1 of 4
Item Description Action
No. By
Minutes of previous Progress Review Meeting no 103 were agreed and signed.
01 Overall Progress, DMA and FM progress
Refer Annex - 1
02 Gothatuwa Jublee System and the Relevant DMAs (Back Feeding from Jublee)
DMA 30A – Additional pipe laying roads flushing is in progress KCG DMA in charge agreed to complete all the
balance works by 10th September 2020.
DMA 30B – Locked for initial NRW, house connections inspection with O and M is in progress and construction
site visit to be arrange after completing the defects and advance copy of as built drawing is under PIU
review to arrange O and M site visit ASAP. Lake Drive PVC connection transferring is in progress
DMA 30C – As built drawing key plan is under PIU review.
DMA 30D – Flushing is remaining and KGC DMA in charge agreed to complete all the balance works by 10th
September 2020.
DMA 25 – Cotta road section and Eliot place system pressure preparation ongoing, house connection transfer in
possible roads is in progress, Decommissioning valves are closing one by one by informing to O and
M. KGC house connection in charge agreed to complete all the HC transferring work by 15th
September 2020. RDA approval for Cotta Road balance pipe laying is pending.
FM - Advance copy of as built drawing submitted on same day and O and M site visit to be arrange
accordingly. Official request to proceed the Gothami road 600mm dia. DI culvert crossing has been
sent to KGC.
Page 2 of 4
03 Maligakanda System 2 and the Relevant DMAs
DMA 23B – Balance pipe laying in school lane, Flushing and meter transferring in Dematagoda road are
in progress, Siri Dhamma Mw meter transferring is ongoing. KGC DMA in charge agreed
to complete the balance pipe laying within the same week.
DMA 23A- DMA in charge of KGC agreed to completet Pipe laying in Marudana road,
Abeyagunawardana Mw by following Friday. Deans road pipe laying and pressure testing
in Vajiranantha mawatha and house connections works are in progress,
- Marudana road crossing is ongoing.
- Anantha Mawatha balance section permission is yet to be obtained.
- KGC, DPM agreed to send handing over letters to Temple road and Sarath Fenseka
Mawatha within couple of days.
FM - 500 mm DI BV to be installed to manage the flow and pressure and he interruption will be
arranged on 12th September 2020 at night.
04 Gothatuwa System and the Relevant DMAs (Back Feeding from Maligaganda)
DMA 18 – Decommissioning to be started, Approval for C.W.W. Kannangara Mawatha is in progress,
key plan submitted to CMC Drainage division.
DMA 17A - Balance pipe laying and pressure testing is in progress KGC, DMA in charge agreed to start
the pipe laying along Abeyagunawardana and Marudana road on following day.
- Getting approval for Balance section of Deans road and T.B. Jaya mawatha is in progress
DMA 17B - Balance pipe laying along Anantha Rajakaruna Mawatha and pressure testing is in progress,
flushing, disinfection and house connection transfer is in progress. DMA in charge of KGC
agreed to complete 315mm dia. HDPE pipe laying by 15th September 2020.
DMA 17C - Balance pipe laying and pressure testing is in progress, this DMA is temporarily feeded, so
flushing, disinfection, house connections works to be started accordingly.
- Getting permission for Vipulasena Mawath, De Seram road Hedgest court, Piyathasa
Srisena Mawatha and Balance section of Madudana road is in progress (estimate to be paid,
Millimg and overlaying will be done by CMC)
DMA 28B - This DMA to be temporarily feeded in Sri Mahinda Darma, Kent road and Aramaya Place.
- Action to be taken to feed Dematagoda place from DMA 23B through emergency feeder.
All other DMAs Balance pipe laying and pressure testing is in progress (DMA 28A, 29A, 29B and 24).
FM - 800 mm DI laying is in progress at Anantha Rajakaruna and Trial excavation inside the
Maligakanda yard has been completed and KGC feeder main in charge agreed to complete the
800 mm DI yard piping by 15th September 2020 by deploying two teams.
- Balance portion of sewer line is yet to be removed at Canal road at Lesli Ranagala junction.
- Trial excavation for Neegrodarama Bridge crossing is in progress.
- Pressure testing for balance portion of 1000mm DI at Pelangasthuduwa is ongoing.
Page 3 of 4
- 400 DI laying is in progress along Dean’s road
- 500mm DI and 400mm DI pressure testing is to be started from J D fernanado Mw to
Dematagoda road (FM at DMA 28B).
- 500 mm DI laying along Linsy Ranagala Mawatha is in progress
- 600mm Moragsmulla balance laying is to be started.
…………………………… ………...........................
Eng. T. Suthakaran Eng. Jeong Goan U
Project Manager, (CN/CE) Project Manager/Contractor Representative
NWSDB Kolon Global Corporation
Page 4 of 4