System Rehabilitation for NRW Reduction in South Part of Colombo City

Summary of Man Power Detail for Site Works


Date : 27-Apr-2021

Man Power Machineries


Sub Contractor
Day / Location /
No. Name of the road Type of Work / Fitter / Fusion Remarks
Night DMA Labour Excavator JCB Asphalt Cutter Compactor Generator
Direct Team Skill labour Machine

Day 1 Kirulapone Bridge (1 Gang) FM Piling Work For Bridge Crossing Sub 2 3 - - - - - 1

Day 2 WijayaKumarathunga Mawatha FM Cold Mix FM-D02-FM-D03 - - - - - - - - Cancelled


Day 3 Thalakotuwa Garden (1 Gang) 33D Water Filling Direct - 2 - - - - - -

Day 4 Alexandra Road 38A House Connection Stage 1 Sub 1 4 1 - - 1 1 1

Day 5 42nd Lane (1 Gang) 38B House Connection Stage 1 Sub 1 2 1 - - 1 1 1

Day 6 42nd Lane (1 Gang) 38B Compaction Test 38B-D30-38B-D31 Sub - 1 - - - - - -

Day 7 Roxy Garden By Road (1 Gang) 38B Interlock Paving Sub - 3 - - - - - -

Day 8 Adamaly Place (1 SMA Group) 35C Pipe Laying 35C - D35 - 35C - D35B Sub 1 3 1 - - 1 1 1

Day 9 Buchanan Street (1 SMA Group) 35C Pipe Laying 35C - D28 - 35C - D28B Sub 2 13 1 - - 1 1 1

Day 10 Beltona Lane (1 SMA Group) 35C Pipe Laying 35C - D25 - 35C - D25A - - - - - - - - Continued from night site
Day 11 Dharmarama 3rd Lane 37A Pressure Testing Direct - 3 - - - - - -

Day 12 Rohini Road 37A Pipe Laying Direct 1 6 1 - 1 1 1 1

Day 13 Peterson Lane by road 37A Pressure Testing Direct - 1 - - - - - -

Total Man Power 8 41 5 0 1 5 5 6

Sub Contractor 7 29

Direct Team 1 12