Project Name: Construction of one floor vertical Extension (3rd Floor)

Project Phase: Finishing


Site Engineer: Md. Asraful Hoque
Weather Condition: Sunny

Manpower Allocati
Sr. No. Task Name: Masonry Carpentry Rebar Concrete
M H M H M H M

Surface Preparation For Tiles Work


1 - 2 - - - - -
Scaffolding For Exterior Wall Plaster
2 2 2 - - - - -
Ti;ing Work in Corridor
3 - - - - - - -

4 - - - - - - -

5 - - - - - - -

6 - - - - - - -

7 - - - - - - -

8 - - - - - - -

9 - - - - - - -

10 - - - - - - -
TOTAL MANPOWER COUNT: 2 4 0 0 0 0 0
#Special Instructions:

#Additional Notes: 1.Metal anchor for tower & Ac outdoor Platform MS A


2.Electrical Cable & Board or all sort of cable need to r
3.Safety Measures shall follow during Exterior Plaster
Prepared By: Checked By:
UCEP GAZIPUR TVET INSTITUTE
North Salna, Gazipur.

Manpower Allocation Challenges/


Achievemets/
Concrete Electrical Tiling Painting Plumbing Issues/Area of
Progress
H M H M H M H M H Concern

- - - - - - - - -

- - - - - - - - -

- - - 2 3 - - - -

- - - - - - - - -

- - - - - - - - -

- - - - - - - - -

- - - - - - - - -

- - - - - - - - -

- - - - - - - - -

- - - - - - - - -
0 0 0 2 3 0 0 0 0

Ac outdoor Platform MS Angle Frame required to remove as early as possible.


r all sort of cable need to remove .
ow during Exterior Plaster Work
Authorized By:
Date: 1/1/2024
Shift: 8:00 AM-05:00 PM
*M= Mason
*H= Helper

Upcoming Activities Comments

AC Outdoor Replacing in
Rooftop

Steel Shed Installtion

Exterior Wall Plastering

Electrical Work

Thai-Aluminum

Tiles

Louver

Parapet Wall-B/W

uPvc Door Installation

Septic Tank & Soak-Well

You might also like