Professional Documents
Culture Documents
A Head Work 0
A Head Work
1 Land Acquisition - - - - - -
2 Earthwork - - - - - -
4 concrete - - - - - -
R
TO
5 Others - - - - - -
C
SE
L
B Canal System - - - - - -
A
C
LO
1 Land Acquisition - - - - - -
TO
R
VE
2 Earthwork - - - - - -
O
D
DE
3 Structure - - - - - -
N
A
H
T
C
C Rehabilitation - - - - - -
JE
O
PR
1 Families Displaced - - - - - -
2 Rehabilitations Sites - - - - - -
3 Compensation - - - - - -
D Miscelleneous - - - - - -
E ETP - - - - - -
Total - - - - - - - - - - - - - -
Name of Project:- Lower Dnyanganga-II (St.) Tal. Khamgaon Dist.:- Buldana ( Rs. in Crores)
Expen- Quarterwise Target and Achievement in 2021-22 Quarter
Ist Quarter Ending IInd Quarter IIIrd Quarter IVth Quarter Expenditure in Ending
diture
Sr. Component of Updated Balance Target for June 21 Ending Sept 21 Ending Dec 21 Ending March 22 2021-22 up to Cumulative Remark
upto
No. Project Cost Cost 2021-22 SEPT -21 Expenditur s
March
2021 Target Achieved Target Achieved Target Achieved Target Achieved (8+10+12+14) e (Col
4+15)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
A Head Work
1 Land Acquisition 83.76 78.14 5.62 1.00 - 0.51 - - 0.50 - 0.50 - 0.51 78.65
3 Masonry - - - -
- - - - - - - - - -
1 Land Acquisition - - - - - - - - - - - - - -
2 Earthwork - - - - - - - - - - - - - -
3 Structure - - - - - - - - - - - - - -
C Rehabilitation - - - - - - - - - - - - -
-
1 Families Displaced - - - - - - - - - - - - - -
2 Rehabilitation Sites - - - - - - - - - - - - - -
3 Compensation - - - - - - - - - - - - - -
D Miscelleneous - - - - - - - - - - - - - -
E ETP - - - - - - - - - - - - - -
Total 163.26 156.87 6.39 1.00 - 0.72 - - 0.50 - 0.50 - 0.72 157.59
Name of Project:- Durgabori (St.) Tal. Mehakar Dist.:- Buldana ( Rs. in Crores)
A Head Work
2 Earthwork - - 14.43
14.43 14.43 - - - - - - - - -
3 Masonry - - -
- - - - - - - - - - -
4 concrete - - 3.98
3.98 3.98 - - - - - - - - -
B Canal System - - - - - - - - - - - -
Storage Tank -
1 Land Acquisition - - - - - - - - - - - -
- -
2 Earthwork - - - - - - - - - - - -
- -
3 Structure - - - - - - - - - - - -
- -
C Rehabilitation - - - - - - - - - - - -
No Rehabilitation -
1 Families Displaced - - - - - - - - - - - -
- -
2 Rehabilitation Sites - - - - - - - - - - - -
- -
3 Compensation - - - - - - - - - - - -
- -
D Miscelleneous - - - - - - - - - - - -
- -
E ETP - - - - - - - - - - - -
- -
A Head Work
3 Masonry - - - - - - - - - - - - - -
1 Land Acquisition - - - - - - - - - - - - - -
2 Earthwork - - - - - - - - - - - - - -
3 Structure - - - - - - - - - - - - - -
C Rehabilitation No Rehabilitation - - - - - - - - - - - - -
1 Families Displaced - - - - - - - - - - - - - -
2 Rehabilitations Sites - - - - - - - - - - - - - -
3 Compensation - - - - - - - - - - - - - -
D Miscelleneous - - - - - - - - - - - - - -
A Head Work
Required
1 Land Acquisition 22.3400 22.3400 - - - - - - - - - - - 22.34 land for
rehabilitatio
n proposed
2 Earthwork 5.80 5.80 - - - - - - - - - - - 5.80 to
purchased
3 Masonry 0.02 0.02 - - - - - - - - - - - 0.02 directly.
B Canal System - - - - - - - - - - - - - -
C Rehabilitation - - - - - - - - - - - - - -
1 Families Displaced - - - - - - - - - - - - - -
2 Rehabilitations Sites 22.22 8.53 13.69 7.43 0.48 0.48 0.77 - 2.33 0.00 3.85 - 0.48 9.01
D Miscelleneous - - - - - - - - - - - - - -
Total 59.96 45.00 14.96 8.20 0.48 0.48 0.77 - 2.33 - 4.62 - 0.48 45.48
Name of Project :- Lonwadi Tq.Nandura Dist.Buldana ( Rs. in Crores)
Expen- Quarterwise Target and Achievement in 2021-22 Expenditure in Quarter
Sr. Component of Updated diture Balance Target for Ist Quarter Ending IInd Quarter IIIrd Quarter IVth Quarter 2021-22 up to Ending Remark
No. Project Cost upto Cost 2021-22 June 21 Ending Sept 21 Ending Dec 21 Ending March 22 SEPT -21 Cumulative s
March Expenditur
Target Achieved Target Achieved Target Achieved Target Achieved (8+10+12+14)
2021 e (Col
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
A Head Work
3 Masonry - - - - -
- - - - - - - - -
B Canal System - - - - -
- - - - - - - - -
i.Land Acquisition 6,034.99 2,379.65 3,655.34 446.05 100.00 35.98 100.00 69.48 100.00 - 146.05 - 105.46 2,485.11
ii.Rehabilitation 724.45 108.09 616.36 75.00 20.00 9.81 20.00 9.60 20.00 - 15.00 - 19.41 127.50
a.Excavation 317.30 259.70 57.60 57.60 15.00 12.00 15.00 4.00 15.00 - 12.60 - 16.00 275.70
b.Embankment 131.29 101.00 30.29 30.29 7.00 5.00 7.00 2.00 7.00 - 9.29 - 7.00 108.00
iv).Spillway - - - - - - - - - - - - - -
a) Colgrout 154.51 149.51 5.00 5.00 1.50 8.00 1.50 5.00 1.50 - 0.50 - 13.00 162.51
b) Concrete 146.31 141.31 5.00 5.00 1.50 12.12 1.50 5.30 1.50 - 0.50 - 17.42 158.73
c) Gate 68.06 66.35 1.71 10.00 2.50 - 2.50 - 2.50 - 2.50 - - 66.35
C. LIS 1 TO 12 - - - - - - - - - - - - - -
i.Civil Protion 1,374.93 853.29 521.64 30.00 7.00 18.03 7.00 26.97 7.00 - 9.00 - 45.00 898.29
ii. Mechnical Portion 261.66 2.29 259.37 45.00 12.00 - 12.00 - 12.00 - 9.00 - - 2.29
iii. Electrical Portion 299.59 103.85 195.74 41.00 10.00 - 10.00 - 10.00 - 11.00 - - 103.85
E Miscelleneous 1,212.86 476.72 736.14 40.00 10.00 - 10.00 - 10.00 - 10.00 - - 476.72
TOTAL Work Portion 8,654.96 784.94 186.50 100.94 186.50 122.35 186.50 - 225.44 - 223.29 4,865.05
13,296.72 4,641.76
F ETP 415.92 24.00 6.00 4.19 6.00 5.21 6.00 - 6.00 - 9.40 171.35
577.87 161.95
Grand Total 13,874.59 4,803.71 9,070.88 808.94 192.50 105.13 192.50 127.56 192.50 - 231.44 - 232.69 5,036.40