Day 5 Rajaguru Sri Subodhi Road (1 Gang) 37D House Connection S2 37D-D10-37D-D16 Sub 1 1 1 - - 1 - 1
Day 8 Pamankada Road (1 Gang) FM Cold Mix Paving For Damaged Sewer Line Direct 1 3 - - - 1 1 1
Day 9 Balapokuna Purana Vihara Mawatha 33B House Connection 33B-D26-33B-D32A Direct 1 5 1 - - 1 1 1
Day 10 By Road at Canal Road (1 SCLC Group) 33C Pipe Laying 33C-D19-33C-D60 Direct 1 4 1 1 - 1 - 1
Day 11 By Road at Canal Road (1 SCLC Group) 33C Pipe Laying 33C-D19-33C-D60 - - - - - - - - Cancelled
Day 12 By Road at Canal Road (1 SCLC Group) 33C Pipe Laying 33C-D17-33C-D63 Direct 1 4 1 1 - 1 - 1
Day 15 Mugalan Road (1 SCLC Group) 33C Permenent Reinstatement 33C-D30-33C-D34 Sub 1 4 - - 1 1 1 1
Day 17 Darmarama Lane (Sun Power Group) 37A Pipe Laying & Valve Fixing 37A-D48-37A-D48A Direct 1 2 1 - 1 1 1 1
Day 18 Kelankaduwa Place (Sun Power Group) House Connection 37A-D46-37A-D46B Sub - - - - - - - - Same team in Item 16
Day 19 Galle Road By Lane (Sun Power Group) Tapping T Test Sub - - - - - - - - Same team in Item 16
Day 20 Galle Road By Lane (Sun Power Group) Tapping T Test Sub - - - - - - - - Same team in Item 16
Day 21 Rohini Road (Sun Power Group) 37A Pipe Laying Direct 1 5 1 - 1 1 1 1
Sub Contractor 9 42
Direct Team 9 43