ASHOKA BUILDCON LIMITED

Sheopur Kalan Gwalior GC Project


DPR SUMMARY
PROGRESS UP TO DATE 29-08-2023
This Month Quantity
Sl. Upto Last
Activity Unit During This Upto Date Remarks
No. Todays Achievement Upto Yesterday Month
Month

A Railway Embankment work


1 Clearing & Grubbing (C&G) Sqm 1,960 25,170 27,130 - 27,130
2 Excavation Cum - - -
3 Embankment in Filling Cum 250 520 770 - 770
4 Blanketing layer Cum - - -
5 Ballast laying Cum - - -
6 Track Laying RMT - - -
7 Tree Cutting Nos. - - -
8 Hectometer stone fixing Nos. - - -
9 Rail Dismantling RMT - 11,515 11,515 - 11,515
10 Sleeper shifting Nos. - - -
11 Rail shifting RMT - - -
12 Embankment in Cutting Cum - - -
13 ROW Trenching Work RMT - 6,375 6,375 38,430.0 44,805.0
14 Tree Measurement Nos. - - - 1,414.0 1,414.0
15 Geotech Work RMT -
16 Labour Nos. - 28 28 131.0 159.0

B Camp Establishment -

PLINTH CONSTRUCTION
1 Excavation Cum - 42.59 42.59 - 42.585
2 PCC Cum - 4.732 4.732 - 4.732
3 UCR masonary Cum - 28.480 28.480 - 28.480
4 Murrum filling Cum 12.182 34.555 46.736 - 46.7
5 Rubble soling Cum - - - - -
6 Coping Cum -
7 Pointing Sqm -
WEIGHT BRIDGE
1 Excavation Cum - 7.92 7.92 - 7.920
2 Rubble soling Cum - 2.20 2.20 - 2.200
3 RCC M20 Cum
PROGRESS UP TO DATE 29-08-2023
This Month Quantity
Sl. Upto Last
Activity Unit During This Upto Date Remarks
No. Todays Achievement Upto Yesterday Month
Month
4 RAMP FILLING Cum
Fenching Work -
1 Excavation Cum - 10.26 10.26 - 10.260
2 M10 Concrete For PIT Cum - 10.26 10.26 - 10.260
3 Angle Fixing Nos - 190.00 190.00 - 190.000
Batchmix Plant Establishment
1 Excavation Cum 35.16 - 35.16 - 35.16
2 PCC Cum - - - -
Sheopur Kalan GC Project
DATE: 29.08.2023
Dept. Labour Utilization Details
Date Utilization for work Name of contractor Unskilled Activity details
1-08-2023 QA /QC Departmental 2
10-08-2023 Store Department Departmental 6 Barbed wire and angle post unloading
11-08-2023 Store Department Departmental 6 Barbed wire and angle post unloading
12-08-2023 Store Department Departmental 5 weigh bridge unloading
14-08-2023 Store Department Departmental 7 batching plant and bundlekhand expressway site material unloading
23-08-2023 Store Department Departmental 2 Batching plant Silo

159
Weather Report
Date Climate Rainfall (mm) Remarks

01-08-2023 light Rainfall 2.1


02-08-2023 Light Rainfall 3.4
03-08-2023 Heavy Rainfall 26
04-08-2023 clear
05-08-2023 Light Rainfall 4.8
06-08-2023 Light Rainfall 3.4
07-08-2023 clear
08-08-2023 clear
09-08-2023 clear
10-08-2023 clear
11-08-2023 clear
12-08-2023 clear
13-08-2023 clear
14-08-2023 clear
15-08-2023 clear
16-08-2023 clear
17-08-2023 clear
18-08-2023 Light Rainfall 5
19-08-2023 Light Rainfall 5.8
20-08-2023 Light Rainfall 4.2
21-08-2023 Light Rainfall 5.3
22-08-2023 Light Rainfall 5.7
23-08-2023 clear
24-08-2023 clear
25-08-2023 clear
26-08-2023 clear
27-08-2023 clear
28-08-2023 clear
29-08-2023 clear
ASHOKA BUILDCON LIMITED

Sheopur Kalan Gwalior GC Project DATE:- 29-08-2023

Daily Progress Report (Highway)


Chainages
Date Name of contractor Items Side No Length  Width Depth   Quantity Unit Remarks Received Qty.(MT)
From To
Tree Cutting

Departmental Tree Cutting Nos.


0

Tree Measurement

1414
C&G

4-08-2023 J P Infra Clearing & Grubbing 177+800 177+850 1 50 25 1250 Sqm


23-08-2023 J P Infra Clearing & Grubbing 177+660 177+820 1 160 20 3200 Sqm
24-08-2023 nihan infa Clearing & Grubbing 172+970 173+150 1 180 21 3780 Sqm
24-08-2023 J P Infra Clearing & Grubbing 177+610 177+660 1 50 22 1100 Sqm
25-08-2023 J P Infra Clearing & Grubbing 177+820 177+940 1 120 20 2400 Sqm
26-08-2023 J P Infra Clearing & Grubbing 177+940 177+980 1 40 24 960 Sqm
26-08-2023 J P Infra Clearing & Grubbing 177+980 178+140 1 160 24 3840 Sqm
27-08-2023 J P Infra Clearing & Grubbing 178+140 178+230 1 90 24 2160 Sqm
28-08-2023 J P Infra Clearing & Grubbing 178+230 178+500 1 270 24 6480 Sqm
29-08-2023 J P Infra Clearing & Grubbing 178+500 178+570 1 70 28 1960 Sqm

27130
Embankment
28-08-2023 J P Infra 1st layer 178+000 178+200 1 200 12.5 0.208 520 Cum 520
29-08-2023 J P Infra 1st layer 177+720 177+800 1 80 12.5 0.25 250 Cum
770 cum
Excavation for Trenching Work
1-08-2023 MAA SATI CONSTRUCTION ROW Trench Excavation 183+750 183+970 RHS 220 0.45 0.75 74.3 Cum
8-08-2023 MAA SATI CONSTRUCTION ROW Trench Excavation 187+830 188+030 LHS 200 0.45 0.75 67.5 Cum
9-08-2023 MAA SATI CONSTRUCTION ROW Trench Excavation 187+400 187+800 LHS 400 0.45 0.75 135.0 Cum
1no jcb
9-08-2023 MAA SATI CONSTRUCTION ROW Trench Excavation 188+090 188+200 LHS 110 0.45 0.75 37.1 Cum
ADDITIONAL HIRE JCB @ 1000 Rs/
9-08-2023 ROW Trench Excavation 188+090 188+200 RHS 110 0.45 0.75 37.1 Cum
hr approved
Total = 3.25 hours
ADDITIONAL HIRE JCB @ 1000 Rs/
9-08-2023 ROW Trench Excavation 187+700 187+780 RHS 80 0.45 0.75 27.0 Cum Anil Gupta
hr approved
10-08-2023 MAA SATI CONSTRUCTION ROW Trench Excavation 186+750 187+400 LHS 650 0.45 0.75 219.4 Cum 1 no jcb
ADDITIONAL HIRE JCB @ 1000 Rs/
10-08-2023 ROW Trench Excavation 186+850 187+295 RHS 445 0.45 0.75 150.2 Cum Total = 6.06 hours Anil Gupta
hr approved
11-08-2023 MAA SATI CONSTRUCTION ROW Trench Excavation 186+050 186+750 LHS 700 0.45 0.75 236.3 Cum 1 no jcb
ADDITIONAL HIRE JCB @ 1000 Rs/
11-08-2023 ROW Trench Excavation 186+150 186+850 RHS 700 0.45 0.75 236.3 Cum Total = 7:48 hours Anil Gupta
hr approved
12-08-2023 MAA SATI CONSTRUCTION ROW Trench Excavation 185+580 186+050 LHS 470 0.45 0.75 158.6 Cum 1 no jcb
ADDITIONAL HIRE JCB @ 1000 Rs/
12-08-2023 ROW Trench Excavation 185+950 186+150 RHS 200 0.45 0.75 67.5 Cum Anil Gupta
hr approved
Total = 2:54 hours
ADDITIONAL HIRE JCB @ 1000 Rs/
12-08-2023 ROW Trench Excavation 185+300 185+400 RHS 100 0.45 0.75 33.8 Cum Anil Gupta
hr approved
14-08-2023 MAA SATI CONSTRUCTION ROW Trench Excavation 181+850 182+500 RHS 650 0.45 0.75 219.4 Cum 1 no jcb
16-08-2023 MAA SATI CONSTRUCTION ROW Trench Excavation 182+050 182+500 LHS 450 0.45 0.75 151.9 Cum 1 no jcb
ASHOKA BUILDCON LIMITED

Sheopur Kalan Gwalior GC Project DATE:- 29-08-2023

Daily Progress Report (Highway)


Chainages
Date Name of contractor Items Side No Length  Width Depth   Quantity Unit Remarks Received Qty.(MT)
From To
17-08-2023 MAA SATI CONSTRUCTION ROW Trench Excavation 181+870 182+050 LHS 180 0.45 0.75 60.8 Cum 1 no jcb
17-08-2023 MAA SATI CONSTRUCTION ROW Trench Excavation 181+400 181+810 RHS 410 0.45 0.75 138.4 Cum 1 no jcb
18-08-2023 MAA SATI CONSTRUCTION ROW Trench Excavation 181+350 181+650 LHS 300 0.45 0.75 101.3 Cum 1 no jcb

44805 15064
ASHOKA BUILDCON LIMITED

Sheopur Kalan Gwalior GC Project DATE:- 29-08-2023


Daily Progress Report Plinth Construction
Chainages
Sr.no Date Name of contractor Items Side No Length  Width Depth   Quantity Unit Remarks Received Qty.(MT)
From To
Excavation Not Started

1 8-08-2023 bharat bricks Industries Excavation for Site office Building 1 65.06 0.65 0.675 29 Cum
2 8-08-2023 bharat bricks Industries Excavation for Lab Building 1 32 0.65 0.675 14 Cum

42.59
PCC

1 9-08-2023 bharat bricks Industries PCC FOR SITE OFFICE 1 30.00 0.65 0.075 1.463 Cum
2 10-08-2023 bharat bricks Industries PCC FOR SITE OFFICE 1 35.06 0.65 0.075 1.709 Cum
3 17-08-2023 bharat bricks Industries PCC FOR LAB 1 32 0.65 0.075 1.560 Cum

4.732
UCR WORK

1 10-08-2023 bharat bricks Industries UCR Masonary Wall 1 23.33 0.45 0.3 3.150 Cum For site office
2 11-08-2023 bharat bricks Industries UCR Masonary Wall 1 9.20 0.45 0.3 1.242 Cum For site office
3 11-08-2023 bharat bricks Industries UCR Masonary Wall 1 23.33 0.375 0.3 2.625 Cum For site office
4 12-08-2023 bharat bricks Industries UCR Masonary Wall 1 9.20 0.375 0.3 1.035 Cum For site office
5 17-08-2023 bharat bricks Industries UCR Masonary Wall 1 10 0.45 0.3 1.350 Cum lab
6 17-08-2023 bharat bricks Industries UCR Masonary Wall 1 10 0.45 0.3 1.350 Cum lab
7 18-08-2023 bharat bricks Industries UCR Masonary Wall 1 6 0.375 0.3 0.675 Cum lab
8 18-08-2023 bharat bricks Industries UCR Masonary Wall 1 6 0.375 0.3 0.675 Cum lab
9 18-08-2023 bharat bricks Industries UCR Masonary Wall 1 23.33 0.38 0.45 3.94 Cum For site office
9 19-08-2023 bharat bricks Industries UCR Masonary Wall 1 23.33 0.375 0.45 3.94 Cum For site office
9 19-08-2023 bharat bricks Industries UCR Masonary Wall 1 9.20 0.375 0.45 1.55 Cum For site office
9 20-08-2023 bharat bricks Industries UCR Masonary Wall 1 9.20 0.375 0.45 1.55 Cum For site office
9 20-08-2023 bharat bricks Industries UCR Masonary Wall 1 10.00 0.375 0.45 1.69 Cum For Lab
9 20-08-2023 bharat bricks Industries UCR Masonary Wall 1 10.00 0.375 0.45 1.69 Cum For Lab
9 20-08-2023 bharat bricks Industries UCR Masonary Wall 1 6.00 0.375 0.45 1.01 Cum For Lab
9 20-08-2023 bharat bricks Industries UCR Masonary Wall 1 6.00 0.375 0.45 1.01 Cum For Lab

28.480
Murrum Filling

1 25-08-2023 bharat bricks Industries Site office 1 21.33 7.2 0.225 34.555 Cum
2 29-08-2023 bharat bricks Industries Lab 1 9.63 5.625 0.225 12.182 Cum
3 0.000 Cum
46.736
Rubble Soling

1 0.000 Cum
2 0.000 Cum
3 0.000 Cum
0.000
Fencing Work
Excavation for Pit

1 12-08-2023 55 0.30 0.3 0.6 2.970 Cum


2 13-08-2023 75 0.30 0.3 0.6 4.050 Cum
3 17-08-2023 60 0.30 0.3 0.6 3.240 Cum
0.000 Cum

10.260
M10 Concrete For PIT

1 12-08-2023 55 0.30 0.3 0.6 2.970 Cum


2 13-08-2023 75 0.30 0.3 0.6 4.050 Cum
3 17-08-2023 60 0.30 0.3 0.6 3.240 Cum
0.000 Cum

10.260
Angle Fixing

1 12-08-2023 55 55.000 Nos


2 13-08-2023 75 75.000 Nos
3 17-08-2023 60 60.000 Nos
4 0.000 Nos
5 0.000 Nos
190.000
Barbed Wire Fixing

0.000
weight bridge
Excavation

1 21-08-2023 1 2.20 4 0.9 7.920 Cum


0.000 Cum

7.920
Ruble Soling

1 25-08-2023 1 2.20 4 0.25 2.200 Cum


0.000 Cum

2.200
Batching Plant works
Excavation

1 29-08-2023 bharat bricks Industries Silo 1 3.30 3.3 0.8 8.712 Cum
2 29-08-2023 bharat bricks Industries Batching plant area 1 11.40 2.9 0.8 26.448 Cum

35.160
PCC

1 0.000 Cum
2 0.000 Cum

0.000
ASHOKA BUILDCON LIMITED

Sheopur to Gwalior GC Project DATE:- 29-08-2023

Daily Progress Report (Dismantling of Rails)


Chainages
Date Name of contractor Items Side No Length  Width Depth   Quantity Unit Remarks Received Qty.(MT)
From To
Rail Dismantling

1-08-2023 G.S. Construction Rail Dismantling 154+990 155+690 700 700 Metre DDS not submitted
2-08-2023 G.S. Construction Rail Dismantling 155+690 156+090 400 400 Metre DDS not submitted
3-08-2023 G.S. Construction Rail Dismantling 156+090 156+370 280 280 Metre DDS not submitted
4-08-2023 G.S. Construction Rail Dismantling 156+370 156+545 175 175 Metre DDS not submitted
5-08-2023 G.S. Construction Rail Dismantling 156+545 156+545 0 0 Metre DDS not submitted
6-08-2023 G.S. Construction Rail Dismantling 156+545 156+860 315 315 Metre DDS not submitted
7-08-2023 G.S. Construction Rail Dismantling 156+860 157+490 630 630 Metre DDS not submitted
8-08-2023 G.S. Construction Rail Dismantling 157+490 158+190 700 700 Metre DDS not submitted
9-08-2023 G.S. Construction Rail Dismantling 158+190 158+890 700 700 Metre DDS not submitted
10-08-2023 G.S. Construction Rail Dismantling 158+890 158+970 80 80 Metre DDS not submitted
11-08-2023 G.S. Construction Rail Dismantling 158+970 159+605 635 635 Metre DDS not submitted
14-08-2023 G.S. Construction Rail Dismantling 159+605 160+975 1370 1370 Metre DDS not submitted
16-08-2023 G.S. Construction Rail Dismantling 160+975 162+130 1155 1155 Metre DDS not submitted
18-08-2023 G.S. Construction Rail Dismantling 162+130 162+970 840 840 Metre DDS not submitted
19-08-2023 G.S. Construction Rail Dismantling 162+970 163+810 840 840 Metre DDS not submitted
20-08-2023 G.S. Construction Rail Dismantling 163+810 164+475 665 665 Metre DDS not submitted
21-08-2023 G.S. Construction Rail Dismantling 164+475 164+825 350 350 Metre DDS not submitted
22-08-2023 G.S. Construction Rail Dismantling 164+825 165+035 210 210 Metre DDS not submitted
23-08-2023 G.S. Construction Rail Dismantling 165+035 165+490 455 455 Metre DDS not submitted
24-08-2023 G.S. Construction Rail Dismantling 165+490 165+945 455 455 Metre DDS not submitted

25-08-2023 G.S. Construction Rail Dismantling 165+945 166+505 560 560 Metre DDS not submitted,

No DPR Provided

11515
Shifting of Rails and Sleepers
ASHOKA BUILDCON LIMITED

Sheopur to Gwalior GC Project DATE:- 29-08-2023

Daily Progress Report (Dismantling of Rails)


Chainages
Date Name of contractor Items Side No Length  Width Depth   Quantity Unit Remarks Received Qty.(MT)
From To
Safety guidelines Girdharpur station

Safety guidelines
Allocated

Allocated

Deployed
chainage

chainage

Executed

Executed

executed

Remarks
Previous
Scope in

Till date
Activity

activity
Vendor

Labour
TOTAL
WORK
Machinery Deployed

today
Sr no.

name

Team

Work

No of
Total

work
from
Date

upto

date
Unit

Side
to
1 2 3 4 5 6
A Survey work
Gautam, Adarsh,
Tree Counting 01-08-2023 ABL 164 173.25 BOTH
Lambodar,Four Helper
Gautam, Adarsh,
Tree Counting 02-08-2023 ABL 173.25 188.25 BOTH
Lambodar,Four Helper
Topo taken and height measurment for Gautam, Adarsh,
03-08-2023 ABL 187 187.2
High tension line crossing at site Lambodar,Four Helper
Topo taken and height measurment for
03-08-2023 Adarsh, three helper ABL 182.76 BOTH
High tension line crossing at site
03-08-2023 Adarsh, three helper ABL 187.017 BOTH
chainnage marking for existing rail top 03-08-2023 Adarsh, three helper ABL 182.7 183.3
03-08-2023 Adarsh, three helper ABL 187 187.7
04-08-2023 Adarsh, three helper ABL 167.8 168.3
04-08-2023 Adarsh, three helper ABL 177 177.3
Topo with details taken for canal
05-08-2023 Adarsh, three helper ABL 177.58
(bridge no. 305)
PCL marking 05-08-2023 Adarsh, three helper ABL 177.5 177.65
Station shed & Building inventory 07-08-2023 Gautam three helper ABL 159.05

Row demarcation & Polyline marking 08-08-2023 Gautam three helper ABL 187.65 188.08 LHS

Gautam,Adarsh, three
09-08-2023 ABL 188.09 188.2 RHS
helper
Gautam,Adarsh, three
09-08-2023 ABL 187 187.65 LHS
helper
Gautam,Adarsh, three
09-08-2023 ABL 188.08 188.2 LHS
helper
Row demarcation & Polyline marking Gautam,Adarsh, three
10-08-2023 ABL 186.85 187.3 RHS
for trench excavtion purposes from helper
Gautam,Adarsh, three
10-08-2023 ABL 186.7 187 LHS
helper
Row demarcation & Polyline marking Gautam,Adarsh, three
11-08-2023 ABL 185.5 186.85 RHS
for trench excavtion purposes from ch: helper
Gautam,Adarsh, three
11-08-2023 ABL 185.5 186.7 LHS
helper
Row demarcation & Polyline marking Gautam,Adarsh, three
12-08-2023 ABL 185.1 185.5 RHS
for trench excavtion purposes from ch: helper
Gautam,Adarsh, three
12-08-2023 ABL 185.1 185.5 LHS
helper
Row demarcation & Polyline marking Gautam,Adarsh, three
14-08-2023 ABL 181.85 182.5 RHS
for trench excavtion purposes from ch: helper
Gautam,Adarsh, three
14-08-2023 ABL 181.87 182.55 LHS
helper
Row demarcation & Polyline marking Gautam,Adarsh, four
16-08-2023 ABL 181.5 181.85 RHS
for trench excavtion purposes from ch: helper
Gautam,Adarsh, four
16-08-2023 ABL 181.5 182.45 LHS
helper
Orignal ground level Recording 16-08-2023 birjes singh jp infrastructure 177.32 177.55 BOTH
Row demarcation & Polyline marking
for trench excavtion purposes from ch: Gautam,Adarsh, four
17-08-2023 ABL 181.3 181.6 RHS
*Weighbridge Layout marking for helper
excavation at girdharpur camp
Gautam,Adarsh, four
17-08-2023 ABL 181.25 181.7 LHS
helper
Orignal ground level Recording 17-08-2023 birjes singh jp infrastructure 177.66 178.53 BOTH
Row demarcation & Polyline marking
for trench excavtion purposes from ch: Gautam,Adarsh, four
18-08-2023 ABL 181 181.7 LHS
*Weighbridge Layout marking for helper
excavation at girdharpur camp
tree destance measurement from Gautam,Adarsh, four
18-08-2023 ABL 172.2 173.2 BOTH
proposed center line from ch: helper

Orignal ground level Recording 18-08-2023 birjesH singh jp infrastructure 178.53 179.18 BOTH

tree destance measurement from Gautam,Adarsh, four


19-08-2023 ABL 177.55 184 BOTH
proposed center line from ch: helper
Gautam,Adarsh, four
19-08-2023 ABL 185.25 187.2 BOTH
helper

Orignal ground level Recording 19-08-2023 birjesH singh jp infrastructure 179.08 179.43 BOTH

tree distance measurement from Gautam,Adarsh, three


21-08-2023 ABL 184 185.2 BOTH
proposed center line helper

Orignal ground level Recording 21-08-2023 birjesH singh jp infrastructure 184.43 184.73 BOTH

*Batching plant layout marking for


excavaton. Purpose at Girdharpur camp
Gautam,Adarsh, three
.*Weighbridge colum Layout marking 22-08-2023 ABL 172
helper
for excavation Purpose at girdharpur
camp
Orignal ground level Recording 22-08-2023 birjesH singh jp infrastructure 184.73 185.38 BOTH
tree distance measurement from Gautam,Adarsh, three
23-08-2023 ABL 175.3 177.6 BOTH
proposed center line helper

*Batching plant Layout marking for


excuvation . Purpose at girdharpur Gautam,Adarsh, three
24-08-2023 ABL 172.9 173.15
camp *purposed centre line marking helper
from ch:

Batching plant Layout marking for


excuvation . Purpose at girdharpur
25-08-2023 Gautam, three helper ABL 155 157 BOTH
camp ,tree distance measurement from
proposed center line .

Borrow Area Sampling 25-08-2023 Nitish Kr ABL 178+420

Weighbridge colum Layout marking for


26-08-2023 Gautam, three helper ABL 173.65 BOTH
excavation Purpose at girdharpur

Orignal ground level Recording 26-08-2023 lambodar behera Nihan infrastructure 176.04 176.5 BOTH
Weighbridge colum Layout marking for
excavation Purpose at girdharpur and 28-08-2023 Gautam, three helper ABL 172+880 173+150 BOTH
centre line marking ch
Orignal ground level Recording 28-08-2023 lambodar behera Nihan infrastructure 176+500 176+550 BOTH
Orignal ground level Recording 28-08-2023 lambodar behera Nihan infrastructure 172+890 173+150 BOTH
centre line marking & chainnage
29-08-2023 Gautam, three helper ABL 175.75 177.45 BOTH
marking Rail top ch: