Development of Six Lane Karki - Kaliagura Section of NH-130-CD from Km 226+500 to Km 249+000 under Raipur Visakhapatnam Economic Corridor

in the
state of Odisha on Hybrid Annuity Mode (HAM) (Pkg OD‐4)
DAILY PROGRESS REPORT
Date: 16-Jul-22
Length Executed Quantity Executed Amount in Lakhs
S No Description of Item Up to Up to Up to Up to
Unit Today Up to Date Unit Today Up to Date Today
Previous Previous Previous Date
I.ROAD WORKS
1 Excavation Km's - - - Cum - - -
2 Earth work Upto Emb Top Km's 30.37 - 30.37 Cum 1,586,497.19 - 1,586,497.190 3,825.15 - 3,825.15
3 Earth work Upto Subgrade Top Km's 22.69 - 22.69 Cum 195,576.15 - 195,576.150 1,224.19 - 1,224.19
4 GSB Km's 13.88 - 13.88 MT 35,442.96 - 35,442.960 678.58 - 678.58
5 CTB Km's - - - Cum - - - - -
6 WMM/AIL Km's - - - Cum - - - - - -
7 DBM Km's - - - Cum - - - - - -
8 BC Km's - - - Cum - - - - - -
II.STRUCTURE WORKS
1 Box Culverts Nos 21.10 21.10 811.75 - 811.75
2 HPC Nos 0.00 - - - -
3 Minor Bridges Nos 0.30 0.30 72.04 - 72.04
4 LVUP Nos 2.59 2.59 529.59 - 529.59
5 Flyover/Viaduct/AUP Nos 0.40 0.40 42.72 - 42.72
6 Major Bridge Nos - - -
7 ROB Nos - - -
8 RE Wall Sqm - - -
Total 7,184.03 - 7,184.03
B. AGGREGATE PRODUCTION
Quantity
Consumed Physical
S No Description of Item Up to
Unit Today Up to Date Up to date Stock
Previous
1 Quarrying of Boulders MT 160725.10 160,725.10 147294.787 13,430.31
2 40mm Aggregate MT 1420.37 1,420.37 1,420.37
3 20mm Aggregate MT 6485.79 6,485.79 3530.034 2,955.75
4 10mm Aggregate MT 5124.59 5,124.59 2,582.132 2,542.46
5 6mm Aggregate MT -
6 Dust MT 7473.71 7,473.71 16.02 7,457.69
7 GSB Material MT 126629.30 126,629.30 72087.53 54,541.77
8 M Sand MT 15445.74 15,445.74 3223.427 12,222.31
Development of Six Lane Karki - Kaliagura Section of NH-130-CD from Km 226+500 to Km 249+000 under Raipur Visakhapatnam Economic Corridor in the
state of Odisha on Hybrid Annuity Mode (HAM) (Pkg OD‐4)
DAILY PROGRESS REPORT
Date: 16-Jul-22
C. MATERIAL PROCUREMENT D. PLANT PRODUCTION
Quantity Quantity
S No Description of Item Up to date Physical S No Description of Item Up to Up to
Unit Consumed Unit Today
received Stock Previous Date
1 Cement MT 1353.17 1184.456 168.71 1 Crusher MT
2 Cement PPC BAG 3160 2,765.00 395.00 2 RMC Plant Cum 3909 3909
3 HYSD Reinforcement MT 809.76 546.20 263.56 3 WMM/AIL MT
4 Bitumen Emulson SS1 MT 4 CTB MT
5 Bitumen Emulson RS1 MT 5 Hot Mix Plant MT
6 Bitumen VG-40 MT
7 Admixture MT 15.075 8.485 6.59
8 Diesel Ltr 1,100,347.21 1,092,045.00 8,302

E. MACHINERY
Quantity
Balance to Break down Break down
S No Description of Item Reason for breakdown
Unit Required Mobilized be if any since
Mobilised
1 Excavator Nos 2
2 Loader Nos 2
3 Tipper Nos 14
4 Water Tanker Nos 1
5 Transit Mixer Nos 6
6 Earth Compactors Nos 1
7 Grader Nos 2

F. CRITICAL ISSUES
1 Sufficient Operators / drivers are not available for machinary, mechanical department has not given updated driver operator details
2
3
G. REASON FOR SHORTFALL IF ANY
1 RMC Plant Breakdown
2
3