19-Jun-23

ACTIVITY DAILY MONTHLY YEARLY DELAYS


PLAN ACTUAL PLAN ACTUAL PLAN ACTUAL JOB AREA DAILY (Hrs) MTD (Hrs)
OB REMOVAL 7.000 10.420,00 210.000 167.778,00 4.737.600 1.554.582,00 MINING 1,08 125,41
COAL GETTING 1.000 1.173,00 30.000 6.582,00 420.000 127.892,00 HAULING 10,0 248,00
COAL HAULING 1.167 - 35.000 9.648,76 420.000 119.527,14 PORTAL - 21,00
STRIPING RATIO 7,00 7,00 25,49 11,28 11,43
FUEL RATIO 1,0 - 1,0 0,83 1,0 0,87 BARGING PORT BP
DAILY MTD YTD
COAL STOCK SUB GRADE COAL - 4.532,53 89.405,82
BUA Port ISP FLOATING BUA PORT
9.872,84 52.676,26 16.356,008 4.504,246 10.864,85 128,52 BARGING PORT ISP/MGM
DAILY MTD YTD
STONE CRUSHER DUAN ARUNG - 7.504,97 94.170,099
STOCK PRODUCTION TRANSPORT REMAIN
60.706,06 NR NR 60.706,06 DRILLING BP
Rig001 Rig002 MTD
FUEL Hours Operation 12,0 12,0 410,00
JOB AREA DAILY MTD YTD Meterage Drilled - 4,9 303,35
MINING 13.195 142.977 1.437.744 Fuel Consumption - - -
HAULING 5.857 90.541 1.400.506 Man power 4 5
INFRASTRUKTUR 3.755 30.944 496.596 DRILLING GIS
BARGING & CRUSHING 282 3.722 46.227 Rig002 Rig003 MTD
PORT 666 17.814 193.075 Meterage Drilled 9,0 12,0 387,20
WASHING PLANT 915 11.166 153.723

REMARKS :
Coal Getting Seam M2 + Seam M2L & Bedding M2
Exca 320 (01) Breakdown
- Update Coal Stock Bua By Survey 17 June 2023 : 19.062,24 MT (Include Sub Grade Coal)
- 6 DT Breakdown (DT33.DT042.DT043.DT044.DT45.DT047)
- 9 MDT Breakdown (MDT04.MDT07.MDT10.MDT11.MDT16.MDT19.MDT25.MDT35.MDT43)
- Delay Rain and Slippery at Mining Area
- Delay at Hauling Area
1. No Hauling Activity, unsaleable coal
2. Rain & Slippery, 10 Hours
REMARKS DRILLING BP :
- Rig001 DHBP-29C, Logging, prepare access for moving, moving to simpang bor
- Rig002 DHBP-42, Meterage Drill 7,4 - 12,3 m, progress 4,9 m
- Rig GIS003 DHBP-22 R, Meterage Drill 20,00 - 32,00, progress 12 m
- Rig GIS002 DHBP-15A.R1, Meterage Drill 56,00 - 65,00 m, progress 9 m