Note * The work volumes above are for reference only and are not binding
* The contractor must recalculate based on the survey
KF-75220-009
No. Description Cost % Rp. % Rp. Work Description Direct Mhr. Volume Unit Mhr/Volume
PLANT AREA
1 Direct Material 212.405.000 - 0
¤ Mechanical 23.660 123 Ton 192,99
2 Indirect Material 105.740.270
¤ Piping - Fab.& Inst. 54.880 11.400 DI 4,81
3 Indirect Costs 127.450.000
¤ Concrete 13.260 248 m3 53,47
4 Construction Force & Fringes 156.367.220 - 0
¤ Structure (Erect) 16.211 88,9 Ton 182,29
5 Sub Contract 640.710.000 0 -
¤ Elect./Inst. 41.951 1,0 Lot 41.951
6 Tools 54.880.000 -
¤ Commissioning 1,0 Lot 0
7 Equipment 732.344.000 - 0
8 Freight 2.940.000
TO TAL 54.880
12 Travel & Telecom 31.500.000 Piping Work : 5.74 Mhr/DI , SP = Rp. 218.949 : 27,300 DI
14 Mob & Demobilization 49.000.000 ¤ Reff. to Const. Of Semberah VLP/MP Gas Comp.Project E-0210 :
15 Insurance 10.750.000 Mechanical : 117.32 Mhr/Ton , SP = Rp. 0 : 155.5 T
21 Bids & Performance Bond 559.000 Piping Work 54.880 Mhr 4,8140 Mhr/DI
22 Proposal Cost Civil/Structure #REF!
A Total Cost (TC) 2.566.280.269 0 - 0 - 0
Electr/Instrument #REF!
23 Escalation + Contingency 0 27 Negotiation 0,00% 0 COST ANALISYS
B Total 252.778.607 0 C Total 0 43.000.000 Tools & Consumable 7.044,23 15,1% 13,5%
D:\CONTRACT-BUDGET-PROGRESS-COST REPORT-OTHERS\[CONTRACT-BUDGET-PROGRESS-COST-REPORT-OTHERS-1.xlsx]CONTRACT
BUDGET BREAKDOWN
1. DIRECT MATERIAL
Welding Electrode
- Welding E7010 4.8 mm LB 52 2.042 kg x Rp. 65.000,00 Rp. 132.730.000,00
- Welding E6010 3.2 mm 875 kg x Rp. 65.000,00 Rp. 56.875.000,00
- Welding Electrode LB 52 2.6mm kg x Rp. 22.000,00 Rp. 0,00
- Welding Electrode LB 52 3.2 mm kg x Rp. 20.000,00 Rp. 0,00
- Welding Electrode CMA kg x Rp. 32.000,00 Rp. 0,00
- Welding Electrode TGS 50 kg x Rp. 64.000,00 Rp. 0,00
- Welding Electrode TGS 316 kg x Rp. 358.000,00 Rp. 0,00
- Welding Electrode TGS 1CM kg x Rp. 212.000,00 Rp. 0,00
- Welding Electrode NC 36 kg x Rp. 114.000,00 Rp. 0,00
- Welding Electrode NC 39 kg x Rp. 121.000,00 Rp. 0,00
- Sand for Under Ground M3 x Rp. 120.000,00 Rp. 0,00
- Sandbag for Under Ground Ea x Rp. 15.000,00 Rp. 0,00
Marker Tape 5.700,00 Mx Rp. 4.000,00 Rp. 22.800.000,00
Pintu Besi & Lampu (UPS room) Ea x Rp. 14.127.000,00 Rp. 0,00
Rp. 212.405.000,00
2. INDIRECT MATERIAL
- Consumables : Total MH 54.880 mh x Rp. 1.000,00 Rp. 54.880.000,00
- Gas = - LPG 10 Btl x Rp. 322.000,00 3.193.531,60
- Oxigen 30 Btl x Rp. 70.000,00 2.082.738,00
- Argon Btl x Rp. 350.000,00 -
- Safety Gear 94 psg x Rp. 336.000,00 Rp. 31.584.000,00
- Wooden 10 M3 x Rp. 1.400.000,00 Rp. 14.000.000,00
- Temp. material for Stringing Pcs x Rp. Ls Rp. -
Rp. 105.740.269,60
3. INDIRECT COSTS
a. - Pre-Job Activity Ls Rp.
Rp. 0,00
b. Temporary Facilities
- Site Office (Workshop Area) month x Rp. 2.800.000,00 Ls Rp. -
- Container Recondition 2,0 Ea x Rp. 3.500.000,00 Ls Rp. 7.000.000,00
- Tools room (incl) Ls Rp.
- AC 3/4 PK Window type (Ex. Project) 2,0 Ea x Rp. Ls Rp. -
- Filing cabinet Ea x Rp. 1.400.000,00 Ls Rp. -
- Dispenser 2,0 Ea x Rp. 140.000,00 Ls Rp. 280.000,00
- Meja 1/2 Biro 4,0 Ea x Rp. 385.000,00 Ls Rp. 1.540.000,00
- Kursi 8,0 Ea x Rp. 105.000,00 Ls Rp. 840.000,00
- Computer + printer laser jet Ea x Rp. 7.700.000,00 Ls Rp. -
- TV for Mess Staff (Ex Project) Ls Rp. 5.600.000,00 Ls Rp. -
- Rental copy machine 3,0 month Rp. 2.800.000,00 Ls Rp. 8.400.000,00
- Rental of Stock Yard month Rp. 14.000.000,00 Ls Rp. -
- Wooden For Stock Pile 1,0 Ls Rp. 35.000.000,00 Ls Rp. 35.000.000,00
- Mattress + Pillow 55,0 Ea x Rp. 350.000,00 Ls Rp. 19.250.000,00
- Fan 8,0 Ea x Rp. 210.000,00 Ls Rp. 1.680.000,00
- Toilet for near Job Rp. 5.000.000,00
Rp. 78.990.000,00
c. Utilities / Communication
- Temp. elect. dist ( Included ) LS Rp. -
- Temp. water dist.( included ) LS Rp. -
- Repeater LS Rp.
- Radio HT (Ex Project) Ea x Rp. 4.550.000,00 Rp. -
- Hand Phone (Esia) + Pulsa (3 Month) 10 Ea x Rp. 1.400.000,00 Rp. 14.000.000,00
- Fire extinguisher / Refill LS Rp. 5.000.000,00
- Water Inhibitor LS Rp. -
Rp. 19.000.000,00
d. Safety Accessories
- Argon Gloves Ea x Rp. 35.000,00 Rp. -
- Fitter Gloves 480 Ea x Rp. 15.000,00 Rp. 7.200.000,00
- Cotton Gloves 1.920 Ea x Rp. 3.000,00 Rp. 5.760.000,00 4,00
- Welder Gloves 480 Ea x Rp. 25.000,00 Rp. 12.000.000,00
- Safety Glass (Include safety Gear) 0 Ea x Rp. 0,00 Rp. -
Rp. 24.960.000,00
e. Miscellaneous
- Scaffolding / Safety Net LS Rp.
- Crane mats : 1,5 m x 6 m (Ex Project) LS Rp.
- Weather protection LS Rp. 4.500.000,00
- Drive Right ea Rp. 6.300.000,00 Rp. -
- Drum Ea x Rp. 560.000,00 Rp. - Rp. 4.500.000,00
Rp. 127.450.000,00
4. CONSTRUCTION FORCE
- Direct MH Piping 42.000 mh x Rp. 3.723,03 Rp. 156.367.220,00
Pipe Welder (CS) 12.880 mh x Rp. 0,00 Rp. -
Others mh x Rp. Rp.
Plate Welder mh x Rp. Rp.
Civil mh x Rp. Rp.
Comm. mh x Rp. Rp. -
54.880,0 mhr Rp. 156.367.220,00
- THR Rp.
- Pesangon 2x Rp.
Rp. 0,00
Rp. 156.367.220,00
5. SUB CONTRACTOR
a. Direct Works
- Radiographic Test 3.420 Sheet x Rp. 49.000,00 Rp. 167.580.000,00
- Sling Belt Sertification 4 Ea x Rp. 490.000,00 Rp. 1.960.000,00
- PT 1 Ls x Rp. 7.000.000,00 Rp. 7.000.000,00
- Welding 11.400 DI x Rp. 28.000,00 Rp. 319.200.000,00
- Painting for Pipe ( Incl. material ) m² x Rp. 210.000,00 Rp. -
- PWHT DI x Rp. 209.000,00 Rp. -
- Scaffolding certification LS Rp. 4.200.000,00 Rp. 4.200.000,00
- Sign Marker Ea x Rp. 1.120.000,00 Rp. -
- Insulation (Include Mtl = 51 m2) LS Rp. 91.000.000,00 Rp. -
Civil Work
- Patok Every 100 M of Pipe Long 57 Ea x Rp. 140.000,00 Rp. 7.980.000,00
- Patok Every 500 M of Pipe Long 11 Ea x Rp. 350.000,00 Rp. 3.990.000,00
- Papan Nama Proyek 2 Ea x Rp. 4.200.000,00 Rp. 8.400.000,00
- Trenching of Concrete m² x Rp. 84.000,00 Rp. -
- Trenching of Hotmix m² x Rp. 84.000,00 Rp. -
- Perbaikan Jalan Asphalt/Hotmix m² x Rp. 84.000,00 Rp. -
- Repair Jalan Beton m3 x Rp. 1.120.000,00 Rp. -
- Block Valve Box 2 Ea x Rp. 25.200.000,00 Rp. 50.400.000,00
Rp. 570.710.000,00
b. Indirect Work
- Welder Test 20,0 ea x Rp. 3.500.000,00 LS Rp. 70.000.000,00
- WPS ea x Rp. 10.500.000,00 Rp. -
Rp. 70.000.000,00
Rp. 640.710.000,00
6. T O O L S
- Cost 54.880,0 mh x Rp. 1.000,00 Rp. 54.880.000,00
- Holiday Detector LS Rp. 35.000.000,00 Rp. -
- Barner for Coating LS Rp. 21.000.000,00 Rp. -
Rp. 54.880.000,00
7. EQUIPMENT
Equipment Cost Rp. 467.750.000,00
Fuel Rp. 264.594.000,00
Rp. 732.344.000,00
8. FREIGHT
30 Ton x Rp. 98.000,00 Rp. 2.940.000,00
Rp. 2.940.000,00
9. LOCAL FADS
- Salary Staff 33 MM x Rp. 6.858.512,86 Rp. 222.901.667,88
Non Staff = 31 MM x Rp. 2.228.068,12 Rp. 69.070.111,77
Rp. 291.971.779,65
- THR (Local Staff + Non Staff) Rp.
- Pesangon 2x (Local Staff+ Non Staff) (Include) Rp.
Rp. 0,00
Rp. 291.971.779,65
10. EXPAT FADS
- Salary 0 mmos x Rp. Rp. -
- Income Tax + Royalty Tax 35% x Rp. Rp. -
- Living Allowance 0 mmos x Rp. Rp. -
- Lunch 0 mmos x Rp. Rp. -
- Food for Expat 0 0,0 Rp. Rp. -
- Expat 2 x5 trip x Rp. /trip Rp. -
Rp. -
11. HOUSING + FOOD
a. HOUSING
- Direct+ Non Staff (Rental Housing) 5 Housing/3 Month x Rp. 7.000.000,00 /3 Mth Rp. 35.000.000,00
0 x Rp. Rp. -
b. FOOD
- FOOD for HO Staff 33 MM x Rp. 292.000,00 Rp. 9.490.000,00
- Food for Direct + Local Staff + non staff 227 MM x Rp. 154.000,00 Rp. 34.958.000,00
- MM x Rp. LS Rp.
Rp. 79.448.000,00
12. TRAVEL AND TELCOM
a. Travel
- HO Management 30 trip x Rp. 700.000,00 /trip Rp. 21.000.000,00
- Local Fads trip x Rp. 420.000,00 /trip Rp. -
- Hire Manpower LS Rp.
Rp. 21.000.000,00
b. Telcoms
- Telcom 3 month x Rp. 3.500.000,00 Rp. 10.500.000,00
Rp. 10.500.000,00
Rp. 31.500.000,00
13. FIELD OFFICE EXPENSE
Cost : 3 month x Rp. 2.100.000,00 Rp. 6.300.000,00
Rp. 6.300.000,00
14. MOB DEMOB
- Manpower LS Rp. 21.000.000,00
- Equipment LS Rp. 28.000.000,00
Rp. 49.000.000,00
15. INSURANCE
Cost : 0,5% x CV Rp. 2.150.000.000,00 Rp. 10.750.000,00 Rp. 10.750.000,00
Rp. 18.165.000,00
20 HOME OFFICE ADM.
Cost : 0,5% x CV Rp. 2.150.000.000,00 Rp. 10.750.000,00 Rp. 10.750.000,00
- Management Expenses 0 mh x Rp. 25,00 Rp. -
- Procurement Expenses 0 mh x Rp. 3,00 Rp. -
- Adm. Acc 0 mh x Rp. 3,00 Rp. -
- Cons. Div Expenses 0 mh x Rp. 5,00 Rp. -
Rp. -
21 HOME OFFICE ENGINEERING
- Engineering Expenses 0 Ls x Rp. 0,00 Rp. -
- Spool Drawing Rp. -
- Isometric Drawing (incl.) Rp. -
Rp. -
1 Truck Crane 35 T 2 0,5 2,0 2,0 4,5 30.000.000 30 720 3.960.000 - 17.820.000 152.820.000
2 Foco Truck 5 T 1 0,5 1,0 1,0 2,5 8.000.000 25 600 3.300.000 - 8.250.000 28.250.000
3 Trailer Truck 40T 2 0,5 2,0 2,0 4,5 12.000.000 25 600 3.300.000 14.850.000 68.850.000
4 Excavator PC-200 2 0,5 2,0 2,0 4,5 22.000.000 30 720 3.960.000 17.820.000 116.820.000
5 Welding Engine 500 Amp 16 10,0 16,0 16,0 42,0 2.250.000 30 720 3.960.000 - 166.320.000 260.820.000
6 Genset 10 KVA 2 0,5 2,0 2,0 4,5 3.000.000 6 144 792.000 - 3.564.000 17.064.000
7 Water Pump 2 0,5 2,0 2,0 4,5 1.000.000 5 120 660.000 - 2.970.000 7.470.000
8 Pick-Up 2 0,5 2,0 2,0 4,5 1.500.000 10 240 1.320.000 - 5.940.000 12.690.000
9 Minibus (Kijang Station) 3 0,5 3,0 3,0 6,5 3.000.000 20 480 2.640.000 17.160.000 36.660.000
INDIRECT MANPOWER
JAMSOST PAJAK JKK, MIGAS
TOT BASIC PER- RATE PER- Cuti RATE TOT 423 HR PER- GRAND TOTAL PER- Indirect Cost + Welding MP
BASIC EK 13.74% HASIL JPK 6% JK, JHT Prog SURPLUS PPH23 Overhead Profit Escalation
Revisi : 0 MONTH 423 HR 8.33% COMPLETE MONTH 423 HR Contigency Proposal Value
DATE : Jun 27, 2020 X BASIC 5% 4.8% 8.33%
NO. DESCRIPTION QTY 2006 TOTAL
ManMont C=(A/173)x
S 2 3 4 5 A B=AxS D = A x WP E F G H I=AxWP J=C+D+I K=AxTx2 L=J x S M=(J x T)+K N=M x WP O=M x WP P=M x WP Q=Mx WP R=Mx WP U=M+N+O+P+Q+R
h=T WP
Monthly Sub Total Direct Labour- Manmonths 13 6,5 13,0 13,0 - - 32,5
Cummulative Total Direct Labour- Manmonths 6,5 19,5 32,5 32,5 32,5 26.600.000 20.860.000 70.909.926 198.134.816 - - - 4.953.370 19.813.482 222.901.668
Non-Staff 423 hr 13,74% 5% 0% 0,00% 0,00% 8,33% 423 hr 3,00% 3,50% 5,00% 2,50% 10,00% A
1 Warehouseman 1 1,0 1,0 1,0 3,0 980.000 980.000 2.396.185 134.652 - - - 81.634 2.612.471 980.000 2.612.471 8.817.413 - - - 220.435 881.741 9.919.590
2 Safetyman 1 0,5 1,0 1,0 2,5 1.050.000 1.050.000 2.567.341 144.270 - - - 87.465 2.799.076 1.050.000 2.799.076 8.047.690 - - - 201.192 804.769 9.053.651
3 Clerk 1 0,5 1,0 1,0 2,5 910.000 910.000 2.225.029 125.034 - - - 75.803 2.425.866 910.000 2.425.866 6.974.665 - - - 174.367 697.466 7.846.498
4 Security 3 1,5 3,0 3,0 7,5 980.000 2.940.000 2.396.185 134.652 - - - 81.634 2.612.471 2.940.000 7.837.413 22.533.532 - - - 563.338 2.253.353 25.350.224
5 Time Keeper 1 0,5 1,0 1,0 2,5 980.000 980.000 2.396.185 134.652 - - - 81.634 2.612.471 980.000 2.612.471 7.511.177 - - - 187.779 751.118 8.450.075
6 Heavy Duty Driver 5 0,5 5,0 5,0 10,5 BY HE SCOPE
7 Driver 1 0,5 1,0 1,0 2,5 980.000 980.000 2.396.185 134.652 - - - 81.634 2.612.471 980.000 2.612.471 7.511.177 - - - 187.779 751.118 8.450.075
Monthly Sub Total Direct Labour- Manmonths 13 5,0 13,0 13,0 - - 31,0
Cummulative Total Direct Labour- Manmonths 5,0 18,0 31,0 31,0 31,0 7.840.000 7.840.000 20.899.768 61.395.655 - - - 1.534.891 6.139.565 69.070.112
BIDDER : ______________________________________ KF - 72240 - 009
CLIENT : ______________________________________
PROJECT : ______________________________________
LOCATION : ______________________________________
WORK : ______________________________________
DIRECT MANPOWER
JAMSOST PAJAK JKK, MIGAS
TOT BASIC PER- RATE PER- Cuti RATE TOT 423 HR PER- GRAND TOTAL PER- Indirect Cost + Welding MP
BASIC EK 13.74% HASIL JPK 6% JK, JHT Prog SURPLUS PPH23 Overhead Profit Escalation Unit Cost Unit Cost Unit Cost
Revisi : 0 MONTH 423 HR 8.33% COMPLETE MONTH 423 HR Contigency Proposal Value
DATE : Jun 27, 2020 X BASIC 5% 4.8% 8.33%
NO. DESCRIPTION QTY 2006 TOTAL Rp/DI Rp/Mhr Rp/Mhr
ManMonth C=(A/173)x
S 2 3 4 5 A B=AxS D = A x WP E F G H I=AxWP J=C+D+I K=AxTx2 L=J x S M=(J x T)+K N=M x WP O=M x WP P=M x WP Q=Mx WP R=Mx WP U=M+N+O+P+Q+R
=T WP
Manpower Schedule - For Direct Labour 423 hr 13,74% 5% 0% 0,00% 0,00% 8,33% 423 hr 3,00% 5,00% 2,50% 10,00% A B = A/78000 C=(B x 30)/8 Hr C=A/(T x 260)
1 Piping Foreman 4 4 4 4 1 13 1.120.000 4.480.000 2.738.497 153.888 - - - 93.296 2.985.681 4.480.000 11.942.724 43.293.854 1.298.816 - 2.164.693 1.082.346 4.329.385 52.169.095 669 2.508 15.435
2 Pipe Welder (CS)-Include Pipe Support Work 16 10 16 16 4 46 BY SUBCONT
3 Rigger 2 2 2 2 6 980.000 1.960.000 2.396.185 134.652 - - - 81.634 2.612.471 1.960.000 5.224.942 17.634.826 529.045 - 881.741 440.871 1.763.483 21.249.965 272 1.022 13.622
4 Operator 4 4 4 4 12 BY HE SCOPE
5 Pipe Fitter (For Welding) 16 10 16 16 4 46 BY SUBCONT
6 Surveyor 1 1 1 1 3 2.100.000 2.100.000 5.134.682 288.540 - - - 174.930 5.598.152 2.100.000 5.598.152 18.894.456 566.834 - 944.723 472.361 1.889.446 22.767.820 292 1.095 29.190
7 Material Handling 3 1 3 3 7 910.000 2.730.000 2.225.029 125.034 - - - 75.803 2.425.866 2.730.000 7.277.598 19.711.061 591.332 - 985.553 492.777 1.971.106 23.751.829 305 1.142 13.050
8 Mechanic/Electric 2 1 2 2 5 BY HE SCOPE
9 Helper for Welder 16 10 16 16 4 46 BY SUBCONT -
10 Helper for Mateial Handling 4 2 4 4 2 12 840.000 3.360.000 2.053.873 115.416 - - - 69.972 2.239.261 3.360.000 8.957.043 30.231.130 906.934 - 1.511.556 755.778 3.023.113 36.428.512 467 1.751 11.676
PROJECT CASHFLOW
Contract Budget Home Office Site Office Account Total Remaining Remaining
DESCRIPTION COST CODE Plan Previous Last This Todate Previous Last This Todate Payable Cost Cost Kontrak
(Rp.) (Rp.) Month Month Month Month Month Month (Rp.) (Rp.) % (Rp.) % (Rp.) %
A B C D E F = C+E G H I J = G+I K L = F+J+K M = L/B N=B-L O = N/B P=A-L Q = P/A
2.1.1 Direct Material 2.1.1 233.633.206 212.405.000 - - - 20.923.000 20.923.000 - 20.923.000 20.923.000 9,85% 191.482.000 90,15% 212.710.206 91,04%
2.1.2 Direct Labour 2.1.2 171.994.891 156.367.220 - - - - - - - - - 0,00% 156.367.220 100,00% 171.994.891 100,00%
2.1.3 Direct Equipment 2.1.3 318.433.244 289.500.000 - - 15.000.000 15.000.000 - - 12.657.800 12.657.800 27.657.800 9,55% 261.842.200 90,45% 290.775.444 91,31%
2.1.4 Tools 2.1.4 60.364.824 54.880.000 4.702.500 4.702.500 - 4.702.500 - - 1.170.000 1.170.000 5.872.500 10,70% 49.007.500 89,30% 54.492.324 90,27%
TOTAL DIRECT COST : 784.426.165 713.152.220 4.702.500 4.702.500 15.000.000 19.702.500 20.923.000 20.923.000 13.827.800 34.750.800 - 54.453.300 7,64% 658.698.920 92,36% 729.972.865 93,06%
2.2.2 Home Office Cost 2.2.2 65.051.018 59.140.401 26.094.400 26.094.400 767.500 26.861.900 - - - - 26.861.900 45,42% 32.278.501 54,58% 38.189.118 58,71%
2.2.3 Maintenance cost 2.2.3 291.038.085 264.594.000 430.000 430.000 - 430.000 - - - - 430.000 0,16% 264.164.000 99,84% 290.608.085 99,85%
2.2.4 Sallary & Allowance 2.2.4 321.152.058 291.971.780 - - - - - - 100.000 100.000 100.000 0,03% 291.871.780 99,97% 321.052.058 99,97%
2.2.5 Temporary Facility 2.2.5 87.388.202 79.448.000 2.423.000 2.423.000 - 2.423.000 200.000 200.000 11.610.000 11.810.000 14.233.000 17,91% 65.215.000 82,09% 73.155.202 83,71%
2.2.6 Temporary Material 2.2.6 116.308.176 105.740.270 - - - - - - - - - 0,00% 105.740.270 100,00% 116.308.176 100,00%
2.2.7 Site Expenses 2.2.7 204.979.714 186.355.000 496.500 496.500 100.300.000 100.796.500 470.000 470.000 5.170.000 5.640.000 106.436.500 57,11% 79.918.500 42,89% 98.543.214 48,07%
2.2.8 Direct & Service Cost 2.2.8 704.743.916 640.710.000 1.000.000 1.000.000 - 1.000.000 945.500 945.500 3.250.000 4.195.500 5.195.500 0,81% 635.514.500 99,19% 699.548.416 99,26%
2.2.9 Insurance & Tax PPh 21 2.2.9 11.824.378 10.750.000 - - - - - - - - - 0,00% 10.750.000 100,00% 11.824.378 100,00%
C PETTY CASH/ADVANCE
TOTAL INDIRECT COST : 1.856.382.711 1.687.709.451 44.883.900 44.883.900 107.412.500 152.296.400 1.615.500 1.615.500 20.130.000 21.745.500 - 174.041.900 10,31% 1.513.667.551 89,69% 1.682.340.811 90,62%
2.3.1 Corporate Tax (PPh Ps 23) 2.3.1 43.000.000 43.000.000 - - - - - - - - - 0,00% 43.000.000 100,00% 43.000.000 100,00%
TOTAL FINANCING COST : 43.000.000 43.000.000 - - - - - - - - - - 0,00% 43.000.000 100,00% 43.000.000 100,00%
E 2.4 LOANS
TOTAL (A) 2.683.808.876 2.443.861.671 49.586.400 49.586.400 122.412.500 171.998.900 22.538.500 22.538.500 33.957.800 56.496.300 - 228.495.200 9,35% 2.215.366.471 90,65% 2.455.313.676 91,49%
Mat'l & Cons Direct Labour Equipment Tools Mob/Demob H/O Cost Maintenance Staff Salary Temp. Fac Temp. Mat'l Site Exp Service Cost Tax & Ins. Pph23 Angs. Pinj. Biaya Provisi Biaya Notaris Comm. Fee Bank Interest
NO MONTH LOC CODE Description Amount
A B C D E F G H I J K L M N O P Q R S
1.4 Mobilization & Demobilization 1,00 Ls 2,78 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04
VII.3 Normal Trenching 8697,44 M3 11,06 0,41 0,41 0,41 0,41 0,41 0,41 0,41 0,41 0,41 0,41 0,41 0,41 0,41 0,41 0,41 0,41 0,41 0,41 0,41 0,41 0,41 0,41 0,41 0,41 0,41 0,41 0,41
VII.5 Temporary Bridge ( Steel Plate ) 2,00 Ea 1,08 0,07 0,07 0,07 0,07 0,07 0,07 0,07 0,07 0,07 0,07 0,07 0,07 0,07 0,07 0,07 0,07
X CROSSING
X.1 Road Crossing
X.2 Asphalt Road Crossing ( Open Cut ) 16,00 M 1,28 0,18 0,18 0,18 0,18 0,18 0,18 0,18
X.3 River Crossing 59,60 M 3,57 0,36 0,36 0,36 0,36 0,36 0,36 0,36 0,36 0,36 0,36
XI M ARKING
XI.1 Marks every 100 m 58,00 Ea 0,80 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04
XI.2 Marks every 500 m 12,00 Ea 0,35 0,02 0,02 0,02 0,02 0,02 0,02 0,02 0,02 0,02 0,02 0,02 0,02 0,02 0,02 0,02 0,02 0,02 0,02 0,02 0,02 0,02 0,02
XI.3 Project Signboard 2,00 Ea 0,60 0,08 0,08 0,08 0,08 0,08 0,08 0,08
XI.4 Marking tape Installation 5738,00 M 0,81 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04 0,04
XII.2 Culvert (River/ Trenches) Repair 59,50 M 1,33 0,19 0,19 0,19 0,19 0,19 0,19 0,19
XII.3 Work Area Clearing 1,00 Ls 0,84 0,08 0,08 0,08 0,08 0,08 0,08 0,08 0,08 0,08 0,08
XIV.1.3 Ball Valve Dia 2" 2,00 Ea 0,15 0,05 0,05 0,05
XIV.3 GASKET
XIV.3.1 Gasket Dia 20" 3,00 Ea 0,15 0,07 0,07
Accummulative Progress Plan 0,00 0,00 0,23 0,45 0,68 0,91 1,13 1,36 1,77 2,18 2,70 3,23 4,03 4,84 5,65 6,45 8,22 9,99 11,57 13,53 15,50 17,46 19,42 21,81 24,27 26,55 28,83 31,10 33,42 35,69 38,42 41,54 44,43 47,32 50,21 53,10 55,99 58,70 61,41 64,11 67,20 70,29 73,38 76,48 79,57 82,59 84,65 86,71 88,77 90,45 91,33 92,09 93,01 94,00 94,34 94,55 94,75 94,95 95,15 95,35 95,66 95,98 96,67 97,36 98,06 98,75 99,4 99,8 99,9 100
Progress Actual
Accummulative Actual Progress
Variance
Plan Manpower 0 0 0 0 0 0 0 65 65 94 94 94 94 92 92 92 92 15 15 15 15 15 0
Actual Manpower
Plan Progress Cumm. 0,00% 0,45% 1,77% 6,45% 19,42% 35,69% 55,99% 76,48% 91,33% 94,95% 98,06% 100,00%
Actual Progress Cumm.
Balance
PIC
SITE MANAGER
Owner :
MANPOWER
SCHEDULE Main Contractor :
Sub Contractor :
Contract no. : Rev. :
PROJECT NAME :____________ Week : Level :
Status on : Period :
WORK SCOPE:__________________________________________________________________________
FEBRUARY__________ MARCH__________ APRIL_____________ MAY__________ Total
NO. URA IA N
1 8 15 22 29 7 14 21 28 4 11 18 25 2 9 16 23 30 Manweek
CONSTRUCTION
A. INDIRECT ;
I Staff
1 Site Manager 1 1 1 1 1 1 1 1 1 1 10
2 Piping Sup'v 1 1 2 2 2 2 2 2 2 2 18
3 QA/QC 1 1 1 1 1 1 1 1 1 1 10
4 Welding Inspector 1 1 1 1 1 1 1 1 1 1 10
5 PPC Coordinator 1 1 1 1 1 1 1 1 1 1 10
6 Safety & Security Coordinator 1 1 1 1 1 1 1 1 1 1 10
7 Heavy Equipment Coordinator 1 1 1 1 1 1 1 1 1 1 10
8 Project Control 1 1 1 1 1 1 1 1 1 1 10
9 Warehouse Sup'v. 1 1 1 1 1 1 1 1 1 1 10
10 Proc. & Finance Supv. 1 1 1 1 1 1 1 1 1 1 10
11 GA & Personnel 1 1 1 1 1 1 1 1 1 1
12 Material Control 1 1 1 1 1 1 1 1 1 1
II Non-Staff
1 Warehouseman 1 1 1 1 1 1 1 1 1 1 10
2 Safetyman 1 1 1 1 1 1 1 1 1 1 10
3 Clerk 1 1 1 1 1 1 1 1 1 1
4 Security 2 2 3 3 3 3 3 3 3 3
5 Time Keeper 1 1 1 1 1 1 1 1 1 1 10
6 Heavy Duty Driver 1 1 5 5 5 5 5 5 5 5
7 Driver 1 1 1 1 1 1 1 1 1 1 10
IMRAN
SITE MANAGER