KODE HARGA
JUMLAH
NO. URAIAN PEKERJAAN KETERANGAN VOLUME SATUAAN
ANALISA
(Rp) (Rp)
I PEKERJAAN PERSIAPAN
TOTAL 1.419.498.833,83
`
`
REKAPITULASI
RENCANA ANGGARAN BIAYA (RAB)
HARGA JUMLAH
NOMOR URAIAN PEKERJAAN
(Rp)
I PEKERJAAN PERSIAPAN -
II PEKERJAAN GALIAN TANAH DAN URUGAN 8.708.229,25
III PEKERJAAN PONDASI 114.879.396,85
IV PEKERJAAN BETON BERTULANG 188.874.038,41
V PEKERJAAN ATAP opsi 1 126.968.859,03
VI PEKERJAAN DINDING 177.720.844,06
VII PEKERJAAN KUSEN 37.557.972,15
VIII PEKERJAAN LANTAI 190.857.941,74
IX PEKERJAAN PLAFOND 70.569.367,50
X PEKERJAAN INSTALASI LISTRIK 43.409.870,00
XI PEKERJAAN SANITASI 22.414.777,00
XII PEKERJAAN ATAP KUBAH 162.367.484,21
XIII PEKERJAAN PENGECATAN 82.061.796,30
XIV PEKERJAAN TERAS 154.127.527,14
XV PEKERJAAN TOILET 34.831.169,00
XVI PEKERJAAN LAIN-LAIN 4.149.561,19
JUMLAH 1.419.498.833,83
TOTAL 1.419.498.833,83
PEMBULATAN 1.419.498.000,00
Terbilang : Satu Milyar Empat Ratus Sembilan Belas Juta Empat Ratus Sembilan Puluh Delapan Ribu Rupiah