You are on page 1of 1

PENAWARAN NEGOSIASI HARGA

POWER HOUSE NEW VERSION


U-PRICE BOBOT PROGRESS
NO DESCRIPTION UNIT QTY AMOUNT REMARKS
(%) (%)
I PREPARATION WORK
1 Bouwplank m' 140,00 51.400,00 7.196.000,00 1,80
Sub Total 7.196.000,00 1,80
II EARTHWORK & FOUNDATION WORK
1 Found. Soil Excavation m3 226,62 - -
2 Refill Found. Soil m3 63,95 15.000,00 959.295,00 0,24
3 Compaction Stamper m2 298,00 7.000,00 2.086.000,00 0,52
4 Sand Fill thk. 50mm m3 9,00 150.000,00 1.350.000,00 0,34
5 Gelam wooden pile (10/10 -4m) btg 192,00 30.000,00 5.760.000,00 1,44
6 Gelam wooden driving pile work (10/10 -4m) m' 768,00 - -
7 Rebar Foot Plate Foundation (P1) kg 474,35 14.000,00 6.640.872,00 1,66
8 Form Work Foot Plate Foundation (P1) m2 21,00 130.000,00 2.730.000,00 0,68
9 Concrete Found. Foot Plate Foundation (P1) K-300 m3 4,24 1.300.000,00 5.505.500,00 1,38
10 Rebar Foot Plate Foundation (P2) kg 109,27 14.000,00 1.529.808,00 0,38
11 Form Work Foot Plate Foundation (P2) m2 3,60 100.000,00 360.000,00 0,09
12 Concrete Found. Foot Plate Foundation (P2) K-300 m3 0,38 1.300.000,00 499.200,00 0,12
13 Rebar Foundation Trafo kg 581,44 14.000,00 8.140.160,00 2,03
14 Form Work Foundation Trafo m2 6,40 130.000,00 832.000,00 0,21
15 Concrete Found. Trafo K-300 m3 4,17 1.300.000,00 5.418.400,00 1,35
Sub Total 41.811.235,00 10,45
III STRUCTURE WORK
1 Sloof Found (S1) 200x400
A Rebar kg 625,44 14.000,00 8.756.160,00 2,19
B Form Work m2 48,00 130.000,00 6.240.000,00 1,56
C Concrete K-250 m3 4,80 1.250.000,00 6.000.000,00 1,50
2 Sloof Found (S2) 200x300
A Rebar kg 40,17 14.000,00 562.408,00 0,14
B Form Work m2 3,30 130.000,00 429.000,00 0,11
C Concrete K-250 m3 5,40 1.250.000,00 6.746.500,00 1,69
3 Dowel D13 kg 0,33 14.000,00 4.620,00 0,00
4 Column (200/200) -
A Rebar kg 445,43 14.000,00 6.235.980,80 1,56
B Form Work m2 56,96 130.000,00 7.404.800,00 1,85
3
C Concrete K-250 m 2,85 1.250.000,00 3.560.000,00 0,89
5 Practice Column (150x150) -
A Rebar kg 15,29 14.000,00 214.044,44 0,05
2
B Form Work m 10,32 130.000,00 1.341.600,00 0,34
C Concrete K-175 m3 0,39 1.000.000,00 387.000,00 0,10
6 Ring Balk (150/200) -
A Rebar kg 440,56 14.000,00 6.167.826,00 1,54
B Form Work m2 40,43 130.000,00 5.255.250,00 1,31
C Concrete K-175 m3 2,21 1.000.000,00 2.205.000,00 0,55
7 Ring Balk Latai (150/150) - -
A Rebar kg 349,70 14.000,00 4.895.863,00 1,22
B Form Work m2 29,48 130.000,00 3.831.750,00 0,96
3
C Concrete K-175 m 1,47 1.000.000,00 1.473.750,00 0,37
Sub Total 71.711.552,24 17,92
IV WALL WORK
1 Mud brick 0.5 Wall m2 293,92 100.000,00 29.392.200,00 7,35
2 Plesteran + acian m2 587,84 105.000,00 61.723.620,00 15,43
3 Ceramics Wall (Toilet) m2 9,92 350.000,00 3.472.000,00 Ex Roman 0,87
Sub Total 94.587.820,00 23,64
V FLOOR WORK
1 Wire Mesh Floor M8 1 Layer (Dalam) m2 107,16 100.000,00 10.716.000,00 2,68
2 Wire Mesh Floor M6 1 Layer (Teras) m2 54,00 80.000,00 4.320.000,00 1,08
3 Wire Mesh Floor M8 2 Layer (extended rabbat) m2 40,00 100.000,00 4.000.000,00 1,00
4 Wire Mesh Floor M6 1 Layer (Ditch for Cable Try) m2 27,03 80.000,00 2.162.400,00 0,54
5 Wire Mesh Floor M6 double Layer (Generator Set Floor) m2 98,00 160.000,00 15.680.000,00 3,92
6 Concrete K-250 m2 41,07 1.250.000,00 51.334.375,00 12,83
7 Floor Finish Acian (inside & outside building) m2 280,00 52.500,00 14.700.000,00 3,67
8 Ceramics 300/300 m2 6,00 250.000,00 1.500.000,00 Ex Roman 0,37
9 Ceramics 600/600 m2 26,00 425.000,00 11.050.000,00 Ex Roman 2,76
10 Ceramics Plint h 100 mm m2 1,95 425.000,00 828.750,00 Ex Roman 0,21
Sub Total 116.291.525,00 29,06
VI DOOR & WINDOW WORK
1 Door & Window Ulin woooden Frame m' 50,12 105.000,00 5.262.600,00 1,32
2 D1 Wood Door double (Glass 6 mm) + accessories set 1,00 3.000.000,00 3.000.000,00 0,75
3 D2 Wood Door single + accessories ea 2,00 1.500.000,00 3.000.000,00 0,75
4 D3 Wood Door single + accessories ea 1,00 1.500.000,00 1.500.000,00 0,37
5 D4 Wood Door single + accessories ea 1,00 1.500.000,00 1.500.000,00 0,37
6 WW1 Window (Glass 6 mm) + accessories ea 1,00 650.000,00 650.000,00 0,16
7 WW3 Window (Glass 6 mm) + accessories ea 2,00 650.000,00 1.300.000,00 0,32
8 VT1 Bouvenlight ea 2,00 350.000,00 700.000,00 0,17
Sub Total 16.912.600,00 4,23
VII SANITATION WORK
1 Installation PVC Pipe 1"-1/2" AW + Accesories m 16,00 30.000,00 480.000,00 0,12
2 Installation PVC Pipe 3" AW + Accesories m 4,00 55.000,00 220.000,00 0,05
3 Installation PVC Pipe 4" AW + Accesories m 24,52 65.000,00 1.593.800,00 0,40
4 Kran air 1/2" include instalation pipe 1/2" ea 1,00 110.000,00 110.000,00 outside the building 0,03
5 Closet Jongkok + Tub ea 1,00 850.000,00 850.000,00 Ex TOTO 0,21
6 Kran air ea 1,00 125.000,00 125.000,00 0,03
7 Stainless Floor Drain ea 1,00 250.000,00 250.000,00 0,06
8 Stainless Steel Valve 3/4" ea 1,00 80.000,00 80.000,00 0,02
9 Septic tank Bio tech, Cap 1000 liter ea 1,00 10.000.000,00 10.000.000,00 2,50
Sub Total 13.708.800,00 3,43
VIII MISCELLANEOUS WORK
1 Ditch Concrete
A Wire Mesh M6 m2 78,00 80.000,00 6.240.000,00 1,56
B Form Work m2 62,40 130.000,00 8.112.000,00 2,03
C Concrete K-250 m3 3,12 1.000.000,00 3.120.000,00 0,78
D Plesteran + acian m2 88,40 105.000,00 9.282.000,00 2,32
2 Oil Trap Foundation Work -
A Rebar Foot Plate Foundation kg 117,00 14.000,00 1.638.000,00 0,41
B Form Work Foot Plate Foundation m2 3,60 130.000,00 468.000,00 0,12
C Concrete Found. Foot Plate Foundation K-250 m3 0,36 1.000.000,00 360.750,00 0,09
3 Oil Trap -
A Wire Mesh M6 m2 36,00 80.000,00 2.880.000,00 0,72
B Form Work m2 33,00 130.000,00 4.290.000,00 1,07
C Concrete K-250 m3 1,50 1.000.000,00 1.500.000,00 0,37
Sub Total 37.890.750,00 9,47
TOTAL CIVIL 400.110.282,24 100,00
* Price Exclude PPN & PPh

Tanah Paser, 29 September 2021


Note : SUB KONTRAKTOR
* Price Exclude PPN & PPh PT. BORNEO ALVA JAYA
* Harga Termasuk bahan matrial dan Upah pekerja

EDY MULYONO,ST
Direktur Utama