LABOUR COSTS VS CONTRACT VS BUDGET

CUT OFF PRODUCTIVITY BASED ON 31 AUGUST 2023 (SSA DAILY PROGRESS MONITORING)

Unit Rate Amount Unit Rate Amount


No. Description Qty Unit
Based On Contract Based On Contract Based On Budget Based On Budget

1 Excavation 7,601.10 m3 11,916 90,572,592 19,000 144,420,928

Horizontal H Beam for Soilslide Protector


2 2,973.60 kg VO 3,000 8,920,800
(WF 150)
Vertical H Beam for Soilslide Protector
3 5,376.00 kg VO 3,000 16,128,000
(WF 150)
4 Thick Plywood for Soilslide Protector 339.84 m2 VO 25,000 8,496,000

5 Lean Concrete 25.28 m3 151,920 3,840,614 300,000 7,584,150

6 Lean Concrete Formwork 81.25 m2 30,240 2,456,940 80,000 6,499,840

7 Plastic Sheet & Lean Concrete 17.32 m3 151,920 2,631,558 300,000 5,196,600

8 Pile Cut Off 98.00 nos 67,200 6,585,600 300,000 29,400,000

9 Rebar (D16) 33.34 ton 1,620,000 54,005,867 3,150,000 105,011,408

10 Rebar (D13) 9.68 ton 1,620,000 15,686,811 3,150,000 30,502,133

11 Formwork 1,625.56 m2 47,376 77,012,341 80,000 130,044,480

12 Waterstop Installation 667.20 m VO 20,000 13,344,000

13 FC 24 Concrete 308.79 m3 132,720 40,983,007 100,000 30,879,300

14 Step Iron Installation 204.00 nos 13,097 2,671,772 30,000 6,120,000

15 Cast Iron Manhole Cover 0.50 unit 229,152 114,576 200,000 100,000

16 Bitumen Coating 704.27 m2 15,360 10,817,587 20,000 14,085,400

17 Epoxy Coating - m2 13,440 - 30,000 -

18 Hume Pipe 500 mm 542.50 m 64,394 34,933,989 150,000 81,375,000

19 Hume Pipe 600 mm 117.30 m 82,342 9,658,733 180,000 21,114,000

20 Hume Pipe 800 mm 62.50 m 100,652 6,290,743 240,000 15,000,000

21 HDPE Installation - m 51,892 - 60,000 -

22 Sand Fill 793.61 m3 115,200 91,423,296 50,000 39,680,250

23 Soil Backfill 5,449.38 m3 16,165 88,091,233 9,500 51,769,121

24 Join Sealant 6.40 m - - 15,000 96,000

25 HDPE Connection 63.00 nos include 20,000 1,260,000

26 Hume Pipe Connection 51.00 nos include 200,000 10,200,000

27 Hume Pipe Mortar Grouting 722.00 nos include 50,000 36,100,000

28 Pipe Connection 14.00 nos include 100,000 1,400,000

29 Stainless Steel Manhole 0.50 unit VO 15,000,000 7,500,000

TOTAL 537,777,258 TOTAL 822,227,410

ACTUAL PAYMENT ACTUAL PAYMENT


BASED ON HRD REPORT BASED ON HRD REPORT

May (68,379,500) May (68,379,500)

June (287,000,000) June (287,000,000)

July (495,000,000) July (495,000,000)

August (463,384,160) August (463,384,160)

TOTAL (1,313,763,660) TOTAL (1,313,763,660)

DEVIATION (775,986,402) DEVIATION (491,536,250)

*minus for loss profit *minus for loss profit


Over Costs Percentage Over Costs Percentage
244% 160%
VS Contract VS Budget
Manhole Progress Monitoring by ZONE PROGRESS MONITORING FORM Progress Date
STORM WATER MANHOLE 001 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Schedule Plan / Target Progress Percentage & Work Steps


Ground Slab Upper Slab
No. Description Plastic Sheet & Bottom Slab Waterstop Ground Slab Hume Pipe Step Iron Wall Pouring Upper Slab Upper Slab Cast Iron
Excavation Pile Cut Off Wall Rebar Pouring Wall Formwork Pouring Bitumen Coating Epoxy Coating Soil Backfill Join Sealant
Start Finish Days Lean Concrete Rebar Installation Formwork Connection Installation Concrete Formwork Rebar Manhole Cover
Concrete Concrete
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
STORM WATER MANHOLE Material on Site
A
(SECTION 1 AREA) 15-06-2023

A.1 ZONE 1
1 MH-01 100% 100% 100% 100% 100% 100% 100% 100% 0% 100% 100% 100% 0% 0% 0% 0% 100% 0% 0% 0%
2 MH-02 100% 100% 100% 100% 100% 100% 100% 100% 0% 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
3 MH-03 100% 100% 100% 100% 50% 100% 100% 100% 0% 50% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
A.2 ZONE 2
4 MH-25 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
5 MH-26 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
6 MH-22 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
7 MH-29 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
8 MH-30 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
A.3 ZONE 3
9 MH-15 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 0% 0%
10 MH-16 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
11 MH-17 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
12 MH-18 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
A.4 ZONE 4
13 MH-11 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 0% 0%
14 MH-12 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 0% 0%
15 MH-13 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 0% 0%
16 MH-14 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 0% 0%
17 MH-20 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 0% 0%
A.5 ZONE 5
18 MH-23 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
19 MH-24 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 0% 0%
A.6 ZONE 6
20 MH-04 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 0% 0%
21 MH-05 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 0% 0%
22 MH-21 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
23 MH-19 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 0% 0%
A.7 ZONE 7
24 MH-09 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 0% 0%
25 MH-10 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 0% 0%
26 MH-06 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 0% 0%
27 MH-07 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 0% 0%
28 MH-08 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
A.8 ZONE 8
29 MH-27 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 0% 0%
30 MH-28
31 MH-31 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
32 MH-32 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

GLOBAL PROGRESS FOR STORM WATER MANHOLE 87% 87% 87% 87% 85% 87% 87% 87% 77% 84% 81% 81% 0% 0% 0% 0% 81% 0% 29% 0%

31/08/2023
Checked by,
PT. Sepuluh Sumber Anugerah

Herdy Dwiyana
Quantity Surveyor
Manhole Progress Monitoring by ZONE PROGRESS MONITORING FORM Progress Date
SEWAGE MANHOLE 002 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Schedule Plan / Target Progress Percentage & Work Steps


Ground Slab Upper Slab
No. Description Plastic Sheet & Bottom Slab Waterstop Ground Slab HDPE 200 mm Step Iron Wall Pouring Upper Slab Upper Slab Cast Iron
Excavation Pile Cut Off Wall Rebar Pouring Wall Formwork Pouring Bitumen Coating Epoxy Coating Soil Backfill Join Sealant
Start Finish Days Lean Concrete Rebar Installation Formwork Connection Installation Concrete Formwork Rebar Manhole Cover
Concrete Concrete
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
SEWAGE MANHOLE (SECTION 1
A
AREA)
A.1 ZONE 1
1 SM-B5 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
2 SM-18 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
3 SM-19 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
4 SM-11 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
5 SM-10 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
A.2 ZONE 2
6 SM-15 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
7 SM-B4 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
8 SM-09 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
9 SM-08 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

A.3 ZONE 3
10 SM-12 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
11 SM-16 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
12 SM-B8 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
13 SM-B7 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
14 SM-B6 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
A.4 ZONE 4
15 SM-B3 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
16 SM-14 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
17 SM-07 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
18 SM-06 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
19 SM-05 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
20 SM-04 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0%
A.5 ZONE 5
21 SM-A1 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
22 SM-01 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
23 SM-02 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
24 SM-13 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0%
25 SM-A2 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0%
A.6 ZONE 6
26 SM-03 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
27 SM-B1 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%
28 SM-B2 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 100% 0%

GLOBAL PROGRESS FOR SEWAGE MANHOLE 100% 100% 100% 100% 100% 100% 100% 100% 93% 93% 93% 93% 0% 0% 0% 0% 82% 0% 82% 0%

31/08/2023
Checked by,
PT. Sepuluh Sumber Anugerah

Herdy Dwiyana
Quantity Surveyor
Manhole Progress Monitoring PROGRESS MONITORING FORM Progress Date
SEWAGE WORKS SECTION 2 AREA 002A 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Schedule Plan / Target Progress Percentage & Work Steps


Ground Slab Upper Slab
No. Description Plastic Sheet & Bottom Slab Waterstop Ground Slab HDPE 200 mm Step Iron Wall Pouring Upper Slab Upper Slab Cast Iron
Excavation Pile Cut Off Wall Rebar Pouring Wall Formwork Pouring Bitumen Coating Epoxy Coating Soil Backfill Join Sealant
Start Finish Days Lean Concrete Rebar Installation Formwork Connection Installation Concrete Formwork Rebar Manhole Cover
Concrete Concrete
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Material On Site
A SEWAGE WORKS SECTION 2 AREA
04-07-2023
1 SMH-01 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
2 SMH-02 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
3 SMH-03 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 0% 0%
4 SMH-04 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
5 SMH-05 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
6 SMH-06 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
7 SMH-07 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
8 SMH-08 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
9 SEWAGE TANK 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
10 SMH-10 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 0% 0%
11 SMH-11 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0%
12 SMH-12 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0%
13 SMH-13 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
14 SMH-14 100% 100% 100% 100% 50% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0%
15 SMH-15 100% 100% 100% 100% 50% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 0% 0% 0% 0%
16 SEPTIC TANK MS 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
17 SEPTIC TANK MW 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 0% 0% 0%
18 SEPTIC TANK FS 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

GLOBAL PROGRESS FOR SEWAGE WORKS SECTION 2 AREA 78% 61% 61% 50% 44% 50% 50% 39% 39% 39% 39% 39% 0% 0% 0% 0% 17% 0% 0% 0%
14.00 11.00 7.00 7.00 - -
31/08/2023 50% for fabrication 50% for fabrication
50% for fabrication 50% for fabrication
Checked by,
PT. Sepuluh Sumber Anugerah

Herdy Dwiyana
Quantity Surveyor
Progress Monitoring PROGRESS MONITORING FORM Progress Date
SEWAGE TANK 003 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Schedule Plan / Target Progress Percentage & Work Steps

H Beam Jacked Ground Slab Upper Slab Upper Slab


No. Description Plastic Sheet & Bottom Slab Waterstop Ground Slab HDPE Step Iron Wall Pouring Upper Slab Upper Slab Stainless Steel Upper Slab Upper Slab Cast Iron
Excavation For Soilslide Sand Bag Fill Pile Cut Off Wall Rebar Pouring Wall Formwork Pouring Pouring Bitumen Coating Epoxy Coating Soil Backfill
Start Finish Days Lean Concrete Rebar Installation Formwork Connection Installation Concrete Formwork (2nd) Rebar (2nd) Manhole Cover Formwork (3rd) Rebar (3rd) Manhole Cover
Protector Concrete Concrete (2nd) Concrete (3rd)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
A SEWAGE TANK SECTION 1 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 50% 100% 100% 100% 50% 100% 100% 0% 90%

B SEWAGE TANK SECTION 3 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%

GLOBAL PROGRESS FOR SEWAGE TANK 50% 50% 50% 50% 50% 50% 50% 50% 50% 50% 50% 50% 50% 50% 50% 50% 25% 50% 50% 50% 25% 50% 50% 0% 45%

31/08/2023
Checked by,
PT. Sepuluh Sumber Anugerah

Herdy Dwiyana
Quantity Surveyor
Progress Monitoring PROGRESS MONITORING FORM Progress Date
SEPTIC TANK 004 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Schedule Plan / Target Progress Percentage & Work Steps


Ground Slab Upper Slab
No. Description Plastic Sheet & Bottom Slab Waterstop Ground Slab HDPE Wall Pouring Upper Slab Upper Slab Cast Iron
Excavation Pile Cut Off Wall Rebar Pouring Wall Formwork Pouring Bitumen Coating Soil Backfill
Start Finish Days Lean Concrete Rebar Installation Formwork Connection Concrete Formwork Rebar Manhole Cover
Concrete Concrete
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
SEPTIC TANK DETAIL 1 (Main
A 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 100%
Building) ST-01
SEPTIC TANK DETAIL 2 (Canteen
B 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 100%
Area 1) ST-03
SEPTIC TANK DETAIL 3 (Masjid Area)
C 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 100%
ST-04
SEPTIC TANK DETAIL 4 (Masjid Area)
D 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 100%
ST-05
SEPTIC TANK DETAIL 5 (Main Gate
E 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 100%
Building) ST-06
SEPTIC TANK DETAIL 5 (Main Gate
F 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 100%
Building) ST-07
SEPTIC TANK DETAIL 2 (Canteen
G 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 100%
Area) ST-02

GLOBAL PROGRESS FOR SEPTIC TANK 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0% 100% 100%

31/08/2023
Checked by,
PT. Sepuluh Sumber Anugerah

Herdy Dwiyana
Quantity Surveyor
Progress Monitoring PROGRESS MONITORING FORM Progress Date
Hume RC Pipe Installation 005 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Schedule Plan / Target Progress Percentage & Work Steps

No. Description Qty Hume Pipe Hume Pipe


Excavation Lean Concrete Sand Fill Back Fill
Start Finish Days Installation Mortar Grouting

1 2 3 4 5 6
HUME RC PIPE 500 mm (CCO From
A
450 mm to 500 mm)
#
1 MH.01 - MH.02 100% 100% 100% 100% 100% 100%
#
2 MH.02 - MH.03 ##### ## 100% 100% 0% 100% 100% 0%
3 MH.03 - MH.04 ##### ## 100% 100% 100% 100% 100% 100%
4 MH.04 - MH.05 ##### ## 100% 100% 100% 100% 100% 100%
5 MH.09 - MH.10 ##### ## 100% 100% 100% 100% 100% 100%
6 MH.10 - MH.06 ##### ## 100% 100% 100% 100% 100% 100%
7 MH.11 - MH.12 ##### ## 100% 100% 100% 100% 100% 100%
8 MH.12 - MH.13 ##### ## 100% 100% 100% 100% 100% 100%
9 MH.13 - MH.14 ##### ## 100% 100% 100% 100% 100% 100%
10 MH.20 - MH.14 ##### ## 100% 100% 100% 100% 100% 100%
11 MH.14 - MH.15 ##### ## 100% 100% 100% 100% 100% 100%
12 MH.15 - MH.16 ##### ## 100% 100% 100% 100% 100% 100%
13 MH.22 - MH.23 ##### ## 100% 100% 100% 100% 100% 100%
14 MH.23 - MH.24 ##### ## 100% 100% 100% 100% 100% 100%
15 MH.24 - MH.07 ##### ## 100% 100% 100% 100% 100% 100%
16 MH.25 - MH.26 ##### ## 100% 100% 100% 100% 100% 100%
17 MH.26 - MH.27 ##### ## 100% 100% 100% 100% 100% 100%
18 MH.27 - MH.28 ##### ## 0% 0% 0% 0% 0% 0%
19 MH.29 - MH.30 ##### ## 100% 100% 100% 100% 100% 100%
20 MH.30 - MH.26 #### ### 100% 100% 100% 100% 100% 100%
21 MH.31 - MH.32 ##### ## 0% 0% 0% 0% 0% 0%
22 MH.32 - MH.28 #### ### 0% 0% 0% 0% 0% 0%
23 MH.19 - MH.21 ##### ## 100% 100% 100% 100% 100% 100%
B HUME RC PIPE 600 mm
1 MH.16 - MH.17 ##### ## 100% 100% 100% 100% 100% 100%
2 MH.17 - MH.18 ##### ## 100% 100% 100% 100% 100% 100%
3 MH.18 - MH.19 ##### ## 100% 100% 100% 100% 100% 100%
4 MH.19 - MH.05 ##### ## 100% 100% 100% 100% 100% 100%
5 MH.28 - River #### ### 0% 0% 0% 0% 0% 0%
C HUME RC PIPE 800 mm
1 MH.05 - MH.06 ##### ## 100% 100% 100% 100% 100% 100%
2 MH.06 - MH.07 ##### ## 100% 100% 100% 100% 100% 100%
3 MH.07 - MH.08 ##### ## 0% 0% 0% 0% 0% 0%
4 MH.07 - END #### ### 0% 0% 0% 0% 0% 0%

GLOBAL PROGRESS FOR Hume RC Pipe Installation 81% 81% 78% 81% 81% 78%

31/08/2023
Checked by,
PT. Sepuluh Sumber Anugerah

Herdy Dwiyana
Quantity Surveyor
Progress Monitoring PROGRESS MONITORING FORM Progress Date
HDPE 200 mm Installation 006 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Schedule Plan / Target Progress Percentage & Work Steps


No. Description Qty HDPE
Excavation Back Fill
Start Finish Days Installation
1 2 3
HDPE FOR STORM WATER (SECTION
A
1)

1 CB.1 4.50 0% 0% 0%

2 CB.2 5.50 0% 0% 0%

3 CB.3 10.30 0% 0% 0%

4 CB.4 10.80 0% 0% 0%

5 CB.5 3.50 0% 0% 0%

6 CB.6 10.00 0% 0% 0%

7 CB.7 3.00 0% 0% 0%

8 CB.8 3.90 0% 0% 0%

9 CB.9 6.10 0% 0% 0%

10 CB.10 6.90 0% 0% 0%

11 CB.11 10.00 0% 0% 0%

12 CB.12 10.00 0% 0% 0%

13 CB.13 6.70 0% 0% 0%

14 CB.14 5.90 0% 0% 0%

15 CB.15 3.30 0% 0% 0%

16 CB.16 10.00 0% 0% 0%

17 CB.17 3.50 0% 0% 0%

18 CB.18 10.00 0% 0% 0%

19 CB.19 9.70 0% 0% 0%

20 CB.20 7.20 0% 0% 0%

21 CB.21 7.20 0% 0% 0%

22 CB.22 13.40 0% 0% 0%

23 CB.23 2.80 0% 0% 0%

24 CB.24 4.70 0% 0% 0%

25 CB.25 9.80 0% 0% 0%

26 CB.26 3.70 0% 0% 0%

27 CB.27 4.70 0% 0% 0%

28 CB.28 9.50 0% 0% 0%

29 CB.29 8.60 0% 0% 0%

30 CB.30 10.00 0% 0% 0%

31 CB.31 11.40 0% 0% 0%

32 CB.32 6.90 0% 0% 0%

33 CB.33 7.30 0% 0% 0%

34 CB.34 7.50 0% 0% 0%

35 CB.35 12.10 0% 0% 0%

36 CB.36 7.50 0% 0% 0%
Progress Monitoring PROGRESS MONITORING FORM Progress Date
HDPE 200 mm Installation 006 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Schedule Plan / Target Progress Percentage & Work Steps


No. Description Qty HDPE
Excavation Back Fill
Start Finish Days Installation
1 2 3
37 CB.37 7.50 0% 0% 0%

38 CB.38 6.70 0% 0% 0%

39 CB.39 7.50 0% 0% 0%

40 CB.40 7.50 0% 0% 0%

41 CB.41 4.80 0% 0% 0%

42 CB.42 7.50 0% 0% 0%

43 CB.43 7.50 0% 0% 0%

44 CB.44 6.80 0% 0% 0%

45 CB.45 3.20 0% 0% 0%

46 CB.46 11.50 0% 0% 0%

47 CB.47 11.50 0% 0% 0%

48 CB.48 11.50 0% 0% 0%

49 CB.49 7.50 0% 0% 0%

50 CB.50 7.50 0% 0% 0%

51 CB.51 11.50 0% 0% 0%

52 CB.52 2.70 0% 0% 0%

53 CB.53 7.50 0% 0% 0%

54 CB.54 6.20 0% 0% 0%

55 CB.55 6.80 0% 0% 0%

56 CB.56 7.40 0% 0% 0%

57 CB.57 7.30 0% 0% 0%

58 CB.58 6.70 0% 0% 0%

59 CB.59 4.50 0% 0% 0%

60 CB.60 8.70 0% 0% 0%

61 CB.61 3.00 0% 0% 0%

62 CB.62 3.00 0% 0% 0%

63 CB.63 8.70 0% 0% 0%

64 CB.64 8.70 0% 0% 0%

65 CB.65 3.00 0% 0% 0%

66 CB.66 2.40 0% 0% 0%

67 CB.67 8.10 0% 0% 0%

68 CB.68 8.70 0% 0% 0%

69 CB.69 3.00 0% 0% 0%

70 CB.70 7.60 0% 0% 0%

71 CB.71 8.70 0% 0% 0%

72 CB.72 8.20 0% 0% 0%

73 CB.73 7.20 0% 0% 0%
Progress Monitoring PROGRESS MONITORING FORM Progress Date
HDPE 200 mm Installation 006 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Schedule Plan / Target Progress Percentage & Work Steps


No. Description Qty HDPE
Excavation Back Fill
Start Finish Days Installation
1 2 3
74 CB.74 9.90 0% 0% 0%

75 CB.75 8.20 0% 0% 0%

76 CB.76 7.20 0% 0% 0%

77 CB.77 9.90 0% 0% 0%

78 CB.77 9.90 0% 0% 0%

79 CB.78 7.20 0% 0% 0%

80 CB.79 8.20 0% 0% 0%

81 CB.80 9.90 0% 0% 0%

82 CB.81 7.20 0% 0% 0%

83 CB.82 8.20 0% 0% 0%

84 CB.83 9.90 0% 0% 0%

85 CB.84 7.20 0% 0% 0%

86 CB.85 8.20 0% 0% 0%

87 CB.86 9.90 0% 0% 0%

88 CB.87 7.90 0% 0% 0%

89 CB.88 8.80 0% 0% 0%

90 CB.89 5.50 0% 0% 0%

91 CB.90 2.70 0% 0% 0%

92 CB.91 10.60 0% 0% 0%

93 CB.92 7.70 0% 0% 0%

94 CB.93 3.50 0% 0% 0%

95 CB.94 3.70 0% 0% 0%

96 CB.B4 - MH.06 28.80 0% 0% 0%

97 CB.A6 - MH.17 7.70 0% 0% 0%

98 CB.A3 - MH.16 8.50 0% 0% 0%

99 CB.A2 - MH.15 10.40 0% 0% 0%

100 CB.B2 - MH.15 6.10 0% 0% 0%

101 CB.A8 - MH.04 12.70 0% 0% 0%

102 CB.A7 - MH.21 14.20 0% 0% 0%

103 CB.B3 - MH.21 4.20 0% 0% 0%

104 CB.B1 - MH.02 12.00 0% 0% 0%

105 CB.A1 - MH.03 14.50 0% 0% 0%

106 CB.A4 - Outside 2.50 0% 0% 0%

107 CB.A5 - Outside 2.50 0% 0% 0%

108 GH-1 1.70 0% 0% 0%

109 GH-2 1.70 0% 0% 0%

110 GH-3 1.70 0% 0% 0%


Progress Monitoring PROGRESS MONITORING FORM Progress Date
HDPE 200 mm Installation 006 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Schedule Plan / Target Progress Percentage & Work Steps


No. Description Qty HDPE
Excavation Back Fill
Start Finish Days Installation
1 2 3
111 GH-4 - DELETED 0% 0% 0%

112 GH-5 3.30 0% 0% 0%

113 GH-6 6.40 0% 0% 0%

114 GH-7 10.80 0% 0% 0%

115 GH-8 5.10 0% 0% 0%

116 GH-9 3.20 0% 0% 0%

117 GH-10 8.50 0% 0% 0%

118 GH-11 - DELETED 0% 0% 0%

119 GH-12 13.10 0% 0% 0%

120 GH-13 12.50 0% 0% 0%

121 GH-14 11.70 0% 0% 0%

122 GH-15 7.10

123 GH-16 6.90

124 GH-17 6.90

125 GH-18 6.90

126 GH-19 6.90

127 GH-20 12.10

128 GH-21 2.00

129 GH-22 2.00

130 GH-23 2.00

131 GH-24 2.00

132 GH-25 1.20

133 GH-26 15.00

134 GH-27 7.50

135 GH-28 2.80

136 GH-29 5.70

137 GH-30 4.10

138 GH-31 2.50

139 GH-32 2.50

140 GH-33 1.70

141 Add GH Canteen 9.00

B HDPE FOR SEWAGE (SECTION 1)

1 SM.A1 - SM.01 2.20 0% 0% 0%

2 SM.01 - SM.02 22.60 0% 0% 0%

3 SM.A2 - SM.13 2.20 0% 0% 0%

4 SM.13 - SM.02 13.00 0% 0% 0%

5 SM.02 - SM.03 11.40 0% 0% 0%


Progress Monitoring PROGRESS MONITORING FORM Progress Date
HDPE 200 mm Installation 006 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Schedule Plan / Target Progress Percentage & Work Steps


No. Description Qty HDPE
Excavation Back Fill
Start Finish Days Installation
1 2 3
6 SM.03 - SM.04 45.80 0% 0% 0%

7 SM.04 - SM.05 12.80 0% 0% 0%

8 SM.05 - SM.06 5.30 0% 0% 0%

9 SM.06 - SM.07 18.70 0% 0% 0%

10 SM.14 - SM.07 9.20 0% 0% 0%

11 SM.B3 - SM.14 2.00 0% 0% 0%

12 SM.07 - SM.08 35.00 0% 0% 0%

13 SM.08 - SM.09 33.40 0% 0% 0%

14 SM.09 - SM.10 27.00 0% 0% 0%

15 SM.B4 - SM.15 3.00 0% 0% 0%

16 SM.15 - SM.11 14.40 0% 0% 0%

17 SM.B5 - SM.18 20.00 0% 0% 0%

18 SM.19 - SM.11 28.00 0% 0% 0%

19 SM.11 - SM.10 6.50 0% 0% 0%

20 SM.10 - SM.12 9.00 0% 0% 0%

21 SM.B6 - SM.B7 31.40 0% 0% 0%

22 SM.B7 - SM.B8 13.30 0% 0% 0%

23 SM.B8 - SM.16 2.00 0% 0% 0%

24 SM.16 - SM.12 4.20 0% 0% 0%

25 SM.12 - SEWAGE 4.70 0% 0% 0%

C HDPE FOR SEWAGE (SECTION 2)

1 SMH.01 - SMH.02 24.80 0% 0% 0%

2 SMH.02 - SMH.03 18.00 0% 0% 0%

3 SMH.10 - SMH.03 4.80 0% 0% 0%

4 SMH.03 - SMH.04 21.70 0% 0% 0%

5 SMH.11 - SMH.12 21.20 100% 100% 100%

6 SMH.12 - SMH.13 8.00 0% 0% 0%

7 SMH.13 - SMH.04 4.10 0% 0% 0%

8 SMH.04 - SMH.05 20.00 0% 0% 0%

9 SMH.05 - SMH.06 23.20 0% 0% 0%

10 SMH.06 - SMH.07 30.00 0% 0% 0%

11 SMH.07 - SMH.09 34.90 0% 0% 0%

12 SMH.08 - SMH.09 8.80 0% 0% 0%

13 SMH.14 - SMH.15 14.40 100% 100% 100%

14 SMH.15 - SMH.09 25.90 0% 0% 0%

D HDPE FOR SEWAGE (SECTION 3)


Progress Monitoring PROGRESS MONITORING FORM Progress Date
HDPE 200 mm Installation 006 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Schedule Plan / Target Progress Percentage & Work Steps


No. Description Qty HDPE
Excavation Back Fill
Start Finish Days Installation
1 2 3
1 SMH.01 - SMH.02 8.70 0% 0% 0%

2 SMH.02 - SMH.03 18.20 0% 0% 0%

3 SMH.02 - SEWAGE 53.00 0% 0% 0%

GLOBAL PROGRESS FOR HDPE 200 mm Installation 1% #DIV/0! 1% 1%

31/08/2023
Checked by,
PT. Sepuluh Sumber Anugerah

Herdy Dwiyana
Quantity Surveyor
Progress Monitoring PROGRESS MONITORING FORM Progress Date
CATCH BASIN (PRECAST) 008 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Schedule Plan / Target Progress Percentage & Work Steps


L Angle Precast
No. Description Precast Pouring Put Catch Basin Steel Grating
Rebar Install Galvanized Formwork Excavation Backfill
Start Finish Days Formwork Install Concrete in Hole Instalation
Install Dismantle
1 2 3 4 5 6 7 8 9

A CATCH BASIN PRECAST

1 Catch Basin CB-01 100% 100% 100% 100% 0% 0% 0% 0% 0%

2 Catch Basin CB-02 100% 100% 100% 100% 0% 0% 0% 0% 0%

3 Catch Basin CB-03 100% 100% 100% 100% 0% 0% 0% 0% 0%

4 Catch Basin CB-04 100% 100% 100% 100% 0% 0% 0% 0% 0%

5 Catch Basin CB-05 100% 100% 100% 100% 0% 0% 0% 0% 0%

6 Catch Basin CB-06 100% 100% 100% 100% 0% 0% 0% 0% 0%

7 Catch Basin CB-07 100% 100% 100% 100% 0% 0% 0% 0% 0%

8 Catch Basin CB-08 100% 100% 100% 100% 0% 0% 0% 0% 0%

9 Catch Basin CB-09 100% 100% 100% 100% 0% 0% 0% 0% 0%

10 Catch Basin CB-10 100% 100% 100% 100% 0% 0% 0% 0% 0%

11 Catch Basin CB-11 100% 100% 100% 100% 0% 0% 0% 0% 0%

12 Catch Basin CB-12 100% 100% 100% 100% 0% 0% 0% 0% 0%

13 Catch Basin CB-13 100% 100% 100% 100% 0% 0% 0% 0% 0%

14 Catch Basin CB-14 100% 100% 100% 100% 0% 0% 0% 0% 0%

15 Catch Basin CB-15 100% 100% 100% 100% 0% 0% 0% 0% 0%

16 Catch Basin CB-16 100% 100% 100% 100% 0% 0% 0% 0% 0%

17 Catch Basin CB-17 100% 100% 100% 100% 0% 0% 0% 0% 0%

18 Catch Basin CB-18 100% 100% 100% 100% 0% 0% 0% 0% 0%

19 Catch Basin CB-19 100% 100% 100% 100% 0% 0% 0% 0% 0%

20 Catch Basin CB-20 100% 100% 100% 100% 0% 0% 0% 0% 0%


Progress Monitoring PROGRESS MONITORING FORM Progress Date
CATCH BASIN (PRECAST) 008 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Schedule Plan / Target Progress Percentage & Work Steps


L Angle Precast
No. Description Precast Pouring Put Catch Basin Steel Grating
Rebar Install Galvanized Formwork Excavation Backfill
Start Finish Days Formwork Install Concrete in Hole Instalation
Install Dismantle
1 2 3 4 5 6 7 8 9
21 Catch Basin CB-21 100% 100% 100% 100% 0% 0% 0% 0% 0%

22 Catch Basin CB-22 100% 100% 100% 100% 0% 0% 0% 0% 0%

23 Catch Basin CB-23 100% 100% 100% 100% 0% 0% 0% 0% 0%

24 Catch Basin CB-24 100% 100% 100% 100% 0% 0% 0% 0% 0%

25 Catch Basin CB-25 100% 100% 100% 100% 0% 0% 0% 0% 0%

26 Catch Basin CB-26 100% 100% 100% 100% 0% 0% 0% 0% 0%

27 Catch Basin CB-27 100% 100% 100% 100% 0% 0% 0% 0% 0%

28 Catch Basin CB-28 100% 100% 100% 100% 0% 0% 0% 0% 0%

29 Catch Basin CB-29 100% 100% 100% 100% 0% 0% 0% 0% 0%

30 Catch Basin CB-30 100% 100% 100% 100% 0% 0% 0% 0% 0%

31 Catch Basin CB-31 0% 0% 0% 0% 0% 0% 0% 0% 0%

32 Catch Basin CB-32 0% 0% 0% 0% 0% 0% 0% 0% 0%

33 Catch Basin CB-33 0% 0% 0% 0% 0% 0% 0% 0% 0%

34 Catch Basin CB-34 0% 0% 0% 0% 0% 0% 0% 0% 0%

35 Catch Basin CB-35 0% 0% 0% 0% 0% 0% 0% 0% 0%

36 Catch Basin CB-36 0% 0% 0% 0% 0% 0% 0% 0% 0%

37 Catch Basin CB-37 0% 0% 0% 0% 0% 0% 0% 0% 0%

38 Catch Basin CB-38 0% 0% 0% 0% 0% 0% 0% 0% 0%

39 Catch Basin CB-39 0% 0% 0% 0% 0% 0% 0% 0% 0%

40 Catch Basin CB-40 0% 0% 0% 0% 0% 0% 0% 0% 0%

41 Catch Basin CB-41 0% 0% 0% 0% 0% 0% 0% 0% 0%


Progress Monitoring PROGRESS MONITORING FORM Progress Date
CATCH BASIN (PRECAST) 008 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Schedule Plan / Target Progress Percentage & Work Steps


L Angle Precast
No. Description Precast Pouring Put Catch Basin Steel Grating
Rebar Install Galvanized Formwork Excavation Backfill
Start Finish Days Formwork Install Concrete in Hole Instalation
Install Dismantle
1 2 3 4 5 6 7 8 9
42 Catch Basin CB-42 0% 0% 0% 0% 0% 0% 0% 0% 0%

43 Catch Basin CB-43 0% 0% 0% 0% 0% 0% 0% 0% 0%

44 Catch Basin CB-44 0% 0% 0% 0% 0% 0% 0% 0% 0%

45 Catch Basin CB-45 0% 0% 0% 0% 0% 0% 0% 0% 0%

46 Catch Basin CB-46 0% 0% 0% 0% 0% 0% 0% 0% 0%

47 Catch Basin CB-47 0% 0% 0% 0% 0% 0% 0% 0% 0%

48 Catch Basin CB-48 0% 0% 0% 0% 0% 0% 0% 0% 0%

49 Catch Basin CB-49 0% 0% 0% 0% 0% 0% 0% 0% 0%

50 Catch Basin CB-50 0% 0% 0% 0% 0% 0% 0% 0% 0%

51 Catch Basin CB-51 0% 0% 0% 0% 0% 0% 0% 0% 0%

52 Catch Basin CB-52 0% 0% 0% 0% 0% 0% 0% 0% 0%

53 Catch Basin CB-53 0% 0% 0% 0% 0% 0% 0% 0% 0%

54 Catch Basin CB-54 0% 0% 0% 0% 0% 0% 0% 0% 0%

55 Catch Basin CB-55 0% 0% 0% 0% 0% 0% 0% 0% 0%

56 Catch Basin CB-56 0% 0% 0% 0% 0% 0% 0% 0% 0%

57 Catch Basin CB-57 0% 0% 0% 0% 0% 0% 0% 0% 0%

58 Catch Basin CB-58 0% 0% 0% 0% 0% 0% 0% 0% 0%

59 Catch Basin CB-59 0% 0% 0% 0% 0% 0% 0% 0% 0%

60 Catch Basin CB-60 0% 0% 0% 0% 0% 0% 0% 0% 0%

61 Catch Basin CB-61 0% 0% 0% 0% 0% 0% 0% 0% 0%

62 Catch Basin CB-62 0% 0% 0% 0% 0% 0% 0% 0% 0%


Progress Monitoring PROGRESS MONITORING FORM Progress Date
CATCH BASIN (PRECAST) 008 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Schedule Plan / Target Progress Percentage & Work Steps


L Angle Precast
No. Description Precast Pouring Put Catch Basin Steel Grating
Rebar Install Galvanized Formwork Excavation Backfill
Start Finish Days Formwork Install Concrete in Hole Instalation
Install Dismantle
1 2 3 4 5 6 7 8 9
63 Catch Basin CB-63 0% 0% 0% 0% 0% 0% 0% 0% 0%

64 Catch Basin CB-64 0% 0% 0% 0% 0% 0% 0% 0% 0%

65 Catch Basin CB-65 0% 0% 0% 0% 0% 0% 0% 0% 0%

66 Catch Basin CB-66 0% 0% 0% 0% 0% 0% 0% 0% 0%

67 Catch Basin CB-67 0% 0% 0% 0% 0% 0% 0% 0% 0%

68 Catch Basin CB-68 0% 0% 0% 0% 0% 0% 0% 0% 0%

69 Catch Basin CB-69 0% 0% 0% 0% 0% 0% 0% 0% 0%

70 Catch Basin CB-70 0% 0% 0% 0% 0% 0% 0% 0% 0%

71 Catch Basin CB-71 0% 0% 0% 0% 0% 0% 0% 0% 0%

72 Catch Basin CB-72 0% 0% 0% 0% 0% 0% 0% 0% 0%

73 Catch Basin CB-73 0% 0% 0% 0% 0% 0% 0% 0% 0%

74 Catch Basin CB-74 0% 0% 0% 0% 0% 0% 0% 0% 0%

75 Catch Basin CB-75 0% 0% 0% 0% 0% 0% 0% 0% 0%

76 Catch Basin CB-76 0% 0% 0% 0% 0% 0% 0% 0% 0%

77 Catch Basin CB-77 0% 0% 0% 0% 0% 0% 0% 0% 0%

78 Catch Basin CB-78 0% 0% 0% 0% 0% 0% 0% 0% 0%

79 Catch Basin CB-79 0% 0% 0% 0% 0% 0% 0% 0% 0%

80 Catch Basin CB-80 0% 0% 0% 0% 0% 0% 0% 0% 0%

81 Catch Basin CB-81 0% 0% 0% 0% 0% 0% 0% 0% 0%

82 Catch Basin CB-82 0% 0% 0% 0% 0% 0% 0% 0% 0%

83 Catch Basin CB-83 0% 0% 0% 0% 0% 0% 0% 0% 0%


Progress Monitoring PROGRESS MONITORING FORM Progress Date
CATCH BASIN (PRECAST) 008 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Schedule Plan / Target Progress Percentage & Work Steps


L Angle Precast
No. Description Precast Pouring Put Catch Basin Steel Grating
Rebar Install Galvanized Formwork Excavation Backfill
Start Finish Days Formwork Install Concrete in Hole Instalation
Install Dismantle
1 2 3 4 5 6 7 8 9
84 Catch Basin CB-84 0% 0% 0% 0% 0% 0% 0% 0% 0%

85 Catch Basin CB-85 0% 0% 0% 0% 0% 0% 0% 0% 0%

86 Catch Basin CB-86 0% 0% 0% 0% 0% 0% 0% 0% 0%

87 Catch Basin CB-87 0% 0% 0% 0% 0% 0% 0% 0% 0%

88 Catch Basin CB-88 0% 0% 0% 0% 0% 0% 0% 0% 0%

89 Catch Basin CB-89 0% 0% 0% 0% 0% 0% 0% 0% 0%

90 Catch Basin CB-90 0% 0% 0% 0% 0% 0% 0% 0% 0%

91 Catch Basin CB-91 0% 0% 0% 0% 0% 0% 0% 0% 0%

92 Catch Basin CB-92 0% 0% 0% 0% 0% 0% 0% 0% 0%

93 Catch Basin CB-93 0% 0% 0% 0% 0% 0% 0% 0% 0%

94 Catch Basin CB-94 0% 0% 0% 0% 0% 0% 0% 0% 0%

95 Catch Basin CB-95 0% 0% 0% 0% 0% 0% 0% 0% 0%

96 Catch Basin CB-96 0% 0% 0% 0% 0% 0% 0% 0% 0%

97 Catch Basin CB-97 0% 0% 0% 0% 0% 0% 0% 0% 0%

98 Catch Basin CB-98 0% 0% 0% 0% 0% 0% 0% 0% 0%

99 Catch Basin CB-99 0% 0% 0% 0% 0% 0% 0% 0% 0%

100 Catch Basin CB-100 0% 0% 0% 0% 0% 0% 0% 0% 0%

101 Catch Basin CB-101 0% 0% 0% 0% 0% 0% 0% 0% 0%

102 Catch Basin CB-102 0% 0% 0% 0% 0% 0% 0% 0% 0%

103 Catch Basin CB-103 0% 0% 0% 0% 0% 0% 0% 0% 0%

104 Catch Basin CB-104 0% 0% 0% 0% 0% 0% 0% 0% 0%


Progress Monitoring PROGRESS MONITORING FORM Progress Date
CATCH BASIN (PRECAST) 008 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Schedule Plan / Target Progress Percentage & Work Steps


L Angle Precast
No. Description Precast Pouring Put Catch Basin Steel Grating
Rebar Install Galvanized Formwork Excavation Backfill
Start Finish Days Formwork Install Concrete in Hole Instalation
Install Dismantle
1 2 3 4 5 6 7 8 9
105 Catch Basin CB-105 0% 0% 0% 0% 0% 0% 0% 0% 0%

106 Catch Basin CB-106 0% 0% 0% 0% 0% 0% 0% 0% 0%

107 Catch Basin CB-107 0% 0% 0% 0% 0% 0% 0% 0% 0%

GLOBAL PROGRESS FOR CATCH BASIN (PRECAST) 28% 28% 28% 28% 0% 0% 0% 0% 0%

31/08/2023
Checked by,
PT. Sepuluh Sumber Anugerah

Herdy Dwiyana
Quantity Surveyor
Progress Calculation PROGRESS CALCULATION FORM Progress Date
STORM WATER MANHOLE 001 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
STORM WATER MANHOLE (SECTION
A 0.70
1 AREA)
A.1 ZONE 1
1 MH-01 Lean Concrete X & Y = 2.4 m Follow Drawing Before Wall Thickness Have Changed
Excavation 5.52 5.52 1.60 0.70 23.85 1.00 1.00 1.00 1.00 23.85 m3 100% 23.85
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 0% -
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
D16 Bottom Slab Rebar 2.10 2.10 1.19 1.58 8.00 2.00 2.00 32.00 106.06 kg 100% 106.06
Wall Rebar (Horizontal) 2.02 2.02 0.79 6.40 1.58 4.00 2.00 1.00 8.00 80.81 kg 100% 80.81
Wall Rebar (Vertical) + u bar 2.08 6.40 1.58 64.00 1.00 1.00 64.00 209.89 kg 100% 209.89
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 0% -
Wall Formwork 1.60 1.60 1.50 9.60 1.00 2.00 1.00 2.00 19.20 m2 0% -
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.79 1.01 1.00 1.00 1.00 1.00 1.01 m3 100% 1.01
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.50 0.79 9.60 1.00 1.00 1.00 1.00 9.60 m2 0% -
Epoxy Coating 1.20 1.20 0.79 5.22 1.00 1.00 1.00 1.00 5.22 m2 0% -
Soil Backfill 1.60 1.60 1.60 19.75 1.00 1.00 1.00 1.00 19.75 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

2 MH-02 Lean Concrete X & Y = 2.4 m Follow Drawing Before Wall Thickness Have Changed
Excavation 5.59 5.59 1.66 0.70 25.06 1.00 1.00 1.00 1.00 25.06 m3 100% 25.06
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 0% -
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
D16 Bottom Slab Rebar 2.10 2.10 1.25 1.58 8.00 2.00 2.00 32.00 106.06 kg 100% 106.06
Wall Rebar (Horizontal) 2.02 2.02 0.85 6.40 1.58 5.00 2.00 1.00 10.00 101.01 kg 100% 101.01
Wall Rebar (Vertical) + u bar 2.14 6.40 1.58 8.00 2.00 4.00 64.00 215.95 kg 100% 215.95
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 0% -
Wall Formwork 1.60 1.60 1.46 9.34 1.00 2.00 1.00 2.00 18.69 m2 0% -
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 0% -
Wall Pouring Concrete 1.60 1.60 0.20 0.85 1.09 1.00 1.00 1.00 1.00 1.09 m3 0% -
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.61 0.85 10.30 1.00 1.00 1.00 1.00 10.30 m2 0% -
Epoxy Coating 1.20 1.20 0.85 5.51 1.00 1.00 1.00 1.00 5.51 m2 0% -
Soil Backfill 1.60 1.60 1.66 20.81 1.00 1.00 1.00 1.00 20.81 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
STORM WATER MANHOLE 001 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
3 MH-03 Lean Concrete X & Y = 2.4 m Follow Drawing Before Wall Thickness Have Changed
Excavation 5.66 5.66 1.72 0.70 26.30 1.00 1.00 1.00 1.00 26.30 m3 100% 26.30
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 0% -
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.10 2.10 1.31 1.58 8.00 2.00 2.00 32.00 106.06 kg 100% 106.06
Wall Rebar (Horizontal) 2.02 2.02 0.91 6.40 1.58 5.00 2.00 1.00 10.00 101.01 kg 50% 50.50
Wall Rebar (Vertical) + u bar 2.20 6.40 1.58 8.00 2.00 4.00 64.00 222.01 kg 50% 111.01
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 0% -
Wall Formwork 1.60 1.60 1.52 9.73 1.00 2.00 1.00 2.00 19.46 m2 0% -
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 0% -
Wall Pouring Concrete 1.60 1.60 0.20 0.91 1.16 1.00 1.00 1.00 1.00 1.16 m3 0% -
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.67 0.91 10.69 1.00 1.00 1.00 1.00 10.69 m2 0% -
Epoxy Coating 1.20 1.20 0.91 5.80 1.00 1.00 1.00 1.00 5.80 m2 0% -
Soil Backfill 1.60 1.60 1.72 21.90 1.00 1.00 1.00 1.00 21.90 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

A.2 ZONE 2
4 MH-25
Excavation 5.46 5.46 1.55 0.70 22.85 1.00 1.00 1.00 1.00 22.85 m3 100% 22.85
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.14 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 2.02 2.02 0.79 6.40 1.58 4.00 2.00 1.00 8.00 80.81 kg 100% 80.81
Wall Rebar (Vertical) + u bar 2.03 6.40 1.58 8.00 2.00 4.00 64.00 204.84 kg 100% 204.84
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.40 8.96 1.00 2.00 1.00 2.00 17.92 m2 100% 17.92
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.79 1.01 1.00 1.00 1.00 1.00 1.01 m3 100% 1.01
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.50 0.79 9.60 1.00 1.00 1.00 1.00 9.60 m2 100% 9.60
Epoxy Coating 1.20 1.20 0.79 5.22 1.00 1.00 1.00 1.00 5.22 m2 0% -
Soil Backfill 1.60 1.60 1.55 18.88 1.00 1.00 1.00 1.00 18.88 m3 100% 18.88
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
STORM WATER MANHOLE 001 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
5 MH-26
Excavation 5.51 5.51 1.59 0.70 23.65 1.00 1.00 1.00 1.00 23.65 m3 100% 23.65
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.18 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 2.02 2.02 0.83 6.40 1.58 5.00 2.00 1.00 10.00 101.01 kg 100% 101.01
Wall Rebar (Vertical) + u bar 2.07 6.40 1.58 8.00 2.00 4.00 64.00 208.88 kg 100% 208.88
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.39 8.90 1.00 2.00 1.00 2.00 17.79 m2 100% 17.79
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.83 1.06 1.00 1.00 1.00 1.00 1.06 m3 100% 1.06
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.54 0.83 9.86 1.00 1.00 1.00 1.00 9.86 m2 100% 9.86
Epoxy Coating 1.20 1.20 0.83 5.41 1.00 1.00 1.00 1.00 5.41 m2 0% -
Soil Backfill 1.60 1.60 1.59 19.58 1.00 1.00 1.00 1.00 19.58 m3 100% 19.58
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

6 MH-22
Excavation 5.46 5.46 1.55 0.70 22.85 1.00 1.00 1.00 1.00 22.85 m3 100% 22.85
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.14 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 2.02 2.02 0.79 6.40 1.58 4.00 2.00 1.00 8.00 80.81 kg 100% 80.81
Wall Rebar (Vertical) + u bar 2.03 6.40 1.58 8.00 2.00 4.00 64.00 204.84 kg 100% 204.84
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.35 8.64 1.00 2.00 1.00 2.00 17.28 m2 100% 17.28
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.79 1.01 1.00 1.00 1.00 1.00 1.01 m3 100% 1.01
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.50 0.79 9.60 1.00 1.00 1.00 1.00 9.60 m2 100% 9.60
Epoxy Coating 1.20 1.20 0.79 5.22 1.00 1.00 1.00 1.00 5.22 m2 0% -
Soil Backfill 1.60 1.60 1.55 18.88 1.00 1.00 1.00 1.00 18.88 m3 100% 18.88
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
STORM WATER MANHOLE 001 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
7 MH-29
Excavation 5.46 5.46 1.55 0.70 22.85 1.00 1.00 1.00 1.00 22.85 m3 100% 22.85
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.14 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 2.02 2.02 0.79 6.40 1.58 4.00 2.00 1.00 8.00 80.81 kg 100% 80.81
Wall Rebar (Vertical) + u bar 2.03 6.40 1.58 8.00 2.00 4.00 64.00 204.84 kg 100% 204.84
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.35 8.64 1.00 2.00 1.00 2.00 17.28 m2 100% 17.28
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.79 1.01 1.00 1.00 1.00 1.00 1.01 m3 100% 1.01
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.50 0.79 9.60 1.00 1.00 1.00 1.00 9.60 m2 100% 9.60
Epoxy Coating 1.20 1.20 0.79 5.22 1.00 1.00 1.00 1.00 5.22 m2 0% -
Soil Backfill 1.60 1.60 1.55 18.88 1.00 1.00 1.00 1.00 18.88 m3 100% 18.88
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

8 MH-30
Excavation 5.51 5.51 1.59 0.70 23.65 1.00 1.00 1.00 1.00 23.65 m3 100% 23.65
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.18 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 2.02 2.02 0.83 6.40 1.58 5.00 2.00 1.00 10.00 101.01 kg 100% 101.01
Wall Rebar (Vertical) + u bar 2.07 6.40 1.58 8.00 2.00 4.00 64.00 208.88 kg 100% 208.88
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.39 8.90 1.00 2.00 1.00 2.00 17.79 m2 100% 17.79
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.83 1.06 1.00 1.00 1.00 1.00 1.06 m3 100% 1.06
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.54 0.83 9.86 1.00 1.00 1.00 1.00 9.86 m2 100% 9.86
Epoxy Coating 1.20 1.20 0.83 5.41 1.00 1.00 1.00 1.00 5.41 m2 0% -
Soil Backfill 1.60 1.60 1.59 19.58 1.00 1.00 1.00 1.00 19.58 m3 100% 19.58
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
STORM WATER MANHOLE 001 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A.3 ZONE 3
9 MH-15
Excavation 5.42 5.42 1.52 0.70 22.22 1.00 1.00 1.00 1.00 22.22 m3 100% 22.22
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.32 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 2.02 2.02 0.97 6.40 1.58 5.00 2.00 1.00 10.00 101.01 kg 100% 101.01
Wall Rebar (Vertical) + u bar 2.21 6.40 1.58 8.00 2.00 4.00 64.00 223.02 kg 100% 223.02
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.32 8.44 1.00 2.00 1.00 2.00 16.87 m2 0% -
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.97 1.24 1.00 1.00 1.00 1.00 1.24 m3 100% 1.24
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.47 0.97 9.40 1.00 1.00 1.00 1.00 9.40 m2 0% -
Epoxy Coating 1.20 1.20 0.97 6.09 1.00 1.00 1.00 1.00 6.09 m2 0% -
Soil Backfill 1.60 1.60 1.52 18.33 1.00 1.00 1.00 1.00 18.33 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

10 MH-16
Excavation 5.37 5.37 1.48 0.70 21.44 1.00 1.00 1.00 1.00 21.44 m3 100% 21.44
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.28 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 2.02 2.02 0.93 6.40 1.58 5.00 2.00 1.00 10.00 101.01 kg 100% 101.01
Wall Rebar (Vertical) + u bar 2.17 6.40 1.58 8.00 2.00 4.00 64.00 218.98 kg 100% 218.98
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.28 8.18 1.00 2.00 1.00 2.00 16.36 m2 0% -
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.93 1.19 1.00 1.00 1.00 1.00 1.19 m3 100% 1.19
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.43 0.93 9.14 1.00 1.00 1.00 1.00 9.14 m2 0% -
Epoxy Coating 1.20 1.20 0.93 5.89 1.00 1.00 1.00 1.00 5.89 m2 0% -
Soil Backfill 1.60 1.60 1.48 17.66 1.00 1.00 1.00 1.00 17.66 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
STORM WATER MANHOLE 001 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
11 MH-17
Excavation 5.45 5.45 1.54 0.70 22.61 1.00 1.00 1.00 1.00 22.61 m3 100% 22.61
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.34 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 2.02 2.02 0.99 6.40 1.58 5.00 2.00 1.00 10.00 101.01 kg 100% 101.01
Wall Rebar (Vertical) + u bar 2.23 6.40 1.58 8.00 2.00 4.00 64.00 225.04 kg 100% 225.04
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.34 8.56 1.00 2.00 1.00 2.00 17.13 m2 0% -
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.99 1.26 1.00 1.00 1.00 1.00 1.26 m3 100% 1.26
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.43 0.99 9.14 1.00 1.00 1.00 1.00 9.14 m2 0% -
Epoxy Coating 1.20 1.20 0.99 6.18 1.00 1.00 1.00 1.00 6.18 m2 0% -
Soil Backfill 1.60 1.60 1.54 18.68 1.00 1.00 1.00 1.00 18.68 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

12 MH-18
Excavation 5.49 5.49 1.58 0.70 23.41 1.00 1.00 1.00 1.00 23.41 m3 100% 23.41
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.38 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 2.02 2.02 1.03 6.40 1.58 6.00 2.00 1.00 12.00 121.21 kg 100% 121.21
Wall Rebar (Vertical) + u bar 2.27 6.40 1.58 8.00 2.00 4.00 64.00 229.08 kg 100% 229.08
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.38 8.82 1.00 2.00 1.00 2.00 17.64 m2 0% -
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 1.03 1.32 1.00 1.00 1.00 1.00 1.32 m3 100% 1.32
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.53 1.03 9.78 1.00 1.00 1.00 1.00 9.78 m2 0% -
Epoxy Coating 1.20 1.20 1.03 6.37 1.00 1.00 1.00 1.00 6.37 m2 0% -
Soil Backfill 1.60 1.60 1.58 19.37 1.00 1.00 1.00 1.00 19.37 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
STORM WATER MANHOLE 001 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A.4 ZONE 4
13 MH-11
Excavation 5.46 5.46 1.55 0.70 22.85 1.00 1.00 1.00 1.00 22.85 m3 100% 22.85
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.14 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 2.02 2.02 0.79 6.40 1.58 4.00 2.00 1.00 8.00 80.81 kg 100% 80.81
Wall Rebar (Vertical) + u bar 2.03 6.40 1.58 8.00 2.00 4.00 64.00 204.84 kg 100% 204.84
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.40 8.96 1.00 2.00 1.00 2.00 17.92 m2 100% 17.92
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.79 1.01 1.00 1.00 1.00 1.00 1.01 m3 100% 1.01
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.50 0.79 9.60 1.00 1.00 1.00 1.00 9.60 m2 0% -
Epoxy Coating 1.20 1.20 0.79 5.22 1.00 1.00 1.00 1.00 5.22 m2 0% -
Soil Backfill 1.60 1.60 1.55 18.88 1.00 1.00 1.00 1.00 18.88 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

14 MH-12
Excavation 5.50 5.50 1.58 0.70 23.45 1.00 1.00 1.00 1.00 23.45 m3 100% 23.45
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.14 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 2.02 2.02 0.82 6.40 1.58 5.00 2.00 1.00 10.00 101.01 kg 100% 101.01
Wall Rebar (Vertical) + u bar 2.06 6.40 1.58 8.00 2.00 4.00 64.00 207.87 kg 100% 207.87
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.53 9.79 1.00 2.00 1.00 2.00 19.58 m2 100% 19.58
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.82 1.05 1.00 1.00 1.00 1.00 1.05 m3 100% 1.05
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.53 0.82 9.79 1.00 1.00 1.00 1.00 9.79 m2 0% -
Epoxy Coating 1.20 1.20 0.82 5.37 1.00 1.00 1.00 1.00 5.37 m2 0% -
Soil Backfill 1.60 1.60 1.58 19.40 1.00 1.00 1.00 1.00 19.40 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
STORM WATER MANHOLE 001 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
15 MH-13
Excavation 5.56 5.56 1.63 0.70 24.45 1.00 1.00 1.00 1.00 24.45 m3 100% 24.45
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.14 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 2.02 2.02 0.87 6.40 1.58 5.00 2.00 1.00 10.00 101.01 kg 100% 101.01
Wall Rebar (Vertical) + u bar 2.11 6.40 1.58 8.00 2.00 4.00 64.00 212.92 kg 100% 212.92
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.58 10.11 1.00 2.00 1.00 2.00 20.22 m2 100% 20.22
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.87 1.11 1.00 1.00 1.00 1.00 1.11 m3 100% 1.11
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.58 0.87 10.11 1.00 1.00 1.00 1.00 10.11 m2 0% -
Epoxy Coating 1.20 1.20 0.87 5.61 1.00 1.00 1.00 1.00 5.61 m2 0% -
Soil Backfill 1.60 1.60 1.63 20.28 1.00 1.00 1.00 1.00 20.28 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

16 MH-14
Excavation 5.64 5.64 1.70 0.70 25.89 1.00 1.00 1.00 1.00 25.89 m3 100% 25.89
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.29 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 2.02 2.02 0.94 6.40 1.58 5.00 2.00 1.00 10.00 101.01 kg 100% 101.01
Wall Rebar (Vertical) + u bar 2.18 6.40 1.58 8.00 2.00 4.00 64.00 219.99 kg 100% 219.99
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 3.00 1.00 1.00 3.00 3.00 nos 100% 3.00
Wall Formwork 1.60 1.60 1.65 10.56 1.00 2.00 1.00 2.00 21.12 m2 100% 21.12
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.94 1.20 1.00 1.00 1.00 1.00 1.20 m3 100% 1.20
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.65 0.94 10.56 1.00 1.00 1.00 1.00 10.56 m2 100% 10.56
Epoxy Coating 1.20 1.20 0.94 5.94 1.00 1.00 1.00 1.00 5.94 m2 0% -
Soil Backfill 1.60 1.60 1.70 21.54 1.00 1.00 1.00 1.00 21.54 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
STORM WATER MANHOLE 001 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
17 MH-20
Excavation 5.58 5.58 1.65 0.70 24.82 1.00 1.00 1.00 1.00 24.82 m3 100% 24.82
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.45 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 2.02 2.02 1.10 1.10 6.40 1.58 6.00 2.00 1.00 12.00 121.21 kg 100% 121.21
Wall Rebar (Vertical) + u bar 2.34 6.40 1.58 8.00 2.00 4.00 64.00 236.16 kg 100% 236.16
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.45 9.27 1.00 2.00 1.00 2.00 18.53 m2 100% 18.53
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 1.10 1.41 1.00 1.00 1.00 1.00 1.41 m3 100% 1.41
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.60 1.10 10.23 1.00 1.00 1.00 1.00 10.23 m2 0% -
Epoxy Coating 1.20 1.20 1.00 6.23 1.00 1.00 1.00 1.00 6.23 m2 0% -
Soil Backfill 1.60 1.60 1.65 20.60 1.00 1.00 1.00 1.00 20.60 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

A.5 ZONE 5
18 MH-23
Excavation 5.53 5.53 1.61 0.70 24.05 1.00 1.00 1.00 1.00 24.05 m3 100% 24.05
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.41 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 2.02 2.02 1.06 1.06 6.40 1.58 6.00 2.00 1.00 12.00 121.21 kg 100% 121.21
Wall Rebar (Vertical) + u bar 2.09 6.40 1.58 8.00 2.00 4.00 64.00 210.90 kg 100% 210.90
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.56 9.98 1.00 2.00 1.00 2.00 19.97 m2 100% 19.97
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 1.06 1.36 1.00 1.00 1.00 1.00 1.36 m3 100% 1.36
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.56 1.06 9.98 1.00 1.00 1.00 1.00 9.98 m2 0% -
Epoxy Coating 1.20 1.20 0.85 5.51 1.00 1.00 1.00 1.00 5.51 m2 0% -
Soil Backfill 1.60 1.60 1.61 19.93 1.00 1.00 1.00 1.00 19.93 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
STORM WATER MANHOLE 001 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
19 MH-24
Excavation 5.62 5.62 1.68 0.70 25.47 1.00 1.00 1.00 1.00 25.47 m3 100% 25.47
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.48 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 2.02 2.02 1.13 1.13 6.40 1.58 6.00 2.00 1.00 12.00 121.21 kg 100% 121.21
Wall Rebar (Vertical) + u bar 2.16 6.40 1.58 8.00 2.00 4.00 64.00 217.97 kg 100% 217.97
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.63 10.43 1.00 2.00 1.00 2.00 20.86 m2 0% -
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 1.13 1.45 1.00 1.00 1.00 1.00 1.45 m3 100% 1.45
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.56 1.13 9.98 1.00 1.00 1.00 1.00 9.98 m2 0% -
Epoxy Coating 1.20 1.20 0.92 5.85 1.00 1.00 1.00 1.00 5.85 m2 0% -
Soil Backfill 1.60 1.60 1.68 21.17 1.00 1.00 1.00 1.00 21.17 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

A.6 ZONE 6
20 MH-04
Excavation 5.46 5.46 1.55 0.70 22.81 1.00 1.00 1.00 1.00 22.81 m3 100% 22.81
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.35 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 2.02 2.02 1.00 1.00 6.40 1.58 5.00 2.00 1.00 10.00 101.01 kg 100% 101.01
Wall Rebar (Vertical) + u bar 2.24 6.40 1.58 8.00 2.00 4.00 64.00 226.05 kg 100% 226.05
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.35 8.63 1.00 2.00 1.00 2.00 17.25 m2 100% 17.25
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 1.00 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.50 1.00 9.59 1.00 1.00 1.00 1.00 9.59 m2 0% -
Epoxy Coating 1.20 1.20 1.00 6.23 1.00 1.00 1.00 1.00 6.23 m2 0% -
Soil Backfill 1.60 1.60 1.55 18.85 1.00 1.00 1.00 1.00 18.85 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
STORM WATER MANHOLE 001 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
21 MH-05
Excavation 5.66 5.66 1.72 0.70 26.26 1.00 1.00 1.00 1.00 26.26 m3 100% 26.26
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.52 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 2.02 2.02 1.17 1.17 6.40 1.58 6.00 2.00 1.00 12.00 121.21 kg 100% 121.21
Wall Rebar (Vertical) + u bar 2.41 6.40 1.58 8.00 2.00 4.00 64.00 243.23 kg 100% 243.23
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.52 9.72 1.00 2.00 1.00 2.00 19.43 m2 0% -
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 1.17 1.50 1.00 1.00 1.00 1.00 1.50 m3 100% 1.50
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.67 1.17 10.68 1.00 1.00 1.00 1.00 10.68 m2 0% -
Epoxy Coating 1.20 1.20 1.17 7.05 1.00 1.00 1.00 1.00 7.05 m2 0% -
Soil Backfill 1.60 1.60 1.72 21.86 1.00 1.00 1.00 1.00 21.86 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

22 MH-21
Excavation 5.09 5.09 1.24 0.70 17.00 1.00 1.00 1.00 1.00 17.00 m3 0% -
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 0% -
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 0% -
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 0% -
Bottom Slab Rebar 2.00 2.00 1.04 1.58 8.00 2.00 2.00 32.00 101.01 kg 0% -
Wall Rebar (Horizontal) 2.02 2.02 0.69 0.69 6.40 1.58 4.00 2.00 1.00 8.00 80.81 kg 0% -
Wall Rebar (Vertical) + u bar 1.93 6.40 1.58 8.00 2.00 4.00 64.00 194.74 kg 0% -
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 0% -
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 0% -
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 0% -
Hume Pipe Connection 1.00 1.00 1.00 1.00 1.00 nos 0% -
Wall Formwork 1.60 1.60 1.04 6.64 1.00 2.00 1.00 2.00 13.29 m2 0% -
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 0% -
Wall Pouring Concrete 1.60 1.60 0.20 0.69 0.88 1.00 1.00 1.00 1.00 0.88 m3 0% -
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.19 0.69 7.60 1.00 1.00 1.00 1.00 7.60 m2 0% -
Epoxy Coating 1.20 1.20 0.69 4.74 1.00 1.00 1.00 1.00 4.74 m2 0% -
Soil Backfill 1.60 1.60 1.24 13.83 1.00 1.00 1.00 1.00 13.83 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
STORM WATER MANHOLE 001 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
23 MH-19
Excavation 5.58 5.58 1.65 0.70 24.82 1.00 1.00 1.00 1.00 24.82 m3 100% 24.82
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.45 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 2.02 2.02 1.10 1.10 6.40 1.58 6.00 2.00 1.00 12.00 121.21 kg 100% 121.21
Wall Rebar (Vertical) + u bar 2.34 6.40 1.58 8.00 2.00 4.00 64.00 236.16 kg 100% 236.16
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.45 9.27 1.00 2.00 1.00 2.00 18.53 m2 0% -
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 1.10 1.41 1.00 1.00 1.00 1.00 1.41 m3 100% 1.41
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.60 1.10 10.23 1.00 1.00 1.00 1.00 10.23 m2 0% -
Epoxy Coating 1.20 1.20 1.00 6.23 1.00 1.00 1.00 1.00 6.23 m2 0% -
Soil Backfill 1.60 1.60 1.65 20.60 1.00 1.00 1.00 1.00 20.60 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

A.7 ZONE 7
24 MH-09
Excavation 5.46 5.46 1.55 0.70 22.85 1.00 1.00 1.00 1.00 22.85 m3 100% 22.85
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.14 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 2.02 2.02 0.79 6.40 1.58 4.00 2.00 1.00 8.00 80.81 kg 100% 80.81
Wall Rebar (Vertical) + u bar 2.03 6.40 1.58 8.00 2.00 4.00 64.00 204.84 kg 100% 204.84
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.50 9.60 1.00 2.00 1.00 2.00 19.20 m2 0% -
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.79 1.01 1.00 1.00 1.00 1.00 1.01 m3 100% 1.01
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.50 0.79 9.60 1.00 1.00 1.00 1.00 9.60 m2 0% -
Epoxy Coating 1.20 1.20 0.79 5.22 1.00 1.00 1.00 1.00 5.22 m2 0% -
Soil Backfill 1.60 1.60 1.55 18.88 1.00 1.00 1.00 1.00 18.88 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
STORM WATER MANHOLE 001 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
25 MH-10
Excavation 5.56 5.56 1.63 0.70 24.45 1.00 1.00 1.00 1.00 24.45 m3 100% 24.45
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.22 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 2.02 2.02 0.87 6.40 1.58 5.00 2.00 1.00 10.00 101.01 kg 100% 101.01
Wall Rebar (Vertical) + u bar 2.11 6.40 1.58 8.00 2.00 4.00 64.00 212.92 kg 100% 212.92
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.22 7.80 1.00 2.00 1.00 2.00 15.59 m2 0% -
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.87 1.11 1.00 1.00 1.00 1.00 1.11 m3 100% 1.11
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.37 0.87 8.76 1.00 1.00 1.00 1.00 8.76 m2 0% -
Epoxy Coating 1.20 1.20 0.87 5.61 1.00 1.00 1.00 1.00 5.61 m2 0% -
Soil Backfill 1.60 1.60 1.63 20.28 1.00 1.00 1.00 1.00 20.28 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

26 MH-06
Excavation 6.00 6.00 2.00 0.70 32.40 1.00 1.00 1.00 1.00 32.40 m3 100% 32.40
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.74 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 2.02 2.02 1.24 6.40 1.58 7.00 2.00 1.00 14.00 141.41 kg 100% 141.41
Wall Rebar (Vertical) + u bar 2.48 6.40 1.58 8.00 2.00 4.00 64.00 250.30 kg 100% 250.30
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 3.00 1.00 1.00 3.00 3.00 nos 100% 3.00
Wall Formwork 1.60 1.60 1.95 12.48 1.00 2.00 1.00 2.00 24.96 m2 0% -
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 1.24 1.58 1.00 1.00 1.00 1.00 1.58 m3 100% 1.58
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.74 1.24 11.12 1.00 1.00 1.00 1.00 11.12 m2 0% -
Epoxy Coating 1.20 1.20 1.24 7.38 1.00 1.00 1.00 1.00 7.38 m2 0% -
Soil Backfill 1.60 1.60 2.00 27.28 1.00 1.00 1.00 1.00 27.28 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
STORM WATER MANHOLE 001 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
27 MH-07
Excavation 6.12 6.12 2.10 0.70 34.70 1.00 1.00 1.00 1.00 34.70 m3 100% 34.70
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.10 2.10 1.64 1.58 8.00 2.00 2.00 32.00 106.06 kg 100% 106.06
Wall Rebar (Horizontal) 2.02 2.02 1.29 6.40 1.58 4.00 2.00 1.00 8.00 80.81 kg 100% 80.81
Wall Rebar (Vertical) + u bar 2.58 6.40 1.58 64.00 1.00 1.00 64.00 260.40 kg 100% 260.40
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 3.00 1.00 1.00 3.00 3.00 nos 100% 3.00
Wall Formwork 1.60 1.60 2.00 12.80 1.00 2.00 1.00 2.00 25.60 m2 100% 25.60
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 1.29 1.65 1.00 1.00 1.00 1.00 1.65 m3 100% 1.65
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 2.00 1.29 12.80 1.00 1.00 1.00 1.00 12.80 m2 100% 12.80
Epoxy Coating 1.20 1.20 1.29 7.62 1.00 1.00 1.00 1.00 7.62 m2 0% -
Soil Backfill 1.60 1.60 2.10 29.32 1.00 1.00 1.00 1.00 29.32 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

28 MH-08
Excavation 6.10 6.10 2.08 0.70 54.11 1.00 1.00 1.00 1.00 54.11 m3 0% -
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 0% -
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 0% -
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 0% -
Bottom Slab Rebar 2.62 2.62 1.58 29.00 1.00 1.00 29.00 119.91 kg 0% -
Wall Rebar (Horizontal) 2.12 6.40 1.58 32.00 1.00 1.00 32.00 107.07 kg 0% -
Wall Rebar (Vertical) + u bar 2.08 6.40 1.58 64.00 1.00 1.00 64.00 209.89 kg 0% -
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 0% -
Ground Slab Formwork 3.52 1.00 1.00 1.00 1.00 3.52 m2 0% -
Ground Slab Pouring Concrete 1.60 1.60 0.55 1.41 1.00 1.00 1.00 1.00 1.41 m3 0% -
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 0% -
Wall Formwork 1.60 1.60 2.08 13.31 1.00 2.00 1.00 2.00 26.62 m2 0% -
Step Iron Installation 6.00 1.00 1.00 6.00 6.00 unit 0% -
Wall Pouring Concrete 1.60 1.60 0.20 2.08 2.66 1.00 1.00 1.00 1.00 2.66 m3 0% -
Upper Slab Formwork 3.20 1.00 1.00 1.00 1.00 3.20 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 36.00 1.00 1.00 36.00 102.27 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 2.08 13.31 1.00 1.00 1.00 1.00 13.31 m2 0% -
Epoxy Coating 1.20 1.20 1.33 7.82 1.00 1.00 1.00 1.00 7.82 m2 0% -
Soil Backfill 1.80 1.80 2.08 48.78 1.00 1.00 1.00 1.00 48.78 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
STORM WATER MANHOLE 001 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A.8 ZONE 8
29 MH-27
Excavation 5.53 5.53 1.61 0.70 24.05 1.00 1.00 1.00 1.00 24.05 m3 100% 24.05
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.20 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 2.02 2.02 0.85 6.40 1.58 5.00 2.00 1.00 10.00 101.01 kg 100% 101.01
Wall Rebar (Vertical) + u bar 2.09 6.40 1.58 8.00 2.00 4.00 64.00 210.90 kg 0% -
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.20 7.67 1.00 2.00 1.00 2.00 15.33 m2 100% 15.33
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.85 1.09 1.00 1.00 1.00 1.00 1.09 m3 100% 1.09
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.35 0.85 8.63 1.00 1.00 1.00 1.00 8.63 m2 0% -
Epoxy Coating 1.20 1.20 0.85 5.51 1.00 1.00 1.00 1.00 5.51 m2 0% -
Soil Backfill 1.60 1.60 1.61 19.93 1.00 1.00 1.00 1.00 19.93 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

30 MH-28
Excavation 5.58 5.58 1.65 0.70 24.86 1.00 1.00 1.00 1.00 24.86 m3 0% -
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 0% -
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 0% -
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 0% -
Bottom Slab Rebar 2.00 2.00 1.24 1.58 8.00 2.00 2.00 32.00 101.01 kg 0% -
Wall Rebar (Horizontal) 2.02 2.02 0.89 6.40 1.58 5.00 2.00 1.00 10.00 101.01 kg 0% -
Wall Rebar (Vertical) + u bar 2.13 6.40 1.58 8.00 2.00 4.00 64.00 214.94 kg 0% -
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 0% -
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 0% -
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 0% -
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 0% -
Wall Formwork 1.60 1.60 1.24 7.92 1.00 2.00 1.00 2.00 15.85 m2 0% -
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 0% -
Wall Pouring Concrete 1.60 1.60 0.20 0.89 1.14 1.00 1.00 1.00 1.00 1.14 m3 0% -
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.60 0.89 10.24 1.00 1.00 1.00 1.00 10.24 m2 0% -
Epoxy Coating 1.20 1.20 0.89 5.70 1.00 1.00 1.00 1.00 5.70 m2 0% -
Soil Backfill 1.60 1.60 1.65 20.63 1.00 1.00 1.00 1.00 20.63 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
STORM WATER MANHOLE 001 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
31 MH-31
Excavation 5.46 5.46 1.55 0.70 22.85 1.00 1.00 1.00 1.00 22.85 m3 0% -
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 0% -
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 0% -
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 0% -
Bottom Slab Rebar 2.00 2.00 1.14 1.58 8.00 2.00 2.00 32.00 101.01 kg 0% -
Wall Rebar (Horizontal) 2.02 2.02 0.79 6.40 1.58 4.00 2.00 1.00 8.00 80.81 kg 0% -
Wall Rebar (Vertical) + u bar 2.03 6.40 1.58 8.00 2.00 4.00 64.00 204.84 kg 0% -
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 0% -
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 0% -
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 0% -
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 0% -
Wall Formwork 1.60 1.60 1.14 7.28 1.00 2.00 1.00 2.00 14.57 m2 0% -
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 0% -
Wall Pouring Concrete 1.60 1.60 0.20 0.79 1.01 1.00 1.00 1.00 1.00 1.01 m3 0% -
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.50 0.79 9.60 1.00 1.00 1.00 1.00 9.60 m2 0% -
Epoxy Coating 1.20 1.20 0.79 5.22 1.00 1.00 1.00 1.00 5.22 m2 0% -
Soil Backfill 1.60 1.60 1.55 18.88 1.00 1.00 1.00 1.00 18.88 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

32 MH-32
Excavation 5.48 5.48 1.57 0.70 23.25 1.00 1.00 1.00 1.00 23.25 m3 0% -
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 0% -
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 0% -
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 0% -
Bottom Slab Rebar 2.00 2.00 1.16 1.58 8.00 2.00 2.00 32.00 101.01 kg 0% -
Wall Rebar (Horizontal) 2.02 2.02 0.81 6.40 1.58 5.00 2.00 1.00 10.00 101.01 kg 0% -
Wall Rebar (Vertical) + u bar 2.05 6.40 1.58 8.00 2.00 4.00 64.00 206.86 kg 0% -
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 0% -
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 0% -
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 0% -
Hume Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 0% -
Wall Formwork 1.60 1.60 1.16 7.41 1.00 2.00 1.00 2.00 14.82 m2 0% -
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 0% -
Wall Pouring Concrete 1.60 1.60 0.20 0.81 1.03 1.00 1.00 1.00 1.00 1.03 m3 0% -
Upper Slab Formwork 1.60 1.60 0.20 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
STORM WATER MANHOLE 001 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Upper Slab Rebar 1.90 1.90 1.58 8.00 2.00 1.00 16.00 47.98 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.52 0.81 9.73 1.00 1.00 1.00 1.00 9.73 m2 0% -
Epoxy Coating 1.20 1.20 0.81 5.32 1.00 1.00 1.00 1.00 5.32 m2 0% -
Soil Backfill 1.60 1.60 1.57 19.23 1.00 1.00 1.00 1.00 19.23 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

RECAP FOR MAIN PROGRESS (BOQ ITEMS) Notes :


Progress Date 1. The Quantity Calculation is Still PT. SSA Version, It is Not Yet Together Measurement With KINE's Quantity Surveyor.
31/08/2023 2. Quantity Calculation Based On Approved Shop Drawing and Lotte Chemical E & C For Construction Drawing.

Progress Progress
No. Description Unit Total Quantity Remarks
Quantity Percentages
1 Excavation m3 806.12 664.06 82.3771%
2 Pile Cut Off nos 32.00 24.00 75.0000%
3 Plastic Sheet & Lean Concrete m3 5.18 4.37 84.3750%
4 Lean Concrete Formwork m2 11.52 9.72 84.3750%
5 Rebar (D16) kg 15,042.09 11,054.14 73.4881%
Bottom Slab Rebar 3,271.34 2,747.40
Wall Rebar (Horizontal) 3,218.09 2,696.90
Wall Rebar (Vertical) + u bar 6,963.04 5,609.85
Upper Slab Rebar 1,589.60 -
6 Formwork m2 817.63 350.00 42.8073%
Ground Slab Formwork 102.72 86.40
Wall Formwork 592.67 263.60
Upper Slab Formwork 122.24 -
7 FC 24 Concrete m3 96.80 64.91 67.0625%
Ground Slab Pouring Concrete 41.09 34.56
Wall Pouring Concrete 39.32 30.35
Upper Slab Pouring Concrete 16.38 -
8 Step Iron Installation nos 99.00 75.00 75.7576%
9 Cast Iron Manhole Cover unit 32.00 - 0.0000%
10 Bitumen Coating m2 318.69 71.87 22.5520%
11 Epoxy Coating m2 186.95 - 0.0000%
12 Soil Backfill m3 672.45 95.80 14.2459% ARITMATH CHECKING
13 Waterstop Installation m 204.80 172.80 84.3750% New Items RECAP 18,596.03
14 Hume Pipe Connection nos 66.00 51.00 77.2727% Method BREAKDOWN 18,596.03
15 Join Sealant m 204.80 - 0.0000% New Items IF ZERO = OK! -

GLOBAL PROGRESS FOR STORM WATER MANHOLE (AVERAGE PRORATE BY ITEMS) 52.2459%

31/08/2023
Checked by,
PT. Sepuluh Sumber Anugerah

Herdy Dwiyana
Quantity Surveyor
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE MANHOLE 13.00 2,500.00 32,500.00 002 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
SEWAGE MANHOLE (SECTION 1
A 0.70
AREA)
A.1 ZONE 1
1 SM-B5
Excavation 5.48 5.48 1.57 0.70 23.25 1.00 1.00 1.00 1.00 23.25 m3 100% 23.25
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 0.81 2.02 1.58 5.00 2.00 4.00 40.00 127.52 kg 100% 127.52
Wall Rebar (Vertical) + u bar 1.60 1.60 2.05 2.02 1.58 8.00 2.00 4.00 64.00 206.86 kg 100% 206.86
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Wall Formwork 1.60 1.60 0.81 10.34 1.00 1.00 1.00 1.00 10.34 m2 100% 10.34
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.81 1.03 1.00 1.00 1.00 1.00 1.03 m3 100% 1.03
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.52 9.73 1.00 1.00 1.00 1.00 9.73 m2 100% 9.73
Epoxy Coating 1.20 1.20 0.81 5.32 1.00 1.00 1.00 1.00 5.32 m2 0% -
Soil Backfill 1.60 1.60 1.57 19.23 1.00 1.00 1.00 1.00 19.23 m3 100% 19.23
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

2 SM-18
Excavation 5.72 5.72 1.77 0.70 27.35 1.00 1.00 1.00 1.00 27.35 m3 100% 27.35
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 1.01 2.02 1.58 6.00 2.00 4.00 48.00 153.03 kg 100% 153.03
Wall Rebar (Vertical) + u bar 1.60 1.60 2.25 2.02 1.58 8.00 2.00 4.00 64.00 227.06 kg 100% 227.06
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.01 12.90 1.00 1.00 1.00 1.00 12.90 m2 100% 12.90
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 1.01 1.29 1.00 1.00 1.00 1.00 1.29 m3 100% 1.29
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.72 11.01 1.00 1.00 1.00 1.00 11.01 m2 0% -
Epoxy Coating 1.20 1.20 1.01 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Soil Backfill 1.60 1.60 1.77 22.82 1.00 1.00 1.00 1.00 22.82 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE MANHOLE 13.00 2,500.00 32,500.00 002 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
3 SM-19
Excavation 5.68 5.68 1.73 0.70 26.51 1.00 1.00 1.00 1.00 26.51 m3 100% 26.51
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 0.97 2.02 1.58 5.00 2.00 4.00 40.00 127.52 kg 100% 127.52
Wall Rebar (Vertical) + u bar 1.60 1.60 2.21 2.02 1.58 8.00 2.00 4.00 64.00 223.02 kg 100% 223.02
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 0.97 12.39 1.00 1.00 1.00 1.00 12.39 m2 100% 12.39
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.97 1.24 1.00 1.00 1.00 1.00 1.24 m3 100% 1.24
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.68 10.75 1.00 1.00 1.00 1.00 10.75 m2 0% -
Epoxy Coating 1.20 1.20 0.97 6.09 1.00 1.00 1.00 1.00 6.09 m2 0% -
Soil Backfill 1.60 1.60 1.73 22.08 1.00 1.00 1.00 1.00 22.08 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

4 SM-11
Excavation 6.68 6.68 2.57 0.70 46.38 1.00 1.00 1.00 1.00 46.38 m3 100% 46.38
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 1.81 2.02 1.58 10.00 2.00 4.00 80.00 255.04 kg 100% 255.04
Wall Rebar (Vertical) + u bar 1.60 1.60 3.05 2.02 1.58 8.00 2.00 4.00 64.00 307.87 kg 100% 307.87
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 3.00 1.00 1.00 3.00 3.00 nos 0% -
Wall Formwork 1.60 1.60 1.81 23.14 1.00 1.00 1.00 1.00 23.14 m2 0% -
Step Iron Installation 6.00 1.00 1.00 6.00 6.00 unit 0% -
Wall Pouring Concrete 1.60 1.60 0.20 1.81 2.31 1.00 1.00 1.00 1.00 2.31 m3 0% -
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 2.52 16.13 1.00 1.00 1.00 1.00 16.13 m2 0% -
Epoxy Coating 1.20 1.20 1.81 10.12 1.00 1.00 1.00 1.00 10.12 m2 0% -
Soil Backfill 1.60 1.60 2.57 39.80 1.00 1.00 1.00 1.00 39.80 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE MANHOLE 13.00 2,500.00 32,500.00 002 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
5 SM-10
Excavation 7.25 7.25 3.04 0.70 59.49 1.00 1.00 1.00 1.00 59.49 m3 100% 59.49
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 2.28 2.02 1.58 12.00 2.00 4.00 96.00 306.05 kg 100% 306.05
Wall Rebar (Vertical) + u bar 1.60 1.60 3.52 2.02 1.58 8.00 2.00 4.00 64.00 355.34 kg 100% 355.34
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 3.00 1.00 1.00 3.00 3.00 nos 100% 3.00
Wall Formwork 1.60 1.60 2.28 29.16 1.00 1.00 1.00 1.00 29.16 m2 100% 29.16
Step Iron Installation 8.00 1.00 1.00 8.00 8.00 unit 100% 8.00
Wall Pouring Concrete 1.60 1.60 0.20 2.28 2.92 1.00 1.00 1.00 1.00 2.92 m3 100% 2.92
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 2.99 19.14 1.00 1.00 1.00 1.00 19.14 m2 100% 19.14
Epoxy Coating 1.20 1.20 2.28 12.37 1.00 1.00 1.00 1.00 12.37 m2 0% -
Soil Backfill 1.60 1.60 3.04 51.71 1.00 1.00 1.00 1.00 51.71 m3 100% 51.71
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

A.2 ZONE 2
6 SM-15
Excavation 5.72 5.72 1.77 0.70 27.35 1.00 1.00 1.00 1.00 27.35 m3 100% 27.35
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 1.01 2.02 1.58 6.00 2.00 4.00 48.00 153.03 kg 100% 153.03
Wall Rebar (Vertical) + u bar 1.60 1.60 2.25 2.02 1.58 8.00 2.00 4.00 64.00 227.06 kg 100% 227.06
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.01 12.90 1.00 1.00 1.00 1.00 12.90 m2 100% 12.90
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 1.01 1.29 1.00 1.00 1.00 1.00 1.29 m3 100% 1.29
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.72 11.01 1.00 1.00 1.00 1.00 11.01 m2 0% -
Epoxy Coating 1.20 1.20 1.01 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Soil Backfill 1.60 1.60 1.77 22.82 1.00 1.00 1.00 1.00 22.82 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE MANHOLE 13.00 2,500.00 32,500.00 002 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
7 SM-B4
Excavation 5.48 5.48 1.57 0.70 23.25 1.00 1.00 1.00 1.00 23.25 m3 100% 23.25
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 0.81 2.02 1.58 5.00 2.00 4.00 40.00 127.52 kg 100% 127.52
Wall Rebar (Vertical) + u bar 1.60 1.60 2.05 2.02 1.58 8.00 2.00 4.00 64.00 206.86 kg 100% 206.86
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Wall Formwork 1.60 1.60 0.81 10.34 1.00 1.00 1.00 1.00 10.34 m2 100% 10.34
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.81 1.03 1.00 1.00 1.00 1.00 1.03 m3 100% 1.03
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.52 9.73 1.00 1.00 1.00 1.00 9.73 m2 0% -
Epoxy Coating 1.20 1.20 0.81 5.32 1.00 1.00 1.00 1.00 5.32 m2 0% -
Soil Backfill 1.60 1.60 1.57 19.23 1.00 1.00 1.00 1.00 19.23 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

8 SM-09
Excavation 7.16 7.16 2.97 0.70 57.45 1.00 1.00 1.00 1.00 57.45 m3 100% 57.45
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 2.21 2.02 1.58 12.00 2.00 4.00 96.00 306.05 kg 100% 306.05
Wall Rebar (Vertical) + u bar 1.60 1.60 3.45 2.02 1.58 8.00 2.00 4.00 64.00 348.27 kg 100% 348.27
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 2.21 28.26 1.00 1.00 1.00 1.00 28.26 m2 100% 28.26
Step Iron Installation 7.00 1.00 1.00 7.00 7.00 unit 100% 7.00
Wall Pouring Concrete 1.60 1.60 0.20 2.21 2.83 1.00 1.00 1.00 1.00 2.83 m3 100% 2.83
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 2.92 18.69 1.00 1.00 1.00 1.00 18.69 m2 0% -
Epoxy Coating 1.20 1.20 2.21 12.04 1.00 1.00 1.00 1.00 12.04 m2 0% -
Soil Backfill 1.60 1.60 2.97 49.84 1.00 1.00 1.00 1.00 49.84 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE MANHOLE 13.00 2,500.00 32,500.00 002 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
9 SM-08
Excavation 6.90 6.90 2.75 0.70 51.23 1.00 1.00 1.00 1.00 51.23 m3 100% 51.23
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 1.99 2.02 1.58 10.00 2.00 4.00 80.00 255.04 kg 100% 255.04
Wall Rebar (Vertical) + u bar 1.60 1.60 3.23 2.02 1.58 8.00 2.00 4.00 64.00 326.05 kg 100% 326.05
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 0% -
Wall Formwork 1.60 1.60 1.99 25.45 1.00 1.00 1.00 1.00 25.45 m2 0% -
Step Iron Installation 7.00 1.00 1.00 7.00 7.00 unit 0% -
Wall Pouring Concrete 1.60 1.60 0.20 1.99 2.54 1.00 1.00 1.00 1.00 2.54 m3 0% -
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 2.70 17.28 1.00 1.00 1.00 1.00 17.28 m2 0% -
Epoxy Coating 1.20 1.20 1.99 10.98 1.00 1.00 1.00 1.00 10.98 m2 0% -
Soil Backfill 1.60 1.60 2.75 44.19 1.00 1.00 1.00 1.00 44.19 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE MANHOLE 13.00 2,500.00 32,500.00 002 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A.3 ZONE 3
10 SM-12
Excavation 7.30 7.30 3.08 0.70 60.67 1.00 1.00 1.00 1.00 60.67 m3 100% 60.67
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 2.32 2.02 1.58 12.00 2.00 4.00 96.00 306.05 kg 100% 306.05
Wall Rebar (Vertical) + u bar 1.60 1.60 3.56 2.02 1.58 8.00 2.00 4.00 64.00 359.38 kg 100% 359.38
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 3.00 1.00 1.00 3.00 3.00 nos 100% 3.00
Wall Formwork 1.60 1.60 2.32 29.67 1.00 1.00 1.00 1.00 29.67 m2 100% 29.67
Step Iron Installation 8.00 1.00 1.00 8.00 8.00 unit 100% 8.00
Wall Pouring Concrete 1.60 1.60 0.20 2.32 2.97 1.00 1.00 1.00 1.00 2.97 m3 100% 2.97
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 3.03 19.39 1.00 1.00 1.00 1.00 19.39 m2 100% 19.39
Epoxy Coating 1.20 1.20 2.32 12.57 1.00 1.00 1.00 1.00 12.57 m2 0% -
Soil Backfill 1.60 1.60 3.08 52.79 1.00 1.00 1.00 1.00 52.79 m3 100% 52.79
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

11 SM-16
Excavation 5.86 5.86 1.88 0.70 29.73 1.00 1.00 1.00 1.00 29.73 m3 100% 29.73
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
D16 Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
D16 Wall Rebar (Horizontal) 1.60 1.60 1.12 2.02 1.58 6.00 2.00 4.00 48.00 153.03 kg 100% 153.03
D16 Wall Rebar (Vertical) + u bar 1.60 1.60 2.36 2.02 1.58 8.00 2.00 4.00 64.00 238.18 kg 100% 238.18
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.12 14.31 1.00 1.00 1.00 1.00 14.31 m2 0% -
Step Iron Installation 4.00 1.00 1.00 4.00 4.00 unit 100% 4.00
Wall Pouring Concrete 1.60 1.60 0.20 1.12 1.43 1.00 1.00 1.00 1.00 1.43 m3 100% 1.43
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.83 11.71 1.00 1.00 1.00 1.00 11.71 m2 100% 11.71
Epoxy Coating 1.20 1.20 1.12 6.81 1.00 1.00 1.00 1.00 6.81 m2 0% -
Soil Backfill 1.60 1.60 1.88 24.91 1.00 1.00 1.00 1.00 24.91 m3 100% 24.91
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE MANHOLE 13.00 2,500.00 32,500.00 002 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
12 SM-B8
Excavation 5.51 5.51 1.59 0.70 23.65 1.00 1.00 1.00 1.00 23.65 m3 100% 23.65
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 0.83 2.02 1.58 5.00 2.00 4.00 40.00 127.52 kg 100% 127.52
Wall Rebar (Vertical) + u bar 1.60 1.60 2.07 2.02 1.58 8.00 2.00 4.00 64.00 208.88 kg 100% 208.88
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 0.83 10.60 1.00 1.00 1.00 1.00 10.60 m2 0% -
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.83 1.06 1.00 1.00 1.00 1.00 1.06 m3 100% 1.06
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.54 9.86 1.00 1.00 1.00 1.00 9.86 m2 100% 9.86
Epoxy Coating 1.20 1.20 0.83 5.41 1.00 1.00 1.00 1.00 5.41 m2 0% -
Soil Backfill 1.60 1.60 1.59 19.58 1.00 1.00 1.00 1.00 19.58 m3 100% 19.58
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 100% 6.40

13 SM-B7
Excavation 5.45 5.45 1.54 0.70 22.65 1.00 1.00 1.00 1.00 22.65 m3 100% 22.65
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
D16 Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
D16 Wall Rebar (Horizontal) 1.60 1.60 0.78 2.02 1.58 4.00 2.00 4.00 32.00 102.02 kg 100% 102.02
D16 Wall Rebar (Vertical) + u bar 1.60 1.60 2.02 2.02 1.58 8.00 2.00 4.00 64.00 203.83 kg 100% 203.83
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 0.78 9.96 1.00 1.00 1.00 1.00 9.96 m2 0% -
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.78 1.00 1.00 1.00 1.00 1.00 1.00 m3 100% 1.00
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.49 9.54 1.00 1.00 1.00 1.00 9.54 m2 0% -
Epoxy Coating 1.20 1.20 0.78 5.17 1.00 1.00 1.00 1.00 5.17 m2 0% -
Soil Backfill 1.60 1.60 1.54 18.71 1.00 1.00 1.00 1.00 18.71 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE MANHOLE 13.00 2,500.00 32,500.00 002 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
14 SM-B6
Excavation 5.40 5.40 1.50 0.70 21.87 1.00 1.00 1.00 1.00 21.87 m3 100% 21.87
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
D16 Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
D16 Wall Rebar (Horizontal) 1.60 1.60 0.74 2.02 1.58 4.00 2.00 4.00 32.00 102.02 kg 100% 102.02
D16 Wall Rebar (Vertical) + u bar 1.60 1.60 1.98 2.02 1.58 8.00 2.00 4.00 64.00 199.79 kg 100% 199.79
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Wall Formwork 1.60 1.60 0.74 9.45 1.00 1.00 1.00 1.00 9.45 m2 0% -
Step Iron Installation 2.00 1.00 1.00 2.00 2.00 unit 100% 2.00
Wall Pouring Concrete 1.60 1.60 0.20 0.74 0.94 1.00 1.00 1.00 1.00 0.94 m3 100% 0.94
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.45 9.28 1.00 1.00 1.00 1.00 9.28 m2 0% -
Epoxy Coating 1.20 1.20 0.74 4.98 1.00 1.00 1.00 1.00 4.98 m2 0% -
Soil Backfill 1.60 1.60 1.50 18.03 1.00 1.00 1.00 1.00 18.03 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

A.4 ZONE 4
15 SM-B3
Excavation 5.48 5.48 1.57 0.70 23.25 1.00 1.00 1.00 1.00 23.25 m3 100% 23.25
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 0.81 2.02 1.58 5.00 2.00 4.00 40.00 127.52 kg 100% 127.52
Wall Rebar (Vertical) + u bar 1.60 1.60 2.05 2.02 1.58 8.00 2.00 4.00 64.00 206.86 kg 100% 206.86
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Wall Formwork 1.60 1.60 0.81 10.34 1.00 1.00 1.00 1.00 10.34 m2 100% 10.34
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.81 1.03 1.00 1.00 1.00 1.00 1.03 m3 100% 1.03
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.52 9.73 1.00 1.00 1.00 1.00 9.73 m2 0% -
Epoxy Coating 1.20 1.20 0.81 5.32 1.00 1.00 1.00 1.00 5.32 m2 0% -
Soil Backfill 1.60 1.60 1.57 19.23 1.00 1.00 1.00 1.00 19.23 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE MANHOLE 13.00 2,500.00 32,500.00 002 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
16 SM-14
Excavation 5.72 5.72 1.77 0.70 27.35 1.00 1.00 1.00 1.00 27.35 m3 100% 27.35
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 1.01 2.02 1.58 6.00 2.00 4.00 48.00 153.03 kg 100% 153.03
Wall Rebar (Vertical) + u bar 1.60 1.60 2.25 2.02 1.58 8.00 2.00 4.00 64.00 227.06 kg 100% 227.06
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.01 12.90 1.00 1.00 1.00 1.00 12.90 m2 100% 12.90
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 1.01 1.29 1.00 1.00 1.00 1.00 1.29 m3 100% 1.29
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.72 11.01 1.00 1.00 1.00 1.00 11.01 m2 0% -
Epoxy Coating 1.20 1.20 1.01 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Soil Backfill 1.60 1.60 1.77 22.82 1.00 1.00 1.00 1.00 22.82 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

17 SM-07
Excavation 6.91 6.91 2.76 0.70 51.51 1.00 1.00 1.00 1.00 51.51 m3 100% 51.51
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 2.00 2.02 1.58 10.00 2.00 4.00 80.00 255.04 kg 100% 255.04
Wall Rebar (Vertical) + u bar 1.60 1.60 3.24 2.02 1.58 8.00 2.00 4.00 64.00 327.06 kg 100% 327.06
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 3.00 1.00 1.00 3.00 3.00 nos 100% 3.00
Wall Formwork 1.60 1.60 2.00 25.57 1.00 1.00 1.00 1.00 25.57 m2 100% 25.57
Step Iron Installation 7.00 1.00 1.00 7.00 7.00 unit 100% 7.00
Wall Pouring Concrete 1.60 1.60 0.20 2.00 2.56 1.00 1.00 1.00 1.00 2.56 m3 100% 2.56
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 2.71 17.34 1.00 1.00 1.00 1.00 17.34 m2 100% 17.34
Epoxy Coating 1.20 1.20 2.00 11.03 1.00 1.00 1.00 1.00 11.03 m2 0% -
Soil Backfill 1.60 1.60 2.76 44.44 1.00 1.00 1.00 1.00 44.44 m3 100% 44.44
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE MANHOLE 13.00 2,500.00 32,500.00 002 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
18 SM-06
Excavation 6.84 6.84 2.70 0.70 49.86 1.00 1.00 1.00 1.00 49.86 m3 100% 49.86
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 1.94 2.02 1.58 10.00 2.00 4.00 80.00 255.04 kg 100% 255.04
Wall Rebar (Vertical) + u bar 1.60 1.60 3.18 2.02 1.58 8.00 2.00 4.00 64.00 321.00 kg 100% 321.00
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.94 24.81 1.00 1.00 1.00 1.00 24.81 m2 100% 24.81
Step Iron Installation 6.00 1.00 1.00 6.00 6.00 unit 100% 6.00
Wall Pouring Concrete 1.60 1.60 0.20 1.94 2.48 1.00 1.00 1.00 1.00 2.48 m3 100% 2.48
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 2.65 16.96 1.00 1.00 1.00 1.00 16.96 m2 100% 16.96
Epoxy Coating 1.20 1.20 1.94 10.74 1.00 1.00 1.00 1.00 10.74 m2 0% -
Soil Backfill 1.60 1.60 2.70 42.95 1.00 1.00 1.00 1.00 42.95 m3 100% 42.95
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

19 SM-05
Excavation 6.80 6.80 2.67 0.70 49.05 1.00 1.00 1.00 1.00 49.05 m3 100% 49.05
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 1.91 2.02 1.58 10.00 2.00 4.00 80.00 255.04 kg 100% 255.04
Wall Rebar (Vertical) + u bar 1.60 1.60 3.15 2.02 1.58 8.00 2.00 4.00 64.00 317.97 kg 100% 317.97
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.91 24.42 1.00 1.00 1.00 1.00 24.42 m2 100% 24.42
Step Iron Installation 6.00 1.00 1.00 6.00 6.00 unit 100% 6.00
Wall Pouring Concrete 1.60 1.60 0.20 1.91 2.44 1.00 1.00 1.00 1.00 2.44 m3 100% 2.44
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 2.62 16.77 1.00 1.00 1.00 1.00 16.77 m2 100% 16.77
Epoxy Coating 1.20 1.20 1.91 10.60 1.00 1.00 1.00 1.00 10.60 m2 0% -
Soil Backfill 1.60 1.60 2.67 42.21 1.00 1.00 1.00 1.00 42.21 m3 100% 42.21
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE MANHOLE 13.00 2,500.00 32,500.00 002 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
20 SM-04
Excavation 6.74 6.74 2.62 0.70 47.71 1.00 1.00 1.00 1.00 47.71 m3 100% 47.71
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 1.86 2.02 1.58 10.00 2.00 4.00 80.00 255.04 kg 100% 255.04
Wall Rebar (Vertical) + u bar 1.60 1.60 3.10 2.02 1.58 8.00 2.00 4.00 64.00 312.92 kg 100% 312.92
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 3.00 1.00 1.00 3.00 3.00 nos 100% 3.00
Wall Formwork 1.60 1.60 1.86 23.78 1.00 1.00 1.00 1.00 23.78 m2 100% 23.78
Step Iron Installation 6.00 1.00 1.00 6.00 6.00 unit 100% 6.00
Wall Pouring Concrete 1.60 1.60 0.20 1.86 2.38 1.00 1.00 1.00 1.00 2.38 m3 100% 2.38
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 2.57 16.45 1.00 1.00 1.00 1.00 16.45 m2 0% -
Epoxy Coating 1.20 1.20 1.86 10.36 1.00 1.00 1.00 1.00 10.36 m2 0% -
Soil Backfill 1.60 1.60 2.62 41.00 1.00 1.00 1.00 1.00 41.00 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

A.5 ZONE 5
21 SM-A1
Excavation 5.36 5.36 1.47 0.70 21.29 1.00 1.00 1.00 1.00 21.29 m3 100% 21.29
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
D16 Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
D16 Wall Rebar (Horizontal) 1.60 1.60 0.71 2.02 1.58 4.00 2.00 4.00 32.00 102.02 kg 100% 102.02
D16 Wall Rebar (Vertical) + u bar 1.60 1.60 1.95 2.02 1.58 8.00 2.00 4.00 64.00 196.76 kg 100% 196.76
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Wall Formwork 1.60 1.60 0.71 9.06 1.00 1.00 1.00 1.00 9.06 m2 100% 9.06
Step Iron Installation 2.00 1.00 1.00 2.00 2.00 unit 100% 2.00
Wall Pouring Concrete 1.60 1.60 0.20 0.71 0.91 1.00 1.00 1.00 1.00 0.91 m3 100% 0.91
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.42 9.09 1.00 1.00 1.00 1.00 9.09 m2 0% -
Epoxy Coating 1.20 1.20 0.71 4.84 1.00 1.00 1.00 1.00 4.84 m2 0% -
Soil Backfill 1.60 1.60 1.47 17.53 1.00 1.00 1.00 1.00 17.53 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE MANHOLE 13.00 2,500.00 32,500.00 002 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
22 SM-01
Excavation 5.60 5.60 1.67 0.70 25.27 1.00 1.00 1.00 1.00 25.27 m3 100% 25.27
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
D16 Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
D16 Wall Rebar (Horizontal) 1.60 1.60 0.91 2.02 1.58 5.00 2.00 4.00 40.00 127.52 kg 100% 127.52
D16 Wall Rebar (Vertical) + u bar 1.60 1.60 2.15 2.02 1.58 8.00 2.00 4.00 64.00 216.96 kg 100% 216.96
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 0.91 11.62 1.00 1.00 1.00 1.00 11.62 m2 100% 11.62
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.91 1.16 1.00 1.00 1.00 1.00 1.16 m3 100% 1.16
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.62 10.37 1.00 1.00 1.00 1.00 10.37 m2 100% 10.37
Epoxy Coating 1.20 1.20 0.91 5.80 1.00 1.00 1.00 1.00 5.80 m2 0% -
Soil Backfill 1.60 1.60 1.67 20.99 1.00 1.00 1.00 1.00 20.99 m3 100% 20.99
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

23 SM-02
Excavation 5.81 5.81 1.84 0.70 28.85 1.00 1.00 1.00 1.00 28.85 m3 100% 28.85
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 1.08 2.02 1.58 6.00 2.00 4.00 48.00 153.03 kg 100% 153.03
Wall Rebar (Vertical) + u bar 1.60 1.60 2.32 2.02 1.58 8.00 2.00 4.00 64.00 234.14 kg 100% 234.14
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 3.00 1.00 1.00 3.00 3.00 nos 100% 3.00
Wall Formwork 1.60 1.60 1.08 13.80 1.00 1.00 1.00 1.00 13.80 m2 100% 13.80
Step Iron Installation 4.00 1.00 1.00 4.00 4.00 unit 100% 4.00
Wall Pouring Concrete 1.60 1.60 0.20 1.08 1.38 1.00 1.00 1.00 1.00 1.38 m3 100% 1.38
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.79 11.46 1.00 1.00 1.00 1.00 11.46 m2 0% -
Epoxy Coating 1.20 1.20 1.08 6.61 1.00 1.00 1.00 1.00 6.61 m2 0% -
Soil Backfill 1.60 1.60 1.84 24.14 1.00 1.00 1.00 1.00 24.14 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE MANHOLE 13.00 2,500.00 32,500.00 002 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
24 SM-13
Excavation 5.60 5.60 1.67 0.70 25.27 1.00 1.00 1.00 1.00 25.27 m3 100% 25.27
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 0.91 2.02 1.58 5.00 2.00 4.00 40.00 127.52 kg 100% 127.52
Wall Rebar (Vertical) + u bar 1.60 1.60 2.15 2.02 1.58 8.00 2.00 4.00 64.00 216.96 kg 100% 216.96
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 0.91 11.62 1.00 1.00 1.00 1.00 11.62 m2 100% 11.62
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.91 1.16 1.00 1.00 1.00 1.00 1.16 m3 100% 1.16
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.62 10.37 1.00 1.00 1.00 1.00 10.37 m2 0% -
Epoxy Coating 1.20 1.20 0.91 5.80 1.00 1.00 1.00 1.00 5.80 m2 0% -
Soil Backfill 1.60 1.60 1.67 20.99 1.00 1.00 1.00 1.00 20.99 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

25 SM-A2
Excavation 5.48 5.48 1.57 0.70 23.25 1.00 1.00 1.00 1.00 23.25 m3 100% 23.25
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 0.81 2.02 1.58 5.00 2.00 4.00 40.00 127.52 kg 100% 127.52
Wall Rebar (Vertical) + u bar 1.60 1.60 2.05 2.02 1.58 8.00 2.00 4.00 64.00 206.86 kg 100% 206.86
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Wall Formwork 1.60 1.60 0.81 10.34 1.00 1.00 1.00 1.00 10.34 m2 100% 10.34
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.81 1.03 1.00 1.00 1.00 1.00 1.03 m3 100% 1.03
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.52 9.73 1.00 1.00 1.00 1.00 9.73 m2 0% -
Epoxy Coating 1.20 1.20 0.81 5.32 1.00 1.00 1.00 1.00 5.32 m2 0% -
Soil Backfill 1.60 1.60 1.57 19.23 1.00 1.00 1.00 1.00 19.23 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE MANHOLE 13.00 2,500.00 32,500.00 002 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A.6 ZONE 6
26 SM-03
Excavation 6.61 6.61 2.51 0.70 44.81 1.00 1.00 1.00 1.00 44.81 m3 100% 44.81
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 1.75 2.02 1.58 9.00 2.00 4.00 72.00 229.54 kg 100% 229.54
Wall Rebar (Vertical) + u bar 1.60 1.60 2.99 2.02 1.58 8.00 2.00 4.00 64.00 301.81 kg 100% 301.81
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 1.75 22.37 1.00 1.00 1.00 1.00 22.37 m2 0% -
Step Iron Installation 6.00 1.00 1.00 6.00 6.00 unit 100% 6.00
Wall Pouring Concrete 1.60 1.60 0.20 1.75 2.24 1.00 1.00 1.00 1.00 2.24 m3 100% 2.24
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 2.46 15.74 1.00 1.00 1.00 1.00 15.74 m2 100% 15.74
Epoxy Coating 1.20 1.20 1.75 9.83 1.00 1.00 1.00 1.00 9.83 m2 0% -
Soil Backfill 1.60 1.60 2.51 38.38 1.00 1.00 1.00 1.00 38.38 m3 100% 38.38
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

27 SM-B1
Excavation 5.48 5.48 1.57 0.70 23.25 1.00 1.00 1.00 1.00 23.25 m3 100% 23.25
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 0.81 2.02 1.58 5.00 2.00 4.00 40.00 127.52 kg 100% 127.52
Wall Rebar (Vertical) + u bar 1.60 1.60 2.05 2.02 1.58 8.00 2.00 4.00 64.00 206.86 kg 100% 206.86
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Wall Formwork 1.60 1.60 0.81 10.34 1.00 1.00 1.00 1.00 10.34 m2 100% 10.34
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.81 1.03 1.00 1.00 1.00 1.00 1.03 m3 100% 1.03
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.52 9.73 1.00 1.00 1.00 1.00 9.73 m2 100% 9.73
Epoxy Coating 1.20 1.20 0.81 5.32 1.00 1.00 1.00 1.00 5.32 m2 0% -
Soil Backfill 1.60 1.60 1.57 19.23 1.00 1.00 1.00 1.00 19.23 m3 100% 19.23
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE MANHOLE 13.00 2,500.00 32,500.00 002 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
28 SM-B2
Excavation 5.52 5.52 1.60 0.70 23.85 1.00 1.00 1.00 1.00 23.85 m3 100% 23.85
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 0.84 2.02 1.58 5.00 2.00 4.00 40.00 127.52 kg 100% 127.52
Wall Rebar (Vertical) + u bar 1.60 1.60 2.08 2.02 1.58 8.00 2.00 4.00 64.00 209.89 kg 100% 209.89
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 0.84 10.73 1.00 1.00 1.00 1.00 10.73 m2 100% 10.73
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.84 1.07 1.00 1.00 1.00 1.00 1.07 m3 100% 1.07
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.55 9.92 1.00 1.00 1.00 1.00 9.92 m2 100% 9.92
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE MANHOLE 13.00 2,500.00 32,500.00 002 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Epoxy Coating 1.20 1.20 0.84 5.46 1.00 1.00 1.00 1.00 5.46 m2 0% -
Soil Backfill 1.60 1.60 1.60 19.75 1.00 1.00 1.00 1.00 19.75 m3 100% 19.75
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

RECAP FOR MAIN PROGRESS (BOQ ITEMS) Notes :


Progress Date 1. The Quantity Calculation is Still PT. SSA Version, It is Not Yet Together Measurement With KINE's Quantity Surveyor.
31/08/2023 2. Quantity Calculation Based On Approved Shop Drawing and Lotte Chemical E & C For Construction Drawing.

Total Progress Progress


No. Description Unit Remarks
Quantity Quantity Percentages
1 Excavation m3 965.40 965.40 100.0000%
2 Pile Cut Off nos 28.00 28.00 100.0000%
3 Plastic Sheet & Lean Concrete m3 4.54 4.54 100.0000%
4 Lean Concrete Formwork m2 10.08 10.08 100.0000%
5 Rebar (D16) kg 16,266.88 14,994.19 92.1762%
Bottom Slab Rebar 2,828.21 2,828.21
Wall Rebar (Horizontal) 5,024.36 5,024.36
Wall Rebar (Vertical) + u bar 7,141.62 7,141.62
Upper Slab Rebar 1,272.69 -
6 Formwork m2 657.72 434.92 66.1256%
Ground Slab Formwork 89.60 89.60
Wall Formwork 460.60 345.32
Upper Slab Formwork 107.52 -
7 FC 24 Concrete m3 96.24 77.04 80.0543%
Ground Slab Pouring Concrete 35.84 35.84
Wall Pouring Concrete 46.06 41.20
Upper Slab Pouring Concrete 14.34 -
8 Step Iron Installation nos 121.00 108.00 89.2562%
9 Cast Iron Manhole Cover unit 28.00 - 0.0000%
10 Bitumen Coating m2 357.89 166.66 46.5665%
11 Epoxy Coating m2 213.04 - 0.0000%
12 Soil Backfill m3 818.66 396.18 48.3935% ARITMATH CHECKING
13 Waterstop Installation m 179.20 179.20 100.0000% New Items RECAP 19,980.83
14 HDPE Connection nos 55.00 50.00 90.9091% Method BREAKDOWN 19,980.83
15 Join Sealant m 179.20 6.40 3.5714% New Items IF ZERO = OK! -

GLOBAL PROGRESS FOR SEWAGE MANHOLE (AVERAGE PRORATE BY ITEMS) 67.8035%

31/08/2023
Checked by,
PT. Sepuluh Sumber Anugerah

Herdy Dwiyana
Quantity Surveyor
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE WORKS SECTION 2 AREA 002A Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A SEWAGE WORKS SECTION 2 AREA 1.00
1 SMH-01
Excavation 5.46 5.46 1.55 1.00 22.85 1.00 1.00 1.00 1.00 22.85 m3 100% 22.85
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 0.79 2.02 1.58 4.00 2.00 4.00 32.00 102.02 kg 100% 102.02
Wall Rebar (Vertical) + u bar 1.60 1.60 2.03 2.02 1.58 8.00 2.00 4.00 64.00 204.84 kg 100% 204.84
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 0% -
HDPE Connection 1.00 1.00 1.00 1.00 1.00 nos 0% -
Wall Formwork 1.60 1.60 0.79 10.09 1.00 1.00 1.00 1.00 10.09 m2 0% -
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 0% -
Wall Pouring Concrete 1.60 1.60 0.20 0.79 1.01 1.00 1.00 1.00 1.00 1.01 m3 0% -
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.50 9.60 1.00 1.00 1.00 1.00 9.60 m2 0% -
Epoxy Coating 1.20 1.20 0.79 5.22 1.00 1.00 1.00 1.00 5.22 m2 0% -
Soil Backfill 1.60 1.60 1.55 18.88 1.00 1.00 1.00 1.00 18.88 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

2 SMH-02
Excavation 5.54 5.54 1.62 1.00 24.25 1.00 1.00 1.00 1.00 24.25 m3 100% 24.25
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 0.86 2.02 1.58 5.00 2.00 4.00 40.00 127.52 kg 100% 127.52
Wall Rebar (Vertical) + u bar 1.60 1.60 2.10 2.02 1.58 8.00 2.00 4.00 64.00 211.91 kg 100% 211.91
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 0% -
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 0% -
Wall Formwork 1.60 1.60 0.86 10.98 1.00 1.00 1.00 1.00 10.98 m2 0% -
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 0% -
Wall Pouring Concrete 1.60 1.60 0.20 0.86 1.10 1.00 1.00 1.00 1.00 1.10 m3 0% -
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.57 10.05 1.00 1.00 1.00 1.00 10.05 m2 0% -
Epoxy Coating 1.20 1.20 0.86 5.56 1.00 1.00 1.00 1.00 5.56 m2 0% -
Soil Backfill 1.60 1.60 1.62 20.10 1.00 1.00 1.00 1.00 20.10 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE WORKS SECTION 2 AREA 002A Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
3 SMH-03
Excavation 5.62 5.62 1.68 1.00 25.47 1.00 1.00 1.00 1.00 25.47 m3 100% 25.47
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 0.92 2.02 1.58 5.00 2.00 4.00 40.00 127.52 kg 100% 127.52
Wall Rebar (Vertical) + u bar 1.60 1.60 2.16 2.02 1.58 8.00 2.00 4.00 64.00 217.97 kg 100% 217.97
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 3.00 1.00 1.00 3.00 3.00 nos 100% 3.00
Wall Formwork 1.60 1.60 0.92 11.75 1.00 1.00 1.00 1.00 11.75 m2 100% 11.75
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.92 1.18 1.00 1.00 1.00 1.00 1.18 m3 100% 1.18
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.63 10.43 1.00 1.00 1.00 1.00 10.43 m2 100% 10.43
Epoxy Coating 1.20 1.20 0.92 5.85 1.00 1.00 1.00 1.00 5.85 m2 0% -
Soil Backfill 1.60 1.60 1.68 21.17 1.00 1.00 1.00 1.00 21.17 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

4 SMH-04
Excavation 5.69 5.69 1.74 1.00 26.72 1.00 1.00 1.00 1.00 26.72 m3 100% 26.72
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 0% -
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 0% -
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 0% -
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 0% -
Wall Rebar (Horizontal) 1.60 1.60 0.98 2.02 1.58 5.00 2.00 4.00 40.00 127.52 kg 0% -
Wall Rebar (Vertical) + u bar 1.60 1.60 2.22 2.02 1.58 8.00 2.00 4.00 64.00 224.03 kg 0% -
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 0% -
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 0% -
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 0% -
HDPE Connection 3.00 1.00 1.00 3.00 3.00 nos 0% -
Wall Formwork 1.60 1.60 0.98 12.52 1.00 1.00 1.00 1.00 12.52 m2 0% -
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 0% -
Wall Pouring Concrete 1.60 1.60 0.20 0.98 1.25 1.00 1.00 1.00 1.00 1.25 m3 0% -
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.69 10.82 1.00 1.00 1.00 1.00 10.82 m2 0% -
Epoxy Coating 1.20 1.20 0.98 6.13 1.00 1.00 1.00 1.00 6.13 m2 0% -
Soil Backfill 1.60 1.60 1.74 22.27 1.00 1.00 1.00 1.00 22.27 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE WORKS SECTION 2 AREA 002A Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
5 SMH-05
Excavation 5.76 5.76 1.80 1.00 27.99 1.00 1.00 1.00 1.00 27.99 m3 100% 27.99
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 0% -
Wall Rebar (Horizontal) 1.60 1.60 1.04 2.02 1.58 6.00 2.00 4.00 48.00 153.03 kg 0% -
Wall Rebar (Vertical) + u bar 1.60 1.60 2.28 2.02 1.58 8.00 2.00 4.00 64.00 230.09 kg 0% -
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 0% -
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 0% -
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 0% -
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 0% -
Wall Formwork 1.60 1.60 1.04 13.29 1.00 1.00 1.00 1.00 13.29 m2 0% -
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 0% -
Wall Pouring Concrete 1.60 1.60 0.20 1.04 1.33 1.00 1.00 1.00 1.00 1.33 m3 0% -
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.75 11.20 1.00 1.00 1.00 1.00 11.20 m2 0% -
Epoxy Coating 1.20 1.20 1.04 6.42 1.00 1.00 1.00 1.00 6.42 m2 0% -
Soil Backfill 1.60 1.60 1.80 23.39 1.00 1.00 1.00 1.00 23.39 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

6 SMH-06
Excavation 5.84 5.84 1.87 1.00 29.51 1.00 1.00 1.00 1.00 29.51 m3 100% 29.51
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 0% -
Wall Rebar (Horizontal) 1.60 1.60 1.11 2.02 1.58 6.00 2.00 4.00 48.00 153.03 kg 0% -
Wall Rebar (Vertical) + u bar 1.60 1.60 2.35 2.02 1.58 8.00 2.00 4.00 64.00 237.17 kg 0% -
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 0% -
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 0% -
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 0% -
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 0% -
Wall Formwork 1.60 1.60 1.11 14.18 1.00 1.00 1.00 1.00 14.18 m2 0% -
Step Iron Installation 4.00 1.00 1.00 4.00 4.00 unit 0% -
Wall Pouring Concrete 1.60 1.60 0.20 1.11 1.42 1.00 1.00 1.00 1.00 1.42 m3 0% -
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.82 11.65 1.00 1.00 1.00 1.00 11.65 m2 0% -
Epoxy Coating 1.20 1.20 1.11 6.76 1.00 1.00 1.00 1.00 6.76 m2 0% -
Soil Backfill 1.60 1.60 1.87 24.72 1.00 1.00 1.00 1.00 24.72 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE WORKS SECTION 2 AREA 002A Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
7 SMH-07
Excavation 5.94 5.94 1.95 1.00 31.27 1.00 1.00 1.00 1.00 31.27 m3 100% 31.27
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 0% -
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 0% -
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 0% -
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 0% -
Wall Rebar (Horizontal) 1.60 1.60 1.19 2.02 1.58 6.00 2.00 4.00 48.00 153.03 kg 0% -
Wall Rebar (Vertical) + u bar 1.60 1.60 2.43 2.02 1.58 8.00 2.00 4.00 64.00 245.25 kg 0% -
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 0% -
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 0% -
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 0% -
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 0% -
Wall Formwork 1.60 1.60 1.19 15.21 1.00 1.00 1.00 1.00 15.21 m2 0% -
Step Iron Installation 4.00 1.00 1.00 4.00 4.00 unit 0% -
Wall Pouring Concrete 1.60 1.60 0.20 1.19 1.52 1.00 1.00 1.00 1.00 1.52 m3 0% -
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.90 12.16 1.00 1.00 1.00 1.00 12.16 m2 0% -
Epoxy Coating 1.20 1.20 1.19 7.14 1.00 1.00 1.00 1.00 7.14 m2 0% -
Soil Backfill 1.60 1.60 1.95 26.28 1.00 1.00 1.00 1.00 26.28 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

8 SMH-08
Excavation 5.22 5.22 1.35 1.00 19.03 1.00 1.00 1.00 1.00 19.03 m3 0% -
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 0% -
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 0% -
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 0% -
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 0% -
Wall Rebar (Horizontal) 1.60 1.60 0.59 2.02 1.58 3.00 2.00 4.00 24.00 76.51 kg 0% -
Wall Rebar (Vertical) + u bar 1.60 1.60 1.83 2.02 1.58 8.00 2.00 4.00 64.00 184.64 kg 0% -
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 0% -
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 0% -
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 0% -
HDPE Connection 1.00 1.00 1.00 1.00 1.00 nos 0% -
Wall Formwork 1.60 1.60 0.59 7.53 1.00 1.00 1.00 1.00 7.53 m2 0% -
Step Iron Installation 2.00 1.00 1.00 2.00 2.00 unit 0% -
Wall Pouring Concrete 1.60 1.60 0.20 0.59 0.75 1.00 1.00 1.00 1.00 0.75 m3 0% -
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.30 8.32 1.00 1.00 1.00 1.00 8.32 m2 0% -
Epoxy Coating 1.20 1.20 0.59 4.26 1.00 1.00 1.00 1.00 4.26 m2 0% -
Soil Backfill 1.60 1.60 1.35 15.57 1.00 1.00 1.00 1.00 15.57 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE WORKS SECTION 2 AREA 002A Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
9 SEWAGE TANK
Excavation 2.60 2.80 6.10 1.00 44.41 1.00 1.00 1.00 1.00 44.41 m3 0% -
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 0% -
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 0% -
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 0% -
Bottom Slab Rebar 2.25 2.25 1.58 45.00 1.00 1.00 45.00 159.80 kg 0% -
Wall Rebar (Horizontal) 6.26 6.40 1.58 63.00 1.00 1.00 63.00 636.35 kg 0% -
Wall Rebar (Vertical) + u bar 6.26 6.40 1.58 64.00 1.00 1.00 64.00 632.31 kg 0% -
Waterstop Installation 1.70 1.70 6.80 1.00 1.00 1.00 1.00 6.80 m1 0% -
Ground Slab Formwork 3.20 1.00 1.00 1.00 1.00 3.20 m2 0% -
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 0% -
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 0% -
Wall Formwork 1.60 1.60 6.10 39.04 1.00 2.00 1.00 2.00 78.08 m2 0% -
Step Iron Installation 6.00 1.00 1.00 6.00 6.00 unit 0% -
Wall Pouring Concrete 1.60 1.60 0.20 6.10 7.81 1.00 1.00 1.00 1.00 7.81 m3 0% -
Upper Slab Formwork 3.20 1.00 1.00 1.00 1.00 3.20 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 36.00 1.00 1.00 36.00 102.27 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 6.10 39.04 1.00 1.00 1.00 1.00 39.04 m2 0% -
Epoxy Coating 1.20 1.20 5.35 27.12 1.00 1.00 1.00 1.00 27.12 m2 0% -
Soil Backfill 1.80 1.80 6.10 28.79 1.00 1.00 1.00 1.00 28.79 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

10 SMH-10
Excavation 5.22 5.22 1.35 1.00 19.03 1.00 1.00 1.00 1.00 19.03 m3 100% 19.03
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 0.59 2.02 1.58 3.00 2.00 4.00 24.00 76.51 kg 100% 76.51
Wall Rebar (Vertical) + u bar 1.60 1.60 1.83 2.02 1.58 8.00 2.00 4.00 64.00 184.64 kg 100% 184.64
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Wall Formwork 1.60 1.60 0.59 7.53 1.00 1.00 1.00 1.00 7.53 m2 100% 7.53
Step Iron Installation 2.00 1.00 1.00 2.00 2.00 unit 100% 2.00
Wall Pouring Concrete 1.60 1.60 0.20 0.59 0.75 1.00 1.00 1.00 1.00 0.75 m3 100% 0.75
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.30 8.32 1.00 1.00 1.00 1.00 8.32 m2 100% 8.32
Epoxy Coating 1.20 1.20 0.59 4.26 1.00 1.00 1.00 1.00 4.26 m2 0% -
Soil Backfill 1.60 1.60 1.35 15.57 1.00 1.00 1.00 1.00 15.57 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE WORKS SECTION 2 AREA 002A Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
11 SMH-11
Excavation 5.22 5.22 1.35 1.00 19.03 1.00 1.00 1.00 1.00 19.03 m3 100% 19.03
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 0.59 2.02 1.58 3.00 2.00 4.00 24.00 76.51 kg 100% 76.51
Wall Rebar (Vertical) + u bar 1.60 1.60 1.83 2.02 1.58 8.00 2.00 4.00 64.00 184.64 kg 100% 184.64
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Wall Formwork 1.60 1.60 0.59 7.53 1.00 1.00 1.00 1.00 7.53 m2 100% 7.53
Step Iron Installation 2.00 1.00 1.00 2.00 2.00 unit 100% 2.00
Wall Pouring Concrete 1.60 1.60 0.20 0.59 0.75 1.00 1.00 1.00 1.00 0.75 m3 100% 0.75
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.30 8.32 1.00 1.00 1.00 1.00 8.32 m2 0% -
Epoxy Coating 1.20 1.20 0.59 4.26 1.00 1.00 1.00 1.00 4.26 m2 0% -
Soil Backfill 1.60 1.60 1.35 15.57 1.00 1.00 1.00 1.00 15.57 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

12 SMH-12
Excavation 5.27 5.27 1.39 1.00 19.77 1.00 1.00 1.00 1.00 19.77 m3 100% 19.77
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 0.63 2.02 1.58 4.00 2.00 4.00 32.00 102.02 kg 100% 102.02
Wall Rebar (Vertical) + u bar 1.60 1.60 1.87 2.02 1.58 8.00 2.00 4.00 64.00 188.68 kg 100% 188.68
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 0.63 8.04 1.00 1.00 1.00 1.00 8.04 m2 100% 8.04
Step Iron Installation 2.00 1.00 1.00 2.00 2.00 unit 100% 2.00
Wall Pouring Concrete 1.60 1.60 0.20 0.63 0.80 1.00 1.00 1.00 1.00 0.80 m3 100% 0.80
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.34 8.58 1.00 1.00 1.00 1.00 8.58 m2 0% -
Epoxy Coating 1.20 1.20 0.63 4.45 1.00 1.00 1.00 1.00 4.45 m2 0% -
Soil Backfill 1.60 1.60 1.39 16.21 1.00 1.00 1.00 1.00 16.21 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE WORKS SECTION 2 AREA 002A Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
13 SMH-13
Excavation 5.30 5.30 1.42 1.00 20.34 1.00 1.00 1.00 1.00 20.34 m3 100% 20.34
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 0% -
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 0% -
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 0% -
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 0% -
Wall Rebar (Horizontal) 1.60 1.60 0.66 2.02 1.58 4.00 2.00 4.00 32.00 102.02 kg 0% -
Wall Rebar (Vertical) + u bar 1.60 1.60 1.90 2.02 1.58 8.00 2.00 4.00 64.00 191.71 kg 0% -
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 0% -
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 0% -
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 0% -
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 0% -
Wall Formwork 1.60 1.60 0.66 8.42 1.00 1.00 1.00 1.00 8.42 m2 0% -
Step Iron Installation 2.00 1.00 1.00 2.00 2.00 unit 0% -
Wall Pouring Concrete 1.60 1.60 0.20 0.66 0.84 1.00 1.00 1.00 1.00 0.84 m3 0% -
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.37 8.77 1.00 1.00 1.00 1.00 8.77 m2 0% -
Epoxy Coating 1.20 1.20 0.66 4.60 1.00 1.00 1.00 1.00 4.60 m2 0% -
Soil Backfill 1.60 1.60 1.42 16.70 1.00 1.00 1.00 1.00 16.70 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

14 SMH-14
Excavation 5.46 5.46 1.55 1.00 22.85 1.00 1.00 1.00 1.00 22.85 m3 100% 22.85
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 0.79 2.02 1.58 4.00 2.00 4.00 32.00 102.02 kg 50% 51.01
Wall Rebar (Vertical) + u bar 1.60 1.60 2.03 2.02 1.58 8.00 2.00 4.00 64.00 204.84 kg 50% 102.42
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Wall Formwork 1.60 1.60 0.79 10.09 1.00 1.00 1.00 1.00 10.09 m2 100% 10.09
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.79 1.01 1.00 1.00 1.00 1.00 1.01 m3 100% 1.01
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.50 9.60 1.00 1.00 1.00 1.00 9.60 m2 0% -
Epoxy Coating 1.20 1.20 0.79 5.22 1.00 1.00 1.00 1.00 5.22 m2 0% -
Soil Backfill 1.60 1.60 1.55 18.88 1.00 1.00 1.00 1.00 18.88 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE WORKS SECTION 2 AREA 002A Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
15 SMH-15
Excavation 5.52 5.52 1.60 1.00 23.85 1.00 1.00 1.00 1.00 23.85 m3 100% 23.85
Pile Cut Off 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Plastic Sheet & Lean Concrete 1.80 1.80 0.05 0.16 1.00 1.00 1.00 1.00 0.16 m3 100% 0.16
Lean Concrete Formwork 1.80 1.80 0.05 0.36 1.00 1.00 1.00 1.00 0.36 m2 100% 0.36
Bottom Slab Rebar 2.00 2.00 1.58 8.00 2.00 2.00 32.00 101.01 kg 100% 101.01
Wall Rebar (Horizontal) 1.60 1.60 0.84 2.02 1.58 5.00 2.00 4.00 40.00 127.52 kg 50% 63.76
Wall Rebar (Vertical) + u bar 1.60 1.60 2.08 2.02 1.58 8.00 2.00 4.00 64.00 209.89 kg 50% 104.95
Waterstop Installation 1.60 1.60 6.40 1.00 1.00 1.00 1.00 6.40 m1 100% 6.40
Ground Slab Formwork 1.60 1.60 0.50 3.20 1.00 1.00 1.00 1.00 3.20 m2 100% 3.20
Ground Slab Pouring Concrete 1.60 1.60 0.50 1.28 1.00 1.00 1.00 1.00 1.28 m3 100% 1.28
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 1.60 1.60 0.84 10.73 1.00 1.00 1.00 1.00 10.73 m2 100% 10.73
Step Iron Installation 3.00 1.00 1.00 3.00 3.00 unit 100% 3.00
Wall Pouring Concrete 1.60 1.60 0.20 0.84 1.07 1.00 1.00 1.00 1.00 1.07 m3 100% 1.07
Upper Slab Formwork 3.84 1.00 1.00 1.00 1.00 3.84 m2 0% -
Upper Slab Rebar 1.80 1.80 1.58 16.00 1.00 1.00 16.00 45.45 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 1.60 1.60 0.20 0.51 1.00 1.00 1.00 1.00 0.51 m3 0% -
Bitumen Coating 1.60 1.60 1.55 9.92 1.00 1.00 1.00 1.00 9.92 m2 0% -
Epoxy Coating 1.20 1.20 0.84 5.46 1.00 1.00 1.00 1.00 5.46 m2 0% -
Soil Backfill 1.60 1.60 1.60 19.75 1.00 1.00 1.00 1.00 19.75 m3 0% -
Join Sealant 1.60 1.60 1.00 1.00 4.00 4.00 6.40 m1 0% -

16 SEPTIC TANK MS
Excavation 7.30 7.30 3.15 0.76 127.76 1.00 1.00 1.00 1.00 127.76 m3 0% -
Pile Cut Off 6.00 1.00 1.00 6.00 6.00 nos 0% -
Plastic Sheet & Lean Concrete 5.50 5.50 0.05 1.51 1.00 1.00 1.00 1.00 1.51 m3 0% -
Lean Concrete Formwork 5.50 5.50 0.05 1.10 1.00 1.00 1.00 1.00 1.10 m2 0% -
Bottom Slab Rebar 6.05 6.05 1.58 62.00 1.00 1.00 62.00 592.00 kg 0% -
Bottom Slab Rebar 6.05 6.05 1.58 62.00 1.00 1.00 62.00 592.00 kg 0%
Wall Rebar (Horizontal) 3.57 27.56 1.04 36.00 1.00 1.00 36.00 1,033.72 kg 0% -
Wall Rebar (Vertical) + u bar 3.57 27.56 1.04 276.00 1.00 1.00 276.00 1,026.59 kg 0% -
Waterstop Installation 5.30 5.30 21.20 2.00 1.00 1.00 2.00 42.40 m1 0% -
Ground Slab Formwork 10.60 1.00 1.00 1.00 1.00 10.60 m2 0% -
Ground Slab Pouring Concrete 5.30 5.30 0.50 14.05 1.00 1.00 1.00 1.00 14.05 m3 0% -
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 0% -
Wall Formwork 5.30 5.30 3.15 66.78 1.00 2.00 1.00 2.00 133.56 m2 0% -
Wall Pouring Concrete 5.30 5.30 0.30 3.15 20.03 1.00 1.00 1.00 1.00 20.03 m3 0% -
Upper Slab Formwork 5.30 1.00 1.00 1.00 1.00 5.30 m2 0% -
Upper Slab Rebar 6.05 6.05 1.04 62.00 1.00 1.00 62.00 390.81 kg 0% -
Upper Slab Rebar 6.05 6.05 1.04 62.00 1.00 1.00 62.00 390.81 kg 0%
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 5.30 5.30 0.25 7.02 1.00 1.00 1.00 1.00 7.02 m3 0% -
Bitumen Coating 5.30 5.30 3.15 66.78 1.00 1.00 1.00 1.00 66.78 m2 0% -
Soil Backfill 39.28 1.00 1.00 1.00 1.00 39.28 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE WORKS SECTION 2 AREA 002A Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
17 SEPTIC TANK MW
Excavation 4.30 4.30 2.10 0.76 29.55 1.00 1.00 1.00 1.00 29.55 m3 100% 29.55
Pile Cut Off 3.00 1.00 1.00 3.00 3.00 nos 100% 3.00
Plastic Sheet & Lean Concrete 2.50 2.50 0.05 0.31 1.00 1.00 1.00 1.00 0.31 m3 100% 0.31
Lean Concrete Formwork 2.50 2.50 0.05 0.50 1.00 1.00 1.00 1.00 0.50 m2 100% 0.50
x Bottom Slab Rebar 2.85 2.85 1.58 12.00 2.00 1.00 24.00 107.95 kg 100% 107.95
y Bottom Slab Rebar 2.85 2.85 1.58 12.00 2.00 1.00 24.00 107.95 kg 100% 107.95
Wall Rebar (Horizontal) 2.72 1.04 16.00 4.00 1.00 64.00 181.37 kg 100% 181.37
Wall Rebar (Vertical) + u bar 2.93 1.04 24.00 4.00 1.00 96.00 292.56 kg 100% 292.56
Waterstop Installation 2.30 2.30 9.20 1.00 1.00 1.00 1.00 9.20 m1 100% 9.20
Ground Slab Formwork 2.30 2.30 4.60 1.00 1.00 1.00 1.00 4.60 m2 100% 4.60
Ground Slab Pouring Concrete 2.30 2.30 0.50 2.65 1.00 1.00 1.00 1.00 2.65 m3 100% 2.65
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 2.30 2.30 2.10 38.64 1.00 2.00 1.00 2.00 77.28 m2 100% 77.28
Wall Pouring Concrete 2.30 2.30 0.25 1.55 3.57 1.00 1.00 1.00 1.00 3.57 m3 100% 3.57
Upper Slab Formwork 2.30 2.30 7.59 1.00 1.00 1.00 1.00 7.59 m2 0% -
Upper Slab Rebar 2.85 2.85 1.04 12.00 2.00 1.00 24.00 71.26 kg 0% -
Upper Slab Rebar 2.85 2.85 1.04 12.00 2.00 1.00 24.00 71.26 kg 0%
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 2.30 2.30 0.25 1.32 1.00 1.00 1.00 1.00 1.32 m3 0% -
Bitumen Coating 2.30 2.30 2.10 19.32 1.00 1.00 1.00 1.00 19.32 m2 100% 19.32
Soil Backfill 2.30 2.30 18.44 1.00 1.00 1.00 1.00 18.44 m3 0% -

18 SEPTIC TANK FS
Excavation 5.20 7.30 3.65 0.76 105.45 1.00 1.00 1.00 1.00 105.45 m3 0% -
Pile Cut Off 6.00 1.00 1.00 6.00 6.00 nos 0% -
Plastic Sheet & Lean Concrete 5.50 5.50 0.05 1.51 1.00 1.00 1.00 1.00 1.51 m3 0% -
Lean Concrete Formwork 5.50 5.50 0.05 1.10 1.00 1.00 1.00 1.00 1.10 m2 0% -
Bottom Slab Rebar 6.05 6.05 1.58 62.00 1.00 1.00 62.00 592.00 kg 0% -
Bottom Slab Rebar 6.05 6.05 1.58 62.00 1.00 1.00 62.00 592.00 kg 0%
Wall Rebar (Horizontal) 4.07 27.56 1.04 41.00 1.00 1.00 41.00 1,177.29 kg 0% -
Wall Rebar (Vertical) + u bar 4.07 27.56 1.04 276.00 1.00 1.00 276.00 1,170.37 kg 0% -
Waterstop Installation 5.30 5.30 21.20 2.00 1.00 1.00 2.00 42.40 m1 0% -
Ground Slab Formwork 10.60 1.00 1.00 1.00 1.00 10.60 m2 0% -
Ground Slab Pouring Concrete 5.30 5.30 0.50 14.05 1.00 1.00 1.00 1.00 14.05 m3 0% -
HDPE Connection 2.00 1.00 1.00 2.00 2.00 nos 0% -
Wall Formwork 5.30 5.30 3.65 77.38 1.00 2.00 1.00 2.00 154.76 m2 0% -
Wall Pouring Concrete 5.30 5.30 0.30 3.65 23.21 1.00 1.00 1.00 1.00 23.21 m3 0% -
Upper Slab Formwork 5.30 1.00 1.00 1.00 1.00 5.30 m2 0% -
Upper Slab Rebar 6.05 6.05 1.04 62.00 1.00 1.00 62.00 390.81 kg 0% -
Upper Slab Rebar 6.05 6.05 1.04 62.00 1.00 1.00 62.00 390.81 kg 0%
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 5.30 5.30 0.25 7.02 1.00 1.00 1.00 1.00 7.02 m3 0% -
Bitumen Coating 5.30 5.30 3.65 77.38 1.00 1.00 1.00 1.00 77.38 m2 0% -
Soil Backfill 2.93 1.00 1.00 1.00 1.00 2.93 m3 0% -

RECAP FOR MAIN PROGRESS (BOQ ITEMS) Notes :


Progress Date 1. The Quantity Calculation is Still PT. SSA Version, It is Not Yet Together Measurement With KINE's Quantity Surveyor.
31/08/2023 2. Quantity Calculation Based On Approved Shop Drawing and Lotte Chemical E & C For Construction Drawing.
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE WORKS SECTION 2 AREA 002A Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Progress Progress
No. Description Unit Total Quantity Remarks
Quantity Percentages
1 Excavation m3 639.13 342.48 53.5853%
2 Pile Cut Off nos 30.00 13.00 43.3333%
3 Plastic Sheet & Lean Concrete m3 5.77 1.93 33.5067%
4 Lean Concrete Formwork m2 8.10 4.10 50.6173%
5 Rebar (D16) kg 17,279.83 3,624.83 20.9772%
Bottom Slab Rebar 4,157.79 1,023.96
Wall Rebar (Horizontal) 4,635.50 908.25
Wall Rebar (Vertical) + u bar 6,042.15 1,692.62
Upper Slab Rebar 2,444.39 -
6 Formwork m2 740.50 163.13 22.0304%
Ground Slab Formwork 73.80 30.20
Wall Formwork 591.55 132.93
Upper Slab Formwork 75.15 -
7 FC 24 Concrete m3 142.39 19.46 13.6635%
Ground Slab Pouring Concrete 49.94 10.33
Wall Pouring Concrete 69.41 9.13
Upper Slab Pouring Concrete 23.05 -
8 Step Iron Installation nos 45.00 15.00 33.3333%
9 Cast Iron Manhole Cover unit 18.00 - 0.0000%
10 Bitumen Coating m2 340.25 38.07 11.1895%
11 Epoxy Coating m2 102.73 - 0.0000%
12 Soil Backfill m3 364.51 - 0.0000% ARITMATH CHECKING
13 Waterstop Installation m 190.40 60.40 31.7227% New Items RECAP 20,035.60
14 HDPE Connection nos 33.00 12.00 36.3636% Method BREAKDOWN 20,035.60
15 Join Sealant m 96.00 - 0.0000% New Items IF ZERO = OK! -

GLOBAL PROGRESS FOR SEWAGE WORKS SECTION 2 AREA (AVERAGE PRORATE BY ITEMS) 23.3549%

31/08/2023
Checked by,
PT. Sepuluh Sumber Anugerah

Herdy Dwiyana
Quantity Surveyor
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEWAGE TANK 5.46 5.46 1.55 - 22.85 003 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A SEWAGE TANK SECTION 1
Excavation 12.70 12.70 5.55 0.67 596.77 1.00 1.00 1.00 1.00 596.77 m3 100% 596.77
Vertical H Beam for Soilslide
6.00 14.00 16.00 2.00 2.00 64.00 5,376.00 kg 100% 5,376.00
Protector (WF 150)
Horizontal H Beam for Soilslide
17.70 17.70 70.80 14.00 3.00 1.00 1.00 3.00 2,973.60 kg Cuma 3 sisi ? 100% 2,973.60
Protector (WF 150)
Thick Plywood for Soilslide Protector 17.70 17.70 4.80 70.80 84.96 1.00 1.00 4.00 339.84 m2 100% 339.84
Pile Cut Off 9.00 1.00 1.00 9.00 9.00 nos 100% 9.00
Plastic Sheet & Lean Concrete 5.50 5.50 0.05 1.51 1.00 1.00 1.00 1.00 1.51 m3 100% 1.51
Lean Concrete Formwork 5.50 5.50 0.05 1.10 1.00 1.00 1.00 1.00 1.10 m2 100% 1.10
D16 Bottom Slab Rebar 5.85 5.85 1.58 30.00 2.00 2.00 120.00 1,107.92 kg 100% 1,107.92
D13 Wall Rebar (Horizontal) 5.00 5.02 1.04 25.00 2.00 4.00 200.00 1,046.05 kg 100% 1,046.05
D13 Wall Rebar (Vertical) 5.65 18.40 1.04 92.00 2.00 1.00 184.00 1,082.19 kg 100% 1,082.19
Waterstop Installation 4.60 4.60 18.40 3.00 1.00 1.00 3.00 55.20 m1 Cuma 3 sisi ? 100% 55.20
Ground Slab Formwork 10.60 1.00 1.00 1.00 1.00 10.60 m2 100% 10.60
Ground Slab Pouring Concrete 5.30 5.30 0.50 14.05 1.00 1.00 1.00 1.00 14.05 m3 100% 14.05
HDPE Connection 1.00 1.00 1.00 1.00 1.00 nos 100% 1.00
Wall Formwork 4.60 4.60 5.00 92.00 1.00 2.00 1.00 2.00 184.00 m2 0% -
Step Iron Installation 6.00 1.00 1.00 6.00 6.00 unit 100% 6.00
Wall Pouring Concrete 4.60 4.60 0.30 5.00 27.60 1.00 1.00 1.00 1.00 27.60 m3 0% -
Upper Slab Formwork (2nd) 4.60 4.60 21.16 1.00 1.00 1.00 1.00 21.16 m2 100% 21.16
Upper Slab Rebar (2nd) 5.02 5.02 1.04 23.00 1.00 2.00 46.00 240.59 kg 100% 240.59
Stainless Steel Manhole 1.00 1.00 1.00 1.00 1.00 unit 50% 0.50
Upper Slab Pouring Concrete (2nd) 4.60 4.60 0.20 4.23 1.00 1.00 1.00 1.00 4.23 m3 100% 4.23
Upper Slab Formwork (3rd) 4.60 4.60 21.16 1.00 1.00 1.00 1.00 21.16 m2 100% 21.16
Upper Slab Rebar (3rd) 5.02 5.02 1.04 23.00 1.00 2.00 46.00 240.59 kg 100% 240.59
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 50% 0.50
Upper Slab Pouring Concrete (3rd) 4.60 4.60 0.20 4.23 1.00 1.00 1.00 1.00 4.23 m3 100% 4.23
Bitumen Coating 4.60 4.60 5.55 102.12 1.00 1.00 1.00 1.00 102.12 m2 100% 102.12
Epoxy Coating 4.00 4.00 4.60 73.60 1.00 1.00 1.00 1.00 73.60 m2 0% -
Soil Backfill 480.39 1.00 1.00 1.00 1.00 480.39 m3 90% 432.35

B SEWAGE TANK SECTION 3


Excavation 10.70 10.70 5.55 0.70 444.79 1.58 1.00 1.00 1.00 1.00 444.79 m3 0% -
Vertical H Beam for Soilslide
6.00 14.00 16.00 2.00 2.00 64.00 5,376.00 kg 0% -
Protector (WF 150)
Horizontal H Beam for Soilslide
17.70 17.70 70.80 14.00 3.00 1.00 1.00 3.00 2,973.60 kg 0% -
Protector (WF 150)
Thick Plywood for Soilslide Protector 17.70 17.70 4.80 70.80 84.96 1.00 1.00 4.00 283.20 m2 0% -
Pile Cut Off 9.00 1.00 1.00 9.00 9.00 nos 0% -
Plastic Sheet & Lean Concrete 3.50 3.50 0.05 0.61 1.00 1.00 1.00 1.00 0.61 m3 0% -
Lean Concrete Formwork 3.50 3.50 0.05 0.70 1.00 1.00 1.00 1.00 0.70 m2 0% -
Bottom Slab Rebar 3.85 3.85 1.58 20.00 2.00 2.00 80.00 486.10 kg 0% -
Wall Rebar (Horizontal) 2.60 4.93 1.04 13.00 2.00 2.00 52.00 266.83 kg 0% -
Wall Rebar (Vertical) 2.75 19.70 1.04 99.00 2.00 1.00 198.00 566.27 kg 0% -
Waterstop Installation 2.60 2.60 10.40 3.00 1.00 1.00 3.00 31.20 m1 0% -
Ground Slab Formwork 6.60 1.00 1.00 1.00 1.00 6.60 m2 0% -
Ground Slab Pouring Concrete 3.30 3.30 0.50 5.45 1.00 1.00 1.00 1.00 5.45 m3 0% -
HDPE Connection 1.00 1.00 1.00 1.00 1.00 nos 0% -
Wall Formwork 5.05 5.05 5.05 102.01 1.00 2.00 1.00 2.00 204.02 m2 0% -
Step Iron Installation 6.00 1.00 1.00 6.00 6.00 unit 0% -
Wall Pouring Concrete 5.05 5.05 0.28 5.55 30.83 1.00 1.00 1.00 1.00 30.83 m3 0% -
Upper Slab Formwork (2nd) 2.60 2.60 6.76 1.00 1.00 1.00 1.00 6.76 m2 0% -
Upper Slab Rebar (2nd) 2.60 2.60 1.04 13.00 1.00 2.00 26.00 70.43 kg 0% -
Stainless Steel Manhole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete (2nd) 2.60 2.60 0.20 1.35 2.00 1.00 1.00 2.00 2.70 m3 0% -
Upper Slab Formwork (3rd) 2.60 2.60 6.76 1.00 1.00 1.00 1.00 6.76 m2 0% -
Upper Slab Rebar (3rd) 2.60 2.60 1.04 13.00 1.00 2.00 26.00 70.43 kg 0% -
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete (3rd) 2.60 2.60 0.20 1.35 2.00 1.00 1.00 2.00 2.70 m3 0% -
Bitumen Coating 2.60 2.60 5.55 57.72 1.00 1.00 1.00 1.00 57.72 m2 0% -
Epoxy Coating 2.00 2.00 4.65 37.20 1.00 1.00 1.00 1.00 37.20 m2 0% -
Soil Backfill 384.90 1.00 1.00 1.00 1.00 384.90 m3 0% -

RECAP FOR MAIN PROGRESS (BOQ ITEMS) Notes :


Progress Date 1. The Quantity Calculation is Still PT. SSA Version, It is Not Yet Together Measurement With KINE's Quantity Surveyor.
31/08/2023 2. Quantity Calculation Based On Approved Shop Drawing and Lotte Chemical E & C For Construction Drawing.

Progress Progress
No. Description Unit Total Quantity Remarks
Quantity Percentages
1 Excavation m3 1,041.57 596.77 57.2957%
Vertical H Beam for Soilslide Protector
2 kg 10,752.00 5,376.00 50.0000% New Items
(WF 150)
Horizontal H Beam for Soilslide Protector
3 kg 5,947.20 2,973.60 50.0000% New Items
(WF 150)
4 Thick Plywood for Soilslide Protector m2 623.04 339.84 54.5455% New Items
5 Pile Cut Off nos 18.00 9.00 50.0000%
6 Plastic Sheet & Lean Concrete m3 2.13 1.51 71.1765%
7 Lean Concrete Formwork m2 1.80 1.10 61.1111%
8 Rebar (D16) kg 1,594.02 1,107.92 69.5050%
Bottom Slab Rebar 1,594.02 1,107.92
9 Rebar (D13) kg 3,583.39 2,609.42 72.8200%
Wall Rebar (Horizontal) 1,312.88 1,046.05
Wall Rebar (Vertical) 1,648.46 1,082.19
Upper Slab Rebar (2nd) 311.02 240.59
Upper Slab Rebar (3rd) 311.02 240.59
10 Formwork m2 461.06 52.92 11.4779%
Ground Slab Formwork 17.20 10.60
Wall Formwork 388.02 -
Upper Slab Formwork (2nd) 27.92 21.16
Upper Slab Formwork (3rd) 27.92 21.16
11 FC 24 Concrete m3 91.79 22.51 24.5217%
Ground Slab Pouring Concrete 19.49 14.05
Wall Pouring Concrete 58.43 -
Upper Slab Pouring Concrete (2nd) 6.94 4.23
Upper Slab Pouring Concrete (3rd) 6.94 4.23
12 Step Iron Installation unit 12.00 6.00 50.0000%
13 Stainless Steel Manhole unit 2.00 0.50 25.0000% New Items
14 Cast Iron Manhole Cover unit 2.00 0.50 25.0000%
15 Bitumen Coating m2 159.84 102.12 63.8889%
16 Epoxy Coating m2 110.80 - 0.0000% ARITMATH CHECKING
17 Waterstop Installation m1 86.40 55.20 63.8889% New Items RECAP 28,939.71
18 HDPE Connection nos 2.00 1.00 50.0000% Method BREAKDOWN 25,356.32
19 Soil Backfill m3 865.29 432.35 49.9662% NOT OK!! 3,583.39

GLOBAL PROGRESS FOR SEWAGE TANK (AVERAGE PRORATE BY ITEMS) 47.3788%

31/08/2023
Checked by,
PT. Sepuluh Sumber Anugerah
Herdy Dwiyana
Quantity Surveyor
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEPTIC TANK 004 Calculation 31/08/2023
WP 6 - Civil & Landscape 5.48 5.48 1.57
PT. Sepuluh Sumber Anugerah 13.56 9.86 3.55

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
SEPTIC TANK DETAIL 1 (Main
A
Building) ST-01
Excavation 17.82 14.12 3.55 0.76 679.85 1.00 1.00 1.00 1.00 679.85 m3 100% 679.85
Pile Cut Off 6.00 1.00 1.00 6.00 6.00 nos 100% 6.00
Plastic Sheet & Lean Concrete 7.50 3.80 0.05 1.43 1.00 1.00 1.00 1.00 1.43 m3 100% 1.43
Lean Concrete Formwork 7.50 3.80 0.05 1.13 1.00 1.00 1.00 1.00 1.13 m2 100% 1.13
Bottom Slab Rebar (x) 8.05 4.35 1.58 45.00 1.00 1.00 45.00 571.72 kg 100% 571.72
Bottom Slab Rebar (y) 8.05 4.35 1.58 82.00 1.00 1.00 82.00 562.96 kg 100%
Wall Rebar (Horizontal) 3.97 28.16 1.04 40.00 1.00 1.00 40.00 1,173.58 kg 100% 1,173.58
Wall Rebar (Vertical) + u bar 3.97 28.16 1.04 282.00 1.00 1.00 282.00 1,166.43 kg 100% 1,166.43
Waterstop Installation 7.30 3.60 21.80 2.00 1.00 1.00 2.00 43.60 m1 100% 43.60
Ground Slab Formwork 10.90 1.00 1.00 1.00 1.00 10.90 m2 100% 10.90
Ground Slab Pouring Concrete 7.30 3.60 0.50 13.14 1.00 1.00 1.00 1.00 13.14 m3 100% 13.14
Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 7.30 3.60 3.55 77.39 1.00 2.00 1.00 2.00 154.78 m2 100% 154.78
Wall Pouring Concrete 7.30 3.60 0.30 3.55 23.22 1.00 1.00 1.00 1.00 23.22 m3 100% 23.22
Upper Slab Formwork 5.45 1.00 1.00 1.00 1.00 5.45 m2 0% -
Upper Slab Rebar (x) 8.05 4.35 1.04 45.00 1.00 1.00 45.00 377.42 kg 0% -
Upper Slab Rebar (y) 8.05 4.35 1.04 82.00 1.00 1.00 82.00 371.64 kg 0%
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 7.30 3.60 0.25 6.57 1.00 1.00 1.00 1.00 6.57 m3 0% -
Bitumen Coating 7.30 3.60 3.55 103.66 1.00 1.00 1.00 1.00 103.66 m2 100% 103.66
Soil Backfill 586.56 1.00 1.00 1.00 1.00 586.56 m3 100% 586.56

SEPTIC TANK DETAIL 2 (Canteen


B 11.90 46.80 0.75
Area 1) ST-03
Excavation 14.86 12.76 3.15 445.35 1.00 1.00 1.00 1.00 445.35 m3 100% 445.35
Pile Cut Off 3.00 1.00 1.00 3.00 3.00 nos 100% 3.00
Plastic Sheet & Lean Concrete 5.50 3.40 0.05 0.94 1.00 1.00 1.00 1.00 0.94 m3 100% 0.94
Lean Concrete Formwork 5.50 3.40 0.05 0.89 1.00 1.00 1.00 1.00 0.89 m2 100% 0.89
Bottom Slab Rebar (x) 5.57 3.47 1.58 36.00 1.00 1.00 36.00 316.47 kg 100% 316.47
Bottom Slab Rebar (y) 5.57 3.47 1.58 57.00 1.00 1.00 57.00 312.16 kg 100% 312.16
D13 Wall Rebar (Horizontal) 3.28 18.38 1.04 17.00 2.00 1.00 34.00 651.09 kg 100% 651.09
D13 Wall Rebar (Vertical) + u bar 3.28 18.38 1.04 170.00 1.00 1.00 170.00 580.07 kg 100% 580.07
Waterstop Installation 5.30 3.20 17.00 2.00 1.00 1.00 2.00 34.00 m1 100% 34.00
Ground Slab Formwork 8.50 1.00 1.00 1.00 1.00 8.50 m2 100% 8.50
Ground Slab Pouring Concrete 5.30 3.20 0.50 8.48 1.00 1.00 1.00 1.00 8.48 m3 100% 8.48
Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 5.30 3.20 3.35 56.95 1.00 2.00 1.00 2.00 113.90 m2 100% 113.90
Wall Pouring Concrete 5.30 3.20 0.30 3.00 15.30 1.00 1.00 1.00 1.00 15.30 m3 100% 15.30
Upper Slab Formwork 5.30 3.20 4.25 1.00 1.00 1.00 1.00 21.21 m2 0% -
Upper Slab Rebar (x) 5.57 3.47 1.04 32.00 1.00 1.00 32.00 185.71 kg 0% -
Upper Slab Rebar (y) 5.57 3.47 1.04 54.00 1.00 1.00 54.00 195.23 kg 0%
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 5.30 3.20 0.25 4.24 1.00 1.00 1.00 1.00 4.24 m3 0% -
Bitumen Coating 5.30 3.20 3.35 56.95 1.00 1.00 1.00 1.00 56.95 m2 100% 56.95
Soil Backfill 391.93 1.00 1.00 1.00 1.00 391.93 m3 100% 391.93
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEPTIC TANK 004 Calculation 31/08/2023
WP 6 - Civil & Landscape 5.48 5.48 1.57
PT. Sepuluh Sumber Anugerah 13.56 9.86 3.55

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
SEPTIC TANK DETAIL 3 (Masjid
C 6.00 26.10 0.77
Area) ST-04
Excavation 11.60 9.60 2.25 0.77 192.96 1.00 1.00 1.00 1.00 192.96 m3 100% 192.96
Pile Cut Off 3.00 1.00 1.00 3.00 3.00 nos 100% 3.00
Plastic Sheet & Lean Concrete 4.40 2.40 0.05 0.53 1.00 1.00 1.00 1.00 0.53 m3 100% 0.53
Lean Concrete Formwork 4.40 2.40 0.05 0.68 1.00 1.00 1.00 1.00 0.68 m2 100% 0.68
Bottom Slab Rebar (x) 4.95 2.95 1.58 31.00 1.00 1.00 31.00 242.18 kg 100% 242.18
Bottom Slab Rebar (y) 4.95 2.95 1.58 51.00 1.00 1.00 51.00 237.45 kg 100%
Wall Rebar (Horizontal) 2.67 19.16 1.04 27.00 1.00 1.00 27.00 538.99 kg 100% 538.99
Wall Rebar (Vertical) + u bar 2.67 19.16 1.04 192.00 1.00 1.00 192.00 534.11 kg 100% 534.11
Waterstop Installation 4.20 2.20 12.80 2.00 1.00 1.00 2.00 25.60 m1 100% 25.60
Ground Slab Formwork 6.40 1.00 1.00 1.00 1.00 6.40 m2 100% 6.40
Ground Slab Pouring Concrete 4.20 2.20 0.50 4.62 1.00 1.00 1.00 1.00 4.62 m3 100% 4.62
Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 4.20 2.20 2.25 28.80 1.00 2.00 1.00 2.00 57.60 m2 100% 57.60
Wall Pouring Concrete 4.20 2.20 0.30 2.25 8.64 1.00 1.00 1.00 1.00 8.64 m3 100% 8.64
Upper Slab Formwork 3.20 1.00 1.00 1.00 1.00 3.20 m2 0% -
Upper Slab Rebar (x) 4.95 2.95 1.04 31.00 1.00 1.00 31.00 159.88 kg 0% -
Upper Slab Rebar (y) 4.95 2.95 1.04 51.00 1.00 1.00 51.00 156.75 kg 0%
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 4.20 2.20 0.25 2.31 1.00 1.00 1.00 1.00 2.31 m3 0% -
Bitumen Coating 4.20 2.20 2.25 37.80 1.00 1.00 1.00 1.00 37.80 m2 100% 37.80
Soil Backfill 172.17 1.00 1.00 1.00 1.00 172.17 m3 100% 172.17

SEPTIC TANK DETAIL 4 (Masjid


D 5.00 20.34 0.75
Area) ST-05
Excavation 9.92 8.92 2.25 - 149.72 1.00 1.00 1.00 1.00 149.72 m3 100% 149.72
Pile Cut Off 3.00 1.00 1.00 3.00 3.00 nos 100% 3.00
Plastic Sheet & Lean Concrete 3.20 2.20 0.05 0.35 1.00 1.00 1.00 1.00 0.35 m3 100% 0.35
Lean Concrete Formwork 3.20 2.20 0.05 0.54 1.00 1.00 1.00 1.00 0.54 m2 100% 0.54
Bottom Slab Rebar (x) 3.42 2.42 1.58 20.00 1.00 1.00 20.00 107.95 kg 100% 107.95
Bottom Slab Rebar (y) 3.42 2.42 1.58 30.00 1.00 1.00 30.00 114.58 kg 100%
Wall Rebar (Horizontal) 2.42 11.68 1.04 11.00 2.00 1.00 22.00 267.72 kg 0% -
Wall Rebar (Vertical) + u bar 2.03 11.68 1.04 50.00 2.00 1.00 100.00 210.98 kg 0% -
Waterstop Installation 3.00 2.00 10.00 2.00 1.00 1.00 2.00 20.00 m1 100% 20.00
Ground Slab Formwork 5.00 1.00 1.00 1.00 1.00 5.00 m2 100% 5.00
Ground Slab Pouring Concrete 3.00 2.00 0.50 3.00 1.00 1.00 1.00 1.00 3.00 m3 100% 3.00
Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 3.00 2.00 2.25 22.50 1.00 2.00 1.00 2.00 45.00 m2 100% 45.00
Wall Pouring Concrete 3.00 2.00 0.30 1.83 5.48 1.00 1.00 1.00 1.00 5.48 m3 100% 5.48
Upper Slab Formwork 3.00 2.00 2.50 1.00 1.00 1.00 1.00 8.50 m2 0% -
Upper Slab Rebar (x) 3.42 2.42 1.04 10.00 2.00 1.00 20.00 71.26 kg 0% -
Upper Slab Rebar (y) 3.42 2.42 1.04 15.00 2.00 1.00 30.00 75.64 kg 0%
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 3.00 2.00 0.25 1.50 1.00 1.00 1.00 1.00 1.50 m3 0% -
Bitumen Coating 3.00 2.00 1.83 18.25 1.00 1.00 1.00 1.00 18.25 m2 100% 18.25
Soil Backfill 136.22 1.00 1.00 1.00 1.00 136.22 m3 100% 136.22
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEPTIC TANK 004 Calculation 31/08/2023
WP 6 - Civil & Landscape 5.48 5.48 1.57
PT. Sepuluh Sumber Anugerah 13.56 9.86 3.55

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
SEPTIC TANK DETAIL 5 (Main Gate
E 6.06 23.62 0.74
Building) ST-06
Excavation 10.50 9.60 2.25 - 168.48 1.00 1.00 1.00 1.00 168.48 m3 100% 168.48
Pile Cut Off 3.00 1.00 1.00 3.00 3.00 nos 100% 3.00
Plastic Sheet & Lean Concrete 3.30 2.40 0.05 0.40 1.00 1.00 1.00 1.00 0.40 m3 100% 0.40
Lean Concrete Formwork 3.30 2.40 0.05 0.57 1.00 1.00 1.00 1.00 0.57 m2 100% 0.57
Bottom Slab Rebar (x) 3.52 2.62 1.58 11.00 2.00 1.00 22.00 122.22 kg 100% 122.22
Bottom Slab Rebar (y) 3.52 2.62 1.58 16.00 2.00 1.00 32.00 132.32 kg 100% 132.32
Wall Rebar (Horizontal) 2.65 12.28 1.04 12.00 2.00 1.00 24.00 307.06 kg 100% 307.06
Wall Rebar (Vertical) + u bar 2.65 12.28 1.04 53.00 2.00 1.00 106.00 292.11 kg 100% 292.11
Waterstop Installation 3.10 2.20 10.60 2.00 1.00 1.00 2.00 21.20 m1 100% 21.20
Ground Slab Formwork 3.10 2.20 5.30 1.00 1.00 1.00 1.00 12.12 m2 100% 12.12
Ground Slab Pouring Concrete 3.10 2.20 0.50 3.41 1.00 1.00 1.00 1.00 3.41 m3 100% 3.41
Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 3.10 2.20 1.95 20.67 1.00 2.00 1.00 2.00 41.34 m2 100% 41.34
Wall Pouring Concrete 3.10 2.20 0.30 1.95 6.20 1.00 1.00 1.00 1.00 6.20 m3 100% 6.20
Upper Slab Formwork 3.10 2.20 2.65 1.00 1.00 1.00 1.00 9.47 m2 0% -
Upper Slab Rebar (x) 3.52 2.62 1.04 11.00 2.00 1.00 22.00 80.68 kg 0% -
Upper Slab Rebar (y) 3.52 2.62 1.04 16.00 2.00 1.00 32.00 87.35 kg 0%
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 3.10 2.20 0.25 1.71 1.00 1.00 1.00 1.00 1.71 m3 0% -
Bitumen Coating 3.10 2.20 2.45 25.97 1.00 1.00 1.00 1.00 25.97 m2 100% 25.97
Soil Backfill 2.45 151.77 1.00 1.00 1.00 1.00 151.77 m3 100% 151.77

SEPTIC TANK DETAIL 5 (Main Gate


F
Building) ST-07
Excavation 10.50 9.60 2.25 168.48 1.00 1.00 1.00 1.00 168.48 m3 100% 168.48
Pile Cut Off 3.00 1.00 1.00 3.00 3.00 nos 100% 3.00
Plastic Sheet & Lean Concrete 3.30 2.40 0.05 0.40 1.00 1.00 1.00 1.00 0.40 m3 100% 0.40
Lean Concrete Formwork 3.30 2.40 0.05 0.57 1.00 1.00 1.00 1.00 0.57 m2 100% 0.57
Bottom Slab Rebar (x) 3.52 2.62 1.58 11.00 2.00 1.00 22.00 122.22 kg 100% 122.22
Bottom Slab Rebar (y) 3.52 2.62 1.58 16.00 2.00 1.00 32.00 132.32 kg 100%
Wall Rebar (Horizontal) 2.65 12.28 1.04 12.00 2.00 1.00 24.00 307.06 kg 100% 307.06
Wall Rebar (Vertical) + u bar 2.65 12.28 1.04 53.00 2.00 1.00 106.00 292.11 kg 100% 292.11
Waterstop Installation 3.10 2.20 10.60 2.00 1.00 1.00 2.00 21.20 m1 100% 21.20
Ground Slab Formwork 3.10 2.20 5.30 1.00 1.00 1.00 1.00 5.30 m2 100% 5.30
Ground Slab Pouring Concrete 3.10 2.20 0.50 3.41 1.00 1.00 1.00 1.00 3.41 m3 100% 3.41
Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 3.10 2.20 1.95 20.67 1.00 2.00 1.00 2.00 41.34 m2 100% 41.34
Wall Pouring Concrete 3.10 2.20 0.30 1.95 6.20 1.00 1.00 1.00 1.00 6.20 m3 100% 6.20
Upper Slab Formwork 3.10 2.20 2.65 1.00 1.00 1.00 1.00 2.65 m2 0% -
Upper Slab Rebar (x) 3.52 2.62 1.04 11.00 2.00 1.00 22.00 80.68 kg 0% -
Upper Slab Rebar (y) 3.52 2.62 1.04 16.00 2.00 1.00 32.00 87.35 kg 0%
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 3.10 2.20 0.25 1.71 1.00 1.00 1.00 1.00 1.71 m3 0% -
Bitumen Coating 3.10 2.20 2.45 25.97 1.00 1.00 1.00 1.00 25.97 m2 100% 25.97
Soil Backfill 2.45 151.77 1.00 1.00 1.00 1.00 151.77 m3 100% 151.77
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEPTIC TANK 004 Calculation 31/08/2023
WP 6 - Civil & Landscape 5.48 5.48 1.57
PT. Sepuluh Sumber Anugerah 13.56 9.86 3.55

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
SEPTIC TANK DETAIL 2 (Canteen
G
Area) ST-02
Excavation 14.86 12.76 3.15 445.35 1.00 1.00 1.00 1.00 445.35 m3 100% 445.35
Pile Cut Off 3.00 1.00 1.00 3.00 3.00 nos 100% 3.00
Plastic Sheet & Lean Concrete 5.50 3.40 0.05 0.94 1.00 1.00 1.00 1.00 0.94 m3 100% 0.94
Lean Concrete Formwork 5.50 3.40 0.05 0.89 1.00 1.00 1.00 1.00 0.89 m2 100% 0.89
Bottom Slab Rebar (x) 5.57 3.47 1.58 36.00 1.00 1.00 36.00 316.47 kg 100% 316.47
Bottom Slab Rebar (y) 5.57 3.47 1.58 57.00 1.00 1.00 57.00 312.16 kg 100% 312.16
Wall Rebar (Horizontal) 3.28 18.38 1.04 17.00 2.00 1.00 34.00 651.09 kg 100% 651.09
Wall Rebar (Vertical) + u bar 3.28 18.38 1.04 170.00 1.00 1.00 170.00 580.07 kg 100% 580.07
Waterstop Installation 5.30 3.20 17.00 2.00 1.00 1.00 2.00 34.00 m1 100% 34.00
Ground Slab Formwork 8.50 1.00 1.00 1.00 1.00 8.50 m2 100% 8.50
Ground Slab Pouring Concrete 5.30 3.20 0.50 8.48 1.00 1.00 1.00 1.00 8.48 m3 100% 8.48
Pipe Connection 2.00 1.00 1.00 2.00 2.00 nos 100% 2.00
Wall Formwork 5.30 3.20 3.35 56.95 1.00 2.00 1.00 2.00 113.90 m2 100% 113.90
Wall Pouring Concrete 5.30 3.20 0.30 3.00 15.30 1.00 1.00 1.00 1.00 15.30 m3 100% 15.30
Upper Slab Formwork 5.30 3.20 4.25 1.00 1.00 1.00 1.00 21.21 m2 0% -
Upper Slab Rebar (x) 5.57 3.47 1.04 32.00 1.00 1.00 32.00 185.71 kg 0% -
Upper Slab Rebar (y) 5.57 3.47 1.04 54.00 1.00 1.00 54.00 195.23 kg 0%
Cast Iron Manhole Cover 1.00 1.00 1.00 1.00 1.00 unit 0% -
Upper Slab Pouring Concrete 5.30 3.20 0.25 4.24 1.00 1.00 1.00 1.00 4.24 m3 0% -
Bitumen Coating 5.30 3.20 3.35 56.95 1.00 1.00 1.00 1.00 56.95 m2 100% 56.95
Soil Backfill 391.93 1.00 1.00 1.00 1.00 391.93 m3 100% 391.93

RECAP FOR MAIN PROGRESS (BOQ ITEMS) Notes :


Progress Date 1. The Quantity Calculation is Still PT. SSA Version, It is Not Yet Together Measurement With KINE's Quantity Surveyor.
31/08/2023 2. Quantity Calculation Based On Approved Shop Drawing and Lotte Chemical E & C For Construction Drawing.
Progress Progress
No. Description Unit Total Quantity Remarks
Quantity Percentages
1 Excavation m3 2,250.19 2,250.19 100.0000%
2 Pile Cut Off nos 24.00 24.00 100.0000%
3 Plastic Sheet & Lean Concrete m3 4.97 4.97 100.0000%
4 Lean Concrete Formwork m2 5.27 5.27 100.0000%
5 Rebar (D16) kg 3,603.17 2,555.86 70.9338%
Bottom Slab Rebar (x) 1,799.23 1,799.23
Bottom Slab Rebar (y) 1,803.94 756.64
6 Rebar (D13) kg 9,863.04 7,073.79 71.7203%
Wall Rebar (Horizontal) 3,896.61 3,628.89
Wall Rebar (Vertical) + u bar 3,655.89 3,444.91
Upper Slab Rebar (x) 1,141.34 -
Upper Slab Rebar (y) 1,169.19 -
7 Formwork m2 696.27 624.58 89.7037%
Ground Slab Formwork 56.72 56.72
Wall Formwork 567.86 567.86
Upper Slab Formwork 71.69 -
8 FC 24 Concrete m3 147.14 124.87 84.8652%
Ground Slab Pouring Concrete 44.54 44.54
Wall Pouring Concrete 80.33 80.33
Upper Slab Pouring Concrete 22.27 -
9 Waterstop Installation m1 199.60 199.60 100.0000% New Items
10 Pipe Connection nos 14.00 14.00 100.0000% Method ARITMATH CHECKING
11 Cast Iron Manhole Cover unit 7.00 - 0.0000% RECAP 28,985.58
12 Bitumen Coating m2 325.55 325.55 100.0000% BREAKDOWN 19,122.54
13 Soil Backfill m3 1,982.34 1,982.34 100.0000% NOT OK!! 9,863.04

GLOBAL PROGRESS FOR SEPTIC TANK (AVERAGE PRORATE BY ITEMS) 85.9402%

31/08/2023
Checked by,
PT. Sepuluh Sumber Anugerah
Progress Calculation PROGRESS CALCULATION FORM Progress Date
SEPTIC TANK 004 Calculation 31/08/2023
WP 6 - Civil & Landscape 5.48 5.48 1.57
PT. Sepuluh Sumber Anugerah 13.56 9.86 3.55

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14

Herdy Dwiyana
Quantity Surveyor
Progress Calculation PROGRESS CALCULATION FORM Progress Date
Hume RC Pipe Installation 005 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
HUME RC PIPE 500 mm (CCO From
A
450 mm to 500 mm)
A. 1 MH.01 - MH.02 31.80
Excavation 3.82 1.00 1.30 0.70 31.80 110.54 1.00 1.00 1.00 1.00 110.54 m3 100% 110.54
Lean Concrete 0.70 1.00 0.05 31.80 1.11 1.00 1.00 1.00 1.00 1.11 m3 100% 1.11
Lean Concrete Formwork 0.70 1.00 0.05 31.80 2.23 1.00 1.00 1.00 1.00 2.23 m2 100% 2.23
Sand Fill 3.82 1.00 0.30 31.80 36.44 1.00 1.00 1.00 1.00 36.44 m3 100% 36.44
Hume Pipe 500 mm 31.80 1.00 1.00 1.00 1.00 31.80 m 100% 31.80
Hume Pipe Mortar Grouting 31.80 1.00 1.00 1.00 1.00 31.80 m 100% 31.80
Soil Backfill 104.30 1.00 1.00 1.00 1.00 104.30 m3 100% 104.30

A. 2 MH.02 - MH.03 29.80


Excavation 3.82 1.00 1.30 0.70 29.80 103.59 1.00 1.00 1.00 1.00 103.59 m3 100% 103.59
Lean Concrete 0.70 1.00 0.05 29.80 1.04 1.00 1.00 1.00 1.00 1.04 m3 100% 1.04
Lean Concrete Formwork 0.70 1.00 0.05 29.80 2.09 1.00 1.00 1.00 1.00 2.09 m2 100% 2.09
Sand Fill 3.82 1.00 0.30 29.80 34.15 1.00 1.00 1.00 1.00 34.15 m3 0% -
Hume Pipe 500 mm 29.80 1.00 1.00 1.00 1.00 29.80 m 100% 29.80
Hume Pipe Mortar Grouting 29.80 1.00 1.00 1.00 1.00 29.80 m 100% 29.80
Soil Backfill 97.74 1.00 1.00 1.00 1.00 97.74 m3 0% -

A. 3 MH.03 - MH.04 46.60


Excavation 3.82 1.00 1.30 0.70 46.60 161.99 1.00 1.00 1.00 1.00 161.99 m3 100% 161.99
Lean Concrete 0.70 1.00 0.05 46.60 1.63 1.00 1.00 1.00 1.00 1.63 m3 100% 1.63
Lean Concrete Formwork 0.70 1.00 0.05 46.60 3.26 1.00 1.00 1.00 1.00 3.26 m2 100% 3.26
Sand Fill 3.82 1.00 0.30 46.60 53.40 1.00 1.00 1.00 1.00 53.40 m3 100% 53.40
Hume Pipe 500 mm 46.60 1.00 1.00 1.00 1.00 46.60 m 100% 46.60
Hume Pipe Mortar Grouting 46.60 1.00 1.00 1.00 1.00 46.60 m 100% 46.60
Soil Backfill 152.85 1.00 1.00 1.00 1.00 152.85 m3 100% 152.85

A. 4 MH.04 - MH.05 46.00


Excavation 3.82 1.00 1.30 0.70 46.00 159.91 1.00 1.00 1.00 1.00 159.91 m3 100% 159.91
Lean Concrete 0.70 1.00 0.05 46.00 1.61 1.00 1.00 1.00 1.00 1.61 m3 100% 1.61
Lean Concrete Formwork 0.70 1.00 0.05 46.00 3.22 1.00 1.00 1.00 1.00 3.22 m2 100% 3.22
Sand Fill 3.82 1.00 0.30 46.00 52.72 1.00 1.00 1.00 1.00 52.72 m3 100% 52.72
Hume Pipe 500 mm 46.00 1.00 1.00 1.00 1.00 46.00 m 100% 46.00
Hume Pipe Mortar Grouting 46.00 1.00 1.00 1.00 1.00 46.00 m 100% 46.00
Soil Backfill 150.88 1.00 1.00 1.00 1.00 150.88 m3 100% 150.88

A. 5 MH.09 - MH.10 42.40


Excavation 3.82 1.00 1.30 0.70 42.40 147.39 1.00 1.00 1.00 1.00 147.39 m3 100% 147.39
Lean Concrete 0.70 1.00 0.05 42.40 1.48 1.00 1.00 1.00 1.00 1.48 m3 100% 1.48
Lean Concrete Formwork 0.70 1.00 0.05 42.40 2.97 1.00 1.00 1.00 1.00 2.97 m2 100% 2.97
Sand Fill 3.82 1.00 0.30 42.40 48.59 1.00 1.00 1.00 1.00 48.59 m3 100% 48.59
Hume Pipe 500 mm 42.40 1.00 1.00 1.00 1.00 42.40 m 100% 42.40
Hume Pipe Mortar Grouting 42.40 1.00 1.00 1.00 1.00 42.40 m 100% 42.40
Soil Backfill 139.07 1.00 1.00 1.00 1.00 139.07 m3 100% 139.07

A. 6 MH.10 - MH.06 38.30


Excavation 3.82 1.00 1.27 0.70 38.30 129.55 1.00 1.00 1.00 1.00 129.55 m3 100% 129.55
Progress Calculation PROGRESS CALCULATION FORM Progress Date
Hume RC Pipe Installation 005 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Lean Concrete 0.70 1.00 0.05 38.30 1.34 1.00 1.00 1.00 1.00 1.34 m3 100% 1.34
Lean Concrete Formwork 0.70 1.00 0.05 38.30 2.68 1.00 1.00 1.00 1.00 2.68 m2 100% 2.68
Sand Fill 3.82 1.00 0.30 38.30 43.89 1.00 1.00 1.00 1.00 43.89 m3 100% 43.89
Hume Pipe 500 mm 38.30 1.00 1.00 1.00 1.00 38.30 m 100% 38.30
Hume Pipe Mortar Grouting 38.30 1.00 1.00 1.00 1.00 38.30 m 100% 38.30
Soil Backfill 122.04 1.00 1.00 1.00 1.00 122.04 m3 100% 122.04
Progress Calculation PROGRESS CALCULATION FORM Progress Date
Hume RC Pipe Installation 005 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 7 MH.11 - MH.12 13.90
Excavation 3.82 1.00 1.03 1.00 13.90 54.69 1.00 1.00 1.00 1.00 54.69 m3 100% 54.69
Lean Concrete 0.70 1.00 0.05 13.90 0.49 1.00 1.00 1.00 1.00 0.49 m3 100% 0.49
Lean Concrete Formwork 0.70 1.00 0.05 13.90 1.39 1.00 1.00 1.00 1.00 1.39 m2 100% 1.39
Sand Fill 3.82 1.00 0.30 13.90 15.93 1.00 1.00 1.00 1.00 15.93 m3 100% 15.93
Hume Pipe 500 mm 13.90 1.00 1.00 1.00 1.00 13.90 m 100% 13.90
Hume Pipe Mortar Grouting 13.90 1.00 1.00 1.00 1.00 13.90 m 100% 13.90
Soil Backfill 51.96 1.00 1.00 1.00 1.00 51.96 m3 100% 51.96

A. 8 MH.12 - MH.13 25.30


Excavation 3.82 1.00 1.03 1.00 25.30 99.55 1.00 1.00 1.00 1.00 99.55 m3 100% 99.55
Lean Concrete 0.70 1.00 0.05 25.30 0.89 1.00 1.00 1.00 1.00 0.89 m3 100% 0.89
Lean Concrete Formwork 0.70 1.00 0.05 25.30 1.77 1.00 1.00 1.00 1.00 1.77 m2 100% 1.77
Sand Fill 3.82 1.00 0.30 25.30 28.99 1.00 1.00 1.00 1.00 28.99 m3 100% 28.99
Hume Pipe 500 mm 25.30 1.00 1.00 1.00 1.00 25.30 m 100% 25.30
Hume Pipe Mortar Grouting 25.30 1.00 1.00 1.00 1.00 25.30 m 100% 25.30
Soil Backfill 94.58 1.00 1.00 1.00 1.00 94.58 m3 100% 94.58

A. 9 MH.13 - MH.14 36.00


Excavation 3.82 1.00 1.03 1.00 36.00 141.65 1.00 1.00 1.00 1.00 141.65 m3 100% 141.65
Lean Concrete 0.70 1.00 0.05 36.00 1.26 1.00 1.00 1.00 1.00 1.26 m3 100% 1.26
Lean Concrete Formwork 0.70 1.00 0.05 36.00 2.52 1.00 1.00 1.00 1.00 2.52 m2 100% 2.52
Sand Fill 3.82 1.00 0.30 36.00 41.26 1.00 1.00 1.00 1.00 41.26 m3 100% 41.26
Hume Pipe 500 mm 36.00 1.00 1.00 1.00 1.00 36.00 m 100% 36.00
Hume Pipe Mortar Grouting 36.00 1.00 1.00 1.00 1.00 36.00 m 100% 36.00
Soil Backfill 134.58 1.00 1.00 1.00 1.00 134.58 m3 100% 134.58

A. 10 MH.20 - MH.14 25.30


Excavation 3.82 1.00 1.03 1.00 25.30 99.55 1.00 1.00 1.00 1.00 99.55 m3 100% 99.55
Lean Concrete 0.70 1.00 0.05 25.30 0.89 1.00 1.00 1.00 1.00 0.89 m3 100% 0.89
Lean Concrete Formwork 0.70 1.00 0.05 25.30 1.77 1.00 1.00 1.00 1.00 1.77 m2 100% 1.77
Sand Fill 3.82 1.00 0.30 25.30 28.99 1.00 1.00 1.00 1.00 28.99 m3 100% 28.99
Hume Pipe 500 mm 25.30 1.00 1.00 1.00 1.00 25.30 m 100% 25.30
Hume Pipe Mortar Grouting 25.30 1.00 1.00 1.00 1.00 25.30 m 100% 25.30
Soil Backfill 94.58 1.00 1.00 1.00 1.00 94.58 m3 100% 94.58

A. 11 MH.14 - MH.15 15.90


Excavation 3.82 1.00 1.03 1.00 15.90 62.56 1.00 1.00 1.00 1.00 62.56 m3 100% 62.56
Lean Concrete 0.70 1.00 0.05 15.90 0.56 1.00 1.00 1.00 1.00 0.56 m3 100% 0.56
Lean Concrete Formwork 0.70 1.00 0.05 15.90 1.11 1.00 1.00 1.00 1.00 1.11 m2 100% 1.11
Sand Fill 3.82 1.00 0.30 15.90 18.22 1.00 1.00 1.00 1.00 18.22 m3 100% 18.22
Hume Pipe 500 mm 15.90 1.00 1.00 1.00 1.00 15.90 m 100% 15.90
Hume Pipe Mortar Grouting 15.90 1.00 1.00 1.00 1.00 15.90 m 100% 15.90
Soil Backfill 59.44 1.00 1.00 1.00 1.00 59.44 m3 100% 59.44

A. 12 MH.15 - MH.16 31.00


Excavation 3.82 1.00 1.03 1.00 31.00 121.97 1.00 1.00 1.00 1.00 121.97 m3 100% 121.97
Lean Concrete 0.70 1.00 0.05 31.00 1.09 1.00 1.00 1.00 1.00 1.09 m3 100% 1.09
Progress Calculation PROGRESS CALCULATION FORM Progress Date
Hume RC Pipe Installation 005 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Lean Concrete Formwork 0.70 1.00 0.05 31.00 2.17 1.00 1.00 1.00 1.00 2.17 m2 100% 2.17
Sand Fill 3.82 1.00 0.30 31.00 35.53 1.00 1.00 1.00 1.00 35.53 m3 100% 35.53
Hume Pipe 500 mm 31.00 1.00 1.00 1.00 1.00 31.00 m 100% 31.00
Hume Pipe Mortar Grouting 31.00 1.00 1.00 1.00 1.00 31.00 m 100% 31.00
Soil Backfill 115.89 1.00 1.00 1.00 1.00 115.89 m3 100% 115.89
Progress Calculation PROGRESS CALCULATION FORM Progress Date
Hume RC Pipe Installation 005 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 13 MH.22 - MH.23 32.00
Excavation 3.82 1.00 1.03 1.00 32.00 125.91 1.00 1.00 1.00 1.00 125.91 m3 100% 125.91
Lean Concrete 0.70 1.00 0.05 32.00 1.12 1.00 1.00 1.00 1.00 1.12 m3 100% 1.12
Lean Concrete Formwork 0.70 1.00 0.05 32.00 2.24 1.00 1.00 1.00 1.00 2.24 m2 100% 2.24
Sand Fill 3.82 1.00 0.30 32.00 36.67 1.00 1.00 1.00 1.00 36.67 m3 100% 36.67
Hume Pipe 500 mm 32.00 1.00 1.00 1.00 1.00 32.00 m 100% 32.00
Hume Pipe Mortar Grouting 32.00 1.00 1.00 1.00 1.00 32.00 m 100% 32.00
Soil Backfill 119.63 1.00 1.00 1.00 1.00 119.63 m3 100% 119.63

A. 14 MH.23 - MH.24 36.00


Excavation 3.82 1.00 1.10 1.00 36.00 150.58 1.00 1.00 1.00 1.00 150.58 m3 100% 150.58
Lean Concrete 0.70 1.00 0.05 36.00 1.26 1.00 1.00 1.00 1.00 1.26 m3 100% 1.26
Lean Concrete Formwork 0.70 1.00 0.05 36.00 2.52 1.00 1.00 1.00 1.00 2.52 m2 100% 2.52
Sand Fill 3.82 1.00 0.30 36.00 41.26 1.00 1.00 1.00 1.00 41.26 m3 100% 41.26
Hume Pipe 500 mm 36.00 1.00 1.00 1.00 1.00 36.00 m 100% 36.00
Hume Pipe Mortar Grouting 36.00 1.00 1.00 1.00 1.00 36.00 m 100% 36.00
Soil Backfill 143.52 1.00 1.00 1.00 1.00 143.52 m3 100% 143.52

A. 15 MH.24 - MH.07 33.00


Excavation 3.82 1.00 1.32 1.00 33.00 165.77 1.00 1.00 1.00 1.00 165.77 m3 100% 165.77
Lean Concrete 0.70 1.00 0.05 33.00 1.16 1.00 1.00 1.00 1.00 1.16 m3 100% 1.16
Lean Concrete Formwork 0.70 1.00 0.05 33.00 2.31 1.00 1.00 1.00 1.00 2.31 m2 100% 2.31
Sand Fill 3.82 1.00 0.30 33.00 37.82 1.00 1.00 1.00 1.00 37.82 m3 100% 37.82
Hume Pipe 500 mm 33.00 1.00 1.00 1.00 1.00 33.00 m 100% 33.00
Hume Pipe Mortar Grouting 33.00 1.00 1.00 1.00 1.00 33.00 m 100% 33.00
Soil Backfill 159.29 1.00 1.00 1.00 1.00 159.29 m3 100% 159.29

A. 16 MH.25 - MH.26 18.00


Excavation 3.82 1.00 1.02 1.00 18.00 70.14 1.00 1.00 1.00 1.00 70.14 m3 100% 70.14
Lean Concrete 0.70 1.00 0.05 18.00 0.63 1.00 1.00 1.00 1.00 0.63 m3 100% 0.63
Lean Concrete Formwork 0.70 1.00 0.05 18.00 1.26 1.00 1.00 1.00 1.00 1.26 m2 100% 1.26
Sand Fill 3.82 1.00 0.30 18.00 20.63 1.00 1.00 1.00 1.00 20.63 m3 100% 20.63
Hume Pipe 500 mm 18.00 1.00 1.00 1.00 1.00 18.00 m 100% 18.00
Hume Pipe Mortar Grouting 18.00 1.00 1.00 1.00 1.00 18.00 m 100% 18.00
Soil Backfill 66.60 1.00 1.00 1.00 1.00 66.60 m3 100% 66.60

A. 17 MH.26 - MH.27 11.20


Excavation 3.82 1.00 1.05 1.00 11.20 44.92 1.00 1.00 1.00 1.00 44.92 m3 100% 44.92
Lean Concrete 0.70 1.00 0.05 11.20 0.39 1.00 1.00 1.00 1.00 0.39 m3 100% 0.39
Lean Concrete Formwork 0.70 1.00 0.05 11.20 0.78 1.00 1.00 1.00 1.00 0.78 m2 100% 0.78
Sand Fill 3.82 1.00 0.30 11.20 12.84 1.00 1.00 1.00 1.00 12.84 m3 100% 12.84
Hume Pipe 500 mm 11.20 1.00 1.00 1.00 1.00 11.20 m 100% 11.20
Hume Pipe Mortar Grouting 11.20 1.00 1.00 1.00 1.00 11.20 m 100% 11.20
Soil Backfill 42.73 1.00 1.00 1.00 1.00 42.73 m3 100% 42.73

A. 18 MH.27 - MH.28 20.20


Excavation 3.82 1.00 1.05 1.00 20.20 81.02 1.00 1.00 1.00 1.00 81.02 m3 0% -
Lean Concrete 0.70 1.00 0.05 20.20 0.71 1.00 1.00 1.00 1.00 0.71 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
Hume RC Pipe Installation 005 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Lean Concrete Formwork 0.70 1.00 0.05 20.20 1.41 1.00 1.00 1.00 1.00 1.41 m2 0% -
Sand Fill 3.82 1.00 0.30 20.20 23.15 1.00 1.00 1.00 1.00 23.15 m3 0% -
Hume Pipe 500 mm 20.20 1.00 1.00 1.00 1.00 20.20 m 0% -
Hume Pipe Mortar Grouting 20.20 1.00 1.00 1.00 1.00 20.20 m 0% -
Soil Backfill 77.06 1.00 1.00 1.00 1.00 77.06 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
Hume RC Pipe Installation 005 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 19 MH.29 - MH.30 20.20
Excavation 3.82 1.00 1.02 1.00 20.20 78.71 1.00 1.00 1.00 1.00 78.71 m3 100% 78.71
Lean Concrete 0.70 1.00 0.05 20.20 0.71 1.00 1.00 1.00 1.00 0.71 m3 100% 0.71
Lean Concrete Formwork 0.70 1.00 0.05 20.20 1.41 1.00 1.00 1.00 1.00 1.41 m2 100% 1.41
Sand Fill 3.82 1.00 0.30 20.20 23.15 1.00 1.00 1.00 1.00 23.15 m3 100% 23.15
Hume Pipe 500 mm 20.20 1.00 1.00 1.00 1.00 20.20 m 100% 20.20
Hume Pipe Mortar Grouting 20.20 1.00 1.00 1.00 1.00 20.20 m 100% 20.20
Soil Backfill 74.74 1.00 1.00 1.00 1.00 74.74 m3 100% 74.74

A. 20 MH.30 - MH.26 9.80


Excavation 3.82 1.00 1.04 1.00 9.80 38.93 1.00 1.00 1.00 1.00 38.93 m3 100% 38.93
Lean Concrete 0.70 1.00 0.05 9.80 0.34 1.00 1.00 1.00 1.00 0.34 m3 100% 0.34
Lean Concrete Formwork 0.70 1.00 0.05 9.80 0.69 1.00 1.00 1.00 1.00 0.69 m2 100% 0.69
Sand Fill 3.82 1.00 0.30 9.80 11.23 1.00 1.00 1.00 1.00 11.23 m3 100% 11.23
Hume Pipe 500 mm 9.80 1.00 1.00 1.00 1.00 9.80 m 100% 9.80
Hume Pipe Mortar Grouting 9.80 1.00 1.00 1.00 1.00 9.80 m 100% 9.80
Soil Backfill 37.01 1.00 1.00 1.00 1.00 37.01 m3 100% 37.01

A. 21 MH.31 - MH.32 10.00


Excavation 3.82 1.00 1.04 1.00 10.00 39.73 1.00 1.00 1.00 1.00 39.73 m3 0% -
Lean Concrete 0.70 1.00 0.05 10.00 0.35 1.00 1.00 1.00 1.00 0.35 m3 0% -
Lean Concrete Formwork 0.70 1.00 0.05 10.00 0.70 1.00 1.00 1.00 1.00 0.70 m2 0% -
Sand Fill 3.82 1.00 0.30 10.00 11.46 1.00 1.00 1.00 1.00 11.46 m3 0% -
Hume Pipe 500 mm 10.00 1.00 1.00 1.00 1.00 10.00 m 0% -
Hume Pipe Mortar Grouting 10.00 1.00 1.00 1.00 1.00 10.00 m 0% -
Soil Backfill 37.77 1.00 1.00 1.00 1.00 37.77 m3 0% -

A. 22 MH.32 - MH.28 6.60


Excavation 3.82 1.00 1.04 1.00 6.60 26.22 1.00 1.00 1.00 1.00 26.22 m3 0% -
Lean Concrete 0.70 1.00 0.05 6.60 0.23 1.00 1.00 1.00 1.00 0.23 m3 0% -
Lean Concrete Formwork 0.70 1.00 0.05 6.60 0.46 1.00 1.00 1.00 1.00 0.46 m2 0% -
Sand Fill 3.82 1.00 0.30 6.60 7.56 1.00 1.00 1.00 1.00 7.56 m3 0% -
Hume Pipe 500 mm 6.60 1.00 1.00 1.00 1.00 6.60 m 0% -
Hume Pipe Mortar Grouting 6.60 1.00 1.00 1.00 1.00 6.60 m 0% -
Soil Backfill 24.93 1.00 1.00 1.00 1.00 24.93 m3 0% -

B HUME RC PIPE 600 mm

B. 1 MH.16 - MH.17 26.00


Excavation 3.82 1.00 1.04 1.00 26.00 103.29 1.00 1.00 1.00 1.00 103.29 m3 100% 103.29
Lean Concrete 0.70 1.00 0.05 26.00 0.91 1.00 1.00 1.00 1.00 0.91 m3 100% 0.91
Lean Concrete Formwork 0.70 1.00 0.05 26.00 1.82 1.00 1.00 1.00 1.00 1.82 m2 100% 1.82
Sand Fill 3.82 1.00 0.30 26.00 29.80 1.00 1.00 1.00 1.00 29.80 m3 100% 29.80
Hume Pipe 600 mm 26.00 1.00 1.00 1.00 1.00 26.00 m 100% 26.00
Hume Pipe Mortar Grouting 26.00 1.00 1.00 1.00 1.00 26.00 m 100% 26.00
Soil Backfill 98.19 1.00 1.00 1.00 1.00 98.19 m3 100% 98.19

B. 2 MH.17 - MH.18 25.50


Excavation 3.82 1.00 1.04 1.00 25.50 101.31 1.00 1.00 1.00 1.00 101.31 m3 100% 101.31
Progress Calculation PROGRESS CALCULATION FORM Progress Date
Hume RC Pipe Installation 005 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Lean Concrete 0.70 1.00 0.05 25.50 0.89 1.00 1.00 1.00 1.00 0.89 m3 100% 0.89
Lean Concrete Formwork 0.70 1.00 0.05 25.50 1.79 1.00 1.00 1.00 1.00 1.79 m2 100% 1.79
Sand Fill 3.82 1.00 0.30 25.50 29.22 1.00 1.00 1.00 1.00 29.22 m3 100% 29.22
Hume Pipe 600 mm 25.50 1.00 1.00 1.00 1.00 25.50 m 100% 25.50
Hume Pipe Mortar Grouting 25.50 1.00 1.00 1.00 1.00 25.50 m 100% 25.50
Soil Backfill 96.30 1.00 1.00 1.00 1.00 96.30 m3 100% 96.30
Progress Calculation PROGRESS CALCULATION FORM Progress Date
Hume RC Pipe Installation 005 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
B. 3 MH.18 - MH.19 32.80
Excavation 3.82 1.00 1.04 1.00 32.80 130.31 1.00 1.00 1.00 1.00 130.31 m3 100% 130.31
Lean Concrete 0.70 1.00 0.05 32.80 1.15 1.00 1.00 1.00 1.00 1.15 m3 100% 1.15
Lean Concrete Formwork 0.70 1.00 0.05 32.80 2.30 1.00 1.00 1.00 1.00 2.30 m2 100% 2.30
Sand Fill 3.82 1.00 0.30 32.80 37.59 1.00 1.00 1.00 1.00 37.59 m3 100% 37.59
Hume Pipe 600 mm 32.80 1.00 1.00 1.00 1.00 32.80 m 100% 32.80
Hume Pipe Mortar Grouting 32.80 1.00 1.00 1.00 1.00 32.80 m 100% 32.80
Soil Backfill 123.87 1.00 1.00 1.00 1.00 123.87 m3 100% 123.87

B. 4 MH.19 - MH.05 33.00


Excavation 3.82 1.00 1.04 1.00 33.00 131.10 1.00 1.00 1.00 1.00 131.10 m3 100% 131.10
Lean Concrete 0.70 1.00 0.05 33.00 1.16 1.00 1.00 1.00 1.00 1.16 m3 100% 1.16
Lean Concrete Formwork 0.70 1.00 0.05 33.00 2.31 1.00 1.00 1.00 1.00 2.31 m2 100% 2.31
Sand Fill 3.82 1.00 0.30 33.00 37.82 1.00 1.00 1.00 1.00 37.82 m3 100% 37.82
Hume Pipe 600 mm 33.00 1.00 1.00 1.00 1.00 33.00 m 100% 33.00
Hume Pipe Mortar Grouting 33.00 1.00 1.00 1.00 1.00 33.00 m 100% 33.00
Soil Backfill 124.63 1.00 1.00 1.00 1.00 124.63 m3 100% 124.63

B. 5 MH.28 - River 7.00


Excavation 3.82 1.00 1.04 1.00 7.00 27.81 1.00 1.00 1.00 1.00 27.81 m3 0% -
Lean Concrete 0.70 1.00 0.05 7.00 0.25 1.00 1.00 1.00 1.00 0.25 m3 0% -
Lean Concrete Formwork 0.70 1.00 0.05 7.00 0.49 1.00 1.00 1.00 1.00 0.49 m2 0% -
Sand Fill 3.82 1.00 0.30 7.00 8.02 1.00 1.00 1.00 1.00 8.02 m3 0% -
Hume Pipe 600 mm 7.00 1.00 1.00 1.00 1.00 7.00 m 0% -
Hume Pipe Mortar Grouting 7.00 1.00 1.00 1.00 1.00 7.00 m 0% -
Soil Backfill 26.44 1.00 1.00 1.00 1.00 26.44 m3 0% -

C HUME RC PIPE 800 mm

C. 1 MH.05 - MH.06 36.00


Excavation 3.82 1.00 1.04 1.00 36.00 143.02 1.00 1.00 1.00 1.00 143.02 m3 100% 143.02
Lean Concrete 0.70 1.00 0.05 36.00 1.26 1.00 1.00 1.00 1.00 1.26 m3 100% 1.26
Lean Concrete Formwork 0.70 1.00 0.05 36.00 2.52 1.00 1.00 1.00 1.00 2.52 m2 100% 2.52
Sand Fill 3.82 1.00 0.30 36.00 41.26 1.00 1.00 1.00 1.00 41.26 m3 100% 41.26
Hume Pipe 800 mm 36.00 1.00 1.00 1.00 1.00 36.00 m 100% 36.00
Hume Pipe Mortar Grouting 36.00 1.00 1.00 1.00 1.00 36.00 m 100% 36.00
Soil Backfill 135.96 1.00 1.00 1.00 1.00 135.96 m3 100% 135.96

C. 2 MH.06 - MH.07 26.50


Excavation 3.82 1.00 1.04 1.00 26.50 105.28 1.00 1.00 1.00 1.00 105.28 m3 100% 105.28
Lean Concrete 0.70 1.00 0.05 26.50 0.93 1.00 1.00 1.00 1.00 0.93 m3 100% 0.93
Lean Concrete Formwork 0.70 1.00 0.05 26.50 1.86 1.00 1.00 1.00 1.00 1.86 m2 100% 1.86
Sand Fill 3.82 1.00 0.30 26.50 30.37 1.00 1.00 1.00 1.00 30.37 m3 100% 30.37
Hume Pipe 800 mm 26.50 1.00 1.00 1.00 1.00 26.50 m 100% 26.50
Hume Pipe Mortar Grouting 26.50 1.00 1.00 1.00 1.00 26.50 m 100% 26.50
Soil Backfill 100.08 1.00 1.00 1.00 1.00 100.08 m3 100% 100.08

C. 3 MH.07 - MH.08 11.40


Excavation 3.82 1.00 1.04 1.00 11.40 45.29 1.00 1.00 1.00 1.00 45.29 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
Hume RC Pipe Installation 005 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Lean Concrete 0.70 1.00 0.05 11.40 0.40 1.00 1.00 1.00 1.00 0.40 m3 0% -
Lean Concrete Formwork 0.70 1.00 0.05 11.40 0.80 1.00 1.00 1.00 1.00 0.80 m2 0% -
Sand Fill 3.82 1.00 0.30 11.40 13.06 1.00 1.00 1.00 1.00 13.06 m3 0% -
Hume Pipe 800 mm 11.40 1.00 1.00 1.00 1.00 11.40 m 0% -
Hume Pipe Mortar Grouting 11.40 1.00 1.00 1.00 1.00 11.40 m 0% -
Soil Backfill 43.05 1.00 1.00 1.00 1.00 43.05 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
Hume RC Pipe Installation 005 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
C. 4 MH.07 - END 7.00
Excavation 3.82 1.00 1.04 1.00 7.00 27.81 1.00 1.00 1.00 1.00 27.81 m3 0% -
Lean Concrete 0.70 1.00 0.05 7.00 0.25 1.00 1.00 1.00 1.00 0.25 m3 0% -
Lean Concrete Formwork 0.70 1.00 0.05 7.00 0.49 1.00 1.00 1.00 1.00 0.49 m2 0% -
Sand Fill 3.82 1.00 0.30 7.00 8.02 1.00 1.00 1.00 1.00 8.02 m3 0% -
Hume Pipe 800 mm 7.00 1.00 1.00 1.00 1.00 7.00 m 0% -
Hume Pipe Mortar Grouting 7.00 1.00 1.00 1.00 1.00 7.00 m 0% -
Soil Backfill 26.44 1.00 1.00 1.00 1.00 26.44 m3 0% -

RECAP FOR MAIN PROGRESS (BOQ ITEMS) Notes :


Progress Date 1. The Quantity Calculation is Still PT. SSA Version, It is Not Yet Together Measurement With KINE's Quantity Surveyor.
31/08/2023 2. Quantity Calculation Based On Approved Shop Drawing and Lotte Chemical E & C For Construction Drawing.

Progress Progress
No. Description Unit Total Quantity Remarks
Quantity Percentages
1 Excavation m3 3,030.08 2,782.20 91.8194%
2 Lean Concrete m3 27.46 25.28 92.0714%
3 Lean Concrete Formwork m2 55.33 50.98 92.1311%
4 Sand Fill m3 899.04 793.61 88.2728%
5 Hume Pipe 500 mm m 579.30 542.50 93.6475%
6 Hume Pipe 600 mm m 124.30 117.30 94.3685% ARITMATH CHECKING
7 Hume Pipe 800 mm m 80.90 62.50 77.2559% RECAP 8,457.04
8 Hume Pipe Mortar Grouting m 784.50 722.30 92.0714% BREAKDOWN 8,457.04
9 Soil Backfill m3 2,876.13 2,542.71 88.4075% IF ZERO = OK! -

GLOBAL PROGRESS FOR Hume RC Pipe Installation (AVERAGE PRORATE BY ITEMS) 90.0050%

31/08/2023
Checked by,
PT. Sepuluh Sumber Anugerah

Herdy Dwiyana
Quantity Surveyor
Progress Calculation PROGRESS CALCULATION FORM Progress Date
HDPE 200 mm Installation 006 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
HDPE FOR STORM WATER (SECTION
A
1)
A. 1 CB.1 4.50
Excavation 3.09 1.00 1.12 0.70 4.50 10.89 1.00 1.00 1.00 1.00 10.89 m3 0% -
Sand Fill 3.09 1.00 0.50 4.50 6.95 1.00 1.00 1.00 1.00 6.95 m3 0% -
HDPE Installation 4.50 1.00 1.00 1.00 1.00 4.50 m 0% -
Soil Backfill 10.01 1.00 1.00 1.00 1.00 10.01 m3 0% -

A. 2 CB.2 5.50
Excavation 3.09 1.00 1.12 0.70 5.50 13.32 1.00 1.00 1.00 1.00 13.32 m3 0% -
Sand Fill 3.09 1.00 0.50 5.50 8.49 1.00 1.00 1.00 1.00 8.49 m3 0% -
HDPE Installation 5.50 1.00 1.00 1.00 1.00 5.50 m 0% -
Soil Backfill 12.24 1.00 1.00 1.00 1.00 12.24 m3 0% -

A. 3 CB.3 10.30
Excavation 3.09 1.00 1.12 0.70 10.30 24.94 1.00 1.00 1.00 1.00 24.94 m3 0% -
Sand Fill 3.09 1.00 0.50 10.30 15.90 1.00 1.00 1.00 1.00 15.90 m3 0% -
HDPE Installation 10.30 1.00 1.00 1.00 1.00 10.30 m 0% -
Soil Backfill 22.91 1.00 1.00 1.00 1.00 22.91 m3 0% -

A. 4 CB.4 10.80
Excavation 3.09 1.00 1.12 0.70 10.80 26.15 1.00 1.00 1.00 1.00 26.15 m3 0% -
Sand Fill 3.09 1.00 0.50 10.80 16.68 1.00 1.00 1.00 1.00 16.68 m3 0% -
HDPE Installation 10.80 1.00 1.00 1.00 1.00 10.80 m 0% -
Soil Backfill 24.03 1.00 1.00 1.00 1.00 24.03 m3 0% -

A. 5 CB.5 3.50
Excavation 3.09 1.00 1.12 0.70 3.50 8.47 1.00 1.00 1.00 1.00 8.47 m3 0% -
Sand Fill 3.09 1.00 0.50 3.50 5.40 1.00 1.00 1.00 1.00 5.40 m3 0% -
HDPE Installation 3.50 1.00 1.00 1.00 1.00 3.50 m 0% -
Soil Backfill 7.79 1.00 1.00 1.00 1.00 7.79 m3 0% -

A. 6 CB.6 10.00
Excavation 3.09 1.00 1.12 0.70 10.00 24.21 1.00 1.00 1.00 1.00 24.21 m3 0% -
Sand Fill 3.09 1.00 0.50 10.00 15.44 1.00 1.00 1.00 1.00 15.44 m3 0% -
HDPE Installation 10.00 1.00 1.00 1.00 1.00 10.00 m 0% -
Soil Backfill 22.25 1.00 1.00 1.00 1.00 22.25 m3 0% -

A. 7 CB.7 3.00
Excavation 3.09 1.00 1.12 0.70 3.00 7.26 1.00 1.00 1.00 1.00 7.26 m3 0% -
Sand Fill 3.09 1.00 0.50 3.00 4.63 1.00 1.00 1.00 1.00 4.63 m3 0% -
HDPE Installation 3.00 1.00 1.00 1.00 1.00 3.00 m 0% -
Soil Backfill 6.67 1.00 1.00 1.00 1.00 6.67 m3 0% -

A. 8 CB.8 3.90
Excavation 3.09 1.00 1.12 0.70 3.90 9.44 1.00 1.00 1.00 1.00 9.44 m3 0% -
Sand Fill 3.09 1.00 0.50 3.90 6.02 1.00 1.00 1.00 1.00 6.02 m3 0% -
HDPE Installation 3.90 1.00 1.00 1.00 1.00 3.90 m 0% -
Soil Backfill 8.68 1.00 1.00 1.00 1.00 8.68 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
HDPE 200 mm Installation 006 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 9 CB.9 6.10
Excavation 3.09 1.00 1.12 0.70 6.10 14.77 1.00 1.00 1.00 1.00 14.77 m3 0% -
Sand Fill 3.09 1.00 0.50 6.10 9.42 1.00 1.00 1.00 1.00 9.42 m3 0% -
HDPE Installation 6.10 1.00 1.00 1.00 1.00 6.10 m 0% -
Soil Backfill 13.57 1.00 1.00 1.00 1.00 13.57 m3 0% -

A. 10 CB.10 6.90
Excavation 3.09 1.00 1.12 0.70 6.90 16.70 1.00 1.00 1.00 1.00 16.70 m3 0% -
Sand Fill 3.09 1.00 0.50 6.90 10.65 1.00 1.00 1.00 1.00 10.65 m3 0% -
HDPE Installation 6.90 1.00 1.00 1.00 1.00 6.90 m 0% -
Soil Backfill 15.35 1.00 1.00 1.00 1.00 15.35 m3 0% -

A. 11 CB.11 10.00
Excavation 3.09 1.00 1.12 0.70 10.00 24.21 1.00 1.00 1.00 1.00 24.21 m3 0% -
Sand Fill 3.09 1.00 0.50 10.00 15.44 1.00 1.00 1.00 1.00 15.44 m3 0% -
HDPE Installation 10.00 1.00 1.00 1.00 1.00 10.00 m 0% -
Soil Backfill 22.25 1.00 1.00 1.00 1.00 22.25 m3 0% -

A. 12 CB.12 10.00
Excavation 3.09 1.00 1.12 0.70 10.00 24.21 1.00 1.00 1.00 1.00 24.21 m3 0% -
Sand Fill 3.09 1.00 0.50 10.00 15.44 1.00 1.00 1.00 1.00 15.44 m3 0% -
HDPE Installation 10.00 1.00 1.00 1.00 1.00 10.00 m 0% -
Soil Backfill 22.25 1.00 1.00 1.00 1.00 22.25 m3 0% -

A. 13 CB.13 6.70
Excavation 3.09 1.00 1.12 0.70 6.70 16.22 1.00 1.00 1.00 1.00 16.22 m3 0% -
Sand Fill 3.09 1.00 0.50 6.70 10.34 1.00 1.00 1.00 1.00 10.34 m3 0% -
HDPE Installation 6.70 1.00 1.00 1.00 1.00 6.70 m 0% -
Soil Backfill 14.91 1.00 1.00 1.00 1.00 14.91 m3 0% -

A. 14 CB.14 5.90
Excavation 3.09 1.00 1.12 0.70 5.90 14.28 1.00 1.00 1.00 1.00 14.28 m3 0% -
Sand Fill 3.09 1.00 0.50 5.90 9.11 1.00 1.00 1.00 1.00 9.11 m3 0% -
HDPE Installation 5.90 1.00 1.00 1.00 1.00 5.90 m 0% -
Soil Backfill 13.13 1.00 1.00 1.00 1.00 13.13 m3 0% -

A. 15 CB.15 3.30
Excavation 3.09 1.00 1.12 0.70 3.30 7.99 1.00 1.00 1.00 1.00 7.99 m3 0% -
Sand Fill 3.09 1.00 0.50 3.30 5.10 1.00 1.00 1.00 1.00 5.10 m3 0% -
HDPE Installation 3.30 1.00 1.00 1.00 1.00 3.30 m 0% -
Soil Backfill 7.34 1.00 1.00 1.00 1.00 7.34 m3 0% -

A. 16 CB.16 10.00
Excavation 3.09 1.00 1.12 0.70 10.00 24.21 1.00 1.00 1.00 1.00 24.21 m3 0% -
Sand Fill 3.09 1.00 0.50 10.00 15.44 1.00 1.00 1.00 1.00 15.44 m3 0% -
HDPE Installation 10.00 1.00 1.00 1.00 1.00 10.00 m 0% -
Soil Backfill 22.25 1.00 1.00 1.00 1.00 22.25 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
HDPE 200 mm Installation 006 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 17 CB.17 3.50
Excavation 3.09 1.00 1.12 0.70 3.50 8.47 1.00 1.00 1.00 1.00 8.47 m3 0% -
Sand Fill 3.09 1.00 0.50 3.50 5.40 1.00 1.00 1.00 1.00 5.40 m3 0% -
HDPE Installation 3.50 1.00 1.00 1.00 1.00 3.50 m 0% -
Soil Backfill 7.79 1.00 1.00 1.00 1.00 7.79 m3 0% -

A. 18 CB.18 10.00
Excavation 3.09 1.00 1.12 0.70 10.00 24.21 1.00 1.00 1.00 1.00 24.21 m3 0% -
Sand Fill 3.09 1.00 0.50 10.00 15.44 1.00 1.00 1.00 1.00 15.44 m3 0% -
HDPE Installation 10.00 1.00 1.00 1.00 1.00 10.00 m 0% -
Soil Backfill 22.25 1.00 1.00 1.00 1.00 22.25 m3 0% -

A. 19 CB.19 9.70
Excavation 3.09 1.00 1.12 0.70 9.70 23.48 1.00 1.00 1.00 1.00 23.48 m3 0% -
Sand Fill 3.09 1.00 0.50 9.70 14.98 1.00 1.00 1.00 1.00 14.98 m3 0% -
HDPE Installation 9.70 1.00 1.00 1.00 1.00 9.70 m 0% -
Soil Backfill 21.58 1.00 1.00 1.00 1.00 21.58 m3 0% -

A. 20 CB.20 7.20
Excavation 3.09 1.00 1.12 0.70 7.20 17.43 1.00 1.00 1.00 1.00 17.43 m3 0% -
Sand Fill 3.09 1.00 0.50 7.20 11.12 1.00 1.00 1.00 1.00 11.12 m3 0% -
HDPE Installation 7.20 1.00 1.00 1.00 1.00 7.20 m 0% -
Soil Backfill 16.02 1.00 1.00 1.00 1.00 16.02 m3 0% -

A. 21 CB.21 7.20
Excavation 3.09 1.00 1.12 0.70 7.20 17.43 1.00 1.00 1.00 1.00 17.43 m3 0% -
Sand Fill 3.09 1.00 0.50 7.20 11.12 1.00 1.00 1.00 1.00 11.12 m3 0% -
HDPE Installation 7.20 1.00 1.00 1.00 1.00 7.20 m 0% -
Soil Backfill 16.02 1.00 1.00 1.00 1.00 16.02 m3 0% -

A. 22 CB.22 13.40
Excavation 3.09 1.00 1.12 0.70 13.40 32.44 1.00 1.00 1.00 1.00 32.44 m3 0% -
Sand Fill 3.09 1.00 0.50 13.40 20.69 1.00 1.00 1.00 1.00 20.69 m3 0% -
HDPE Installation 13.40 1.00 1.00 1.00 1.00 13.40 m 0% -
Soil Backfill 29.81 1.00 1.00 1.00 1.00 29.81 m3 0% -

A. 23 CB.23 2.80
Excavation 3.09 1.00 1.12 0.70 2.80 6.78 1.00 1.00 1.00 1.00 6.78 m3 0% -
Sand Fill 3.09 1.00 0.50 2.80 4.32 1.00 1.00 1.00 1.00 4.32 m3 0% -
HDPE Installation 2.80 1.00 1.00 1.00 1.00 2.80 m 0% -
Soil Backfill 6.23 1.00 1.00 1.00 1.00 6.23 m3 0% -

A. 24 CB.24 4.70
Excavation 3.09 1.00 1.12 0.70 4.70 11.38 1.00 1.00 1.00 1.00 11.38 m3 0% -
Sand Fill 3.09 1.00 0.50 4.70 7.26 1.00 1.00 1.00 1.00 7.26 m3 0% -
HDPE Installation 4.70 1.00 1.00 1.00 1.00 4.70 m 0% -
Soil Backfill 10.46 1.00 1.00 1.00 1.00 10.46 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
HDPE 200 mm Installation 006 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 25 CB.25 9.80
Excavation 3.09 1.00 1.12 0.70 9.80 23.73 1.00 1.00 1.00 1.00 23.73 m3 0% -
Sand Fill 3.09 1.00 0.50 9.80 15.13 1.00 1.00 1.00 1.00 15.13 m3 0% -
HDPE Installation 9.80 1.00 1.00 1.00 1.00 9.80 m 0% -
Soil Backfill 21.80 1.00 1.00 1.00 1.00 21.80 m3 0% -

A. 26 CB.26 3.70
Excavation 3.09 1.00 1.12 0.70 3.70 8.96 1.00 1.00 1.00 1.00 8.96 m3 0% -
Sand Fill 3.09 1.00 0.50 3.70 5.71 1.00 1.00 1.00 1.00 5.71 m3 0% -
HDPE Installation 3.70 1.00 1.00 1.00 1.00 3.70 m 0% -
Soil Backfill 8.23 1.00 1.00 1.00 1.00 8.23 m3 0% -

A. 27 CB.27 4.70
Excavation 3.09 1.00 1.12 0.70 4.70 11.38 1.00 1.00 1.00 1.00 11.38 m3 0% -
Sand Fill 3.09 1.00 0.50 4.70 7.26 1.00 1.00 1.00 1.00 7.26 m3 0% -
HDPE Installation 4.70 1.00 1.00 1.00 1.00 4.70 m 0% -
Soil Backfill 10.46 1.00 1.00 1.00 1.00 10.46 m3 0% -

A. 28 CB.28 9.50
Excavation 3.09 1.00 1.12 0.70 9.50 23.00 1.00 1.00 1.00 1.00 23.00 m3 0% -
Sand Fill 3.09 1.00 0.50 9.50 14.67 1.00 1.00 1.00 1.00 14.67 m3 0% -
HDPE Installation 9.50 1.00 1.00 1.00 1.00 9.50 m 0% -
Soil Backfill 21.14 1.00 1.00 1.00 1.00 21.14 m3 0% -

A. 29 CB.29 8.60
Excavation 3.09 1.00 1.12 0.70 8.60 20.82 1.00 1.00 1.00 1.00 20.82 m3 0% -
Sand Fill 3.09 1.00 0.50 8.60 13.28 1.00 1.00 1.00 1.00 13.28 m3 0% -
HDPE Installation 8.60 1.00 1.00 1.00 1.00 8.60 m 0% -
Soil Backfill 19.13 1.00 1.00 1.00 1.00 19.13 m3 0% -

A. 30 CB.30 10.00
Excavation 3.09 1.00 1.12 0.70 10.00 24.21 1.00 1.00 1.00 1.00 24.21 m3 0% -
Sand Fill 3.09 1.00 0.50 10.00 15.44 1.00 1.00 1.00 1.00 15.44 m3 0% -
HDPE Installation 10.00 1.00 1.00 1.00 1.00 10.00 m 0% -
Soil Backfill 22.25 1.00 1.00 1.00 1.00 22.25 m3 0% -

A. 31 CB.31 11.40
Excavation 3.09 1.00 1.12 0.70 11.40 27.60 1.00 1.00 1.00 1.00 27.60 m3 0% -
Sand Fill 3.09 1.00 0.50 11.40 17.60 1.00 1.00 1.00 1.00 17.60 m3 0% -
HDPE Installation 11.40 1.00 1.00 1.00 1.00 11.40 m 0% -
Soil Backfill 25.36 1.00 1.00 1.00 1.00 25.36 m3 0% -

A. 32 CB.32 6.90
Excavation 3.09 1.00 1.12 0.70 6.90 16.70 1.00 1.00 1.00 1.00 16.70 m3 0% -
Sand Fill 3.09 1.00 0.50 6.90 10.65 1.00 1.00 1.00 1.00 10.65 m3 0% -
HDPE Installation 6.90 1.00 1.00 1.00 1.00 6.90 m 0% -
Soil Backfill 15.35 1.00 1.00 1.00 1.00 15.35 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
HDPE 200 mm Installation 006 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 33 CB.33 7.30
Excavation 3.09 1.00 1.12 0.70 7.30 17.67 1.00 1.00 1.00 1.00 17.67 m3 0% -
Sand Fill 3.09 1.00 0.50 7.30 11.27 1.00 1.00 1.00 1.00 11.27 m3 0% -
HDPE Installation 7.30 1.00 1.00 1.00 1.00 7.30 m 0% -
Soil Backfill 16.24 1.00 1.00 1.00 1.00 16.24 m3 0% -

A. 34 CB.34 7.50
Excavation 3.09 1.00 1.12 0.70 7.50 18.16 1.00 1.00 1.00 1.00 18.16 m3 0% -
Sand Fill 3.09 1.00 0.50 7.50 11.58 1.00 1.00 1.00 1.00 11.58 m3 0% -
HDPE Installation 7.50 1.00 1.00 1.00 1.00 7.50 m 0% -
Soil Backfill 16.69 1.00 1.00 1.00 1.00 16.69 m3 0% -

A. 35 CB.35 12.10
Excavation 3.09 1.00 1.12 0.70 12.10 29.29 1.00 1.00 1.00 1.00 29.29 m3 0% -
Sand Fill 3.09 1.00 0.50 12.10 18.68 1.00 1.00 1.00 1.00 18.68 m3 0% -
HDPE Installation 12.10 1.00 1.00 1.00 1.00 12.10 m 0% -
Soil Backfill 26.92 1.00 1.00 1.00 1.00 26.92 m3 0% -

A. 36 CB.36 7.50
Excavation 3.09 1.00 1.12 0.70 7.50 18.16 1.00 1.00 1.00 1.00 18.16 m3 0% -
Sand Fill 3.09 1.00 0.50 7.50 11.58 1.00 1.00 1.00 1.00 11.58 m3 0% -
HDPE Installation 7.50 1.00 1.00 1.00 1.00 7.50 m 0% -
Soil Backfill 16.69 1.00 1.00 1.00 1.00 16.69 m3 0% -

A. 37 CB.37 7.50
Excavation 3.09 1.00 1.12 0.70 7.50 18.16 1.00 1.00 1.00 1.00 18.16 m3 0% -
Sand Fill 3.09 1.00 0.50 7.50 11.58 1.00 1.00 1.00 1.00 11.58 m3 0% -
HDPE Installation 7.50 1.00 1.00 1.00 1.00 7.50 m 0% -
Soil Backfill 16.69 1.00 1.00 1.00 1.00 16.69 m3 0% -

A. 38 CB.38 6.70
Excavation 3.09 1.00 1.12 0.70 6.70 16.22 1.00 1.00 1.00 1.00 16.22 m3 0% -
Sand Fill 3.09 1.00 0.50 6.70 10.34 1.00 1.00 1.00 1.00 10.34 m3 0% -
HDPE Installation 6.70 1.00 1.00 1.00 1.00 6.70 m 0% -
Soil Backfill 14.91 1.00 1.00 1.00 1.00 14.91 m3 0% -

A. 39 CB.39 7.50
Excavation 3.09 1.00 1.12 0.70 7.50 18.16 1.00 1.00 1.00 1.00 18.16 m3 0% -
Sand Fill 3.09 1.00 0.50 7.50 11.58 1.00 1.00 1.00 1.00 11.58 m3 0% -
HDPE Installation 7.50 1.00 1.00 1.00 1.00 7.50 m 0% -
Soil Backfill 16.69 1.00 1.00 1.00 1.00 16.69 m3 0% -

A. 40 CB.40 7.50
Excavation 3.09 1.00 1.12 0.70 7.50 18.16 1.00 1.00 1.00 1.00 18.16 m3 0% -
Sand Fill 3.09 1.00 0.50 7.50 11.58 1.00 1.00 1.00 1.00 11.58 m3 0% -
HDPE Installation 7.50 1.00 1.00 1.00 1.00 7.50 m 0% -
Soil Backfill 16.69 1.00 1.00 1.00 1.00 16.69 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
HDPE 200 mm Installation 006 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 41 CB.41 4.80
Excavation 3.09 1.00 1.12 0.70 4.80 11.62 1.00 1.00 1.00 1.00 11.62 m3 0% -
Sand Fill 3.09 1.00 0.50 4.80 7.41 1.00 1.00 1.00 1.00 7.41 m3 0% -
HDPE Installation 4.80 1.00 1.00 1.00 1.00 4.80 m 0% -
Soil Backfill 10.68 1.00 1.00 1.00 1.00 10.68 m3 0% -

A. 42 CB.42 7.50
Excavation 3.09 1.00 1.12 0.70 7.50 18.16 1.00 1.00 1.00 1.00 18.16 m3 0% -
Sand Fill 3.09 1.00 0.50 7.50 11.58 1.00 1.00 1.00 1.00 11.58 m3 0% -
HDPE Installation 7.50 1.00 1.00 1.00 1.00 7.50 m 0% -
Soil Backfill 16.69 1.00 1.00 1.00 1.00 16.69 m3 0% -

A. 43 CB.43 7.50
Excavation 3.09 1.00 1.12 0.70 7.50 18.16 1.00 1.00 1.00 1.00 18.16 m3 0% -
Sand Fill 3.09 1.00 0.50 7.50 11.58 1.00 1.00 1.00 1.00 11.58 m3 0% -
HDPE Installation 7.50 1.00 1.00 1.00 1.00 7.50 m 0% -
Soil Backfill 16.69 1.00 1.00 1.00 1.00 16.69 m3 0% -

A. 44 CB.44 6.80
Excavation 3.09 1.00 1.12 0.70 6.80 16.46 1.00 1.00 1.00 1.00 16.46 m3 0% -
Sand Fill 3.09 1.00 0.50 6.80 10.50 1.00 1.00 1.00 1.00 10.50 m3 0% -
HDPE Installation 6.80 1.00 1.00 1.00 1.00 6.80 m 0% -
Soil Backfill 15.13 1.00 1.00 1.00 1.00 15.13 m3 0% -

A. 45 CB.45 3.20
Excavation 3.09 1.00 1.12 0.70 3.20 7.75 1.00 1.00 1.00 1.00 7.75 m3 0% -
Sand Fill 3.09 1.00 0.50 3.20 4.94 1.00 1.00 1.00 1.00 4.94 m3 0% -
HDPE Installation 3.20 1.00 1.00 1.00 1.00 3.20 m 0% -
Soil Backfill 7.12 1.00 1.00 1.00 1.00 7.12 m3 0% -

A. 46 CB.46 11.50
Excavation 3.09 1.00 1.12 0.70 11.50 27.84 1.00 1.00 1.00 1.00 27.84 m3 0% -
Sand Fill 3.09 1.00 0.50 11.50 17.76 1.00 1.00 1.00 1.00 17.76 m3 0% -
HDPE Installation 11.50 1.00 1.00 1.00 1.00 11.50 m 0% -
Soil Backfill 25.58 1.00 1.00 1.00 1.00 25.58 m3 0% -

A. 47 CB.47 11.50
Excavation 3.09 1.00 1.12 0.70 11.50 27.84 1.00 1.00 1.00 1.00 27.84 m3 0% -
Sand Fill 3.09 1.00 0.50 11.50 17.76 1.00 1.00 1.00 1.00 17.76 m3 0% -
HDPE Installation 11.50 1.00 1.00 1.00 1.00 11.50 m 0% -
Soil Backfill 25.58 1.00 1.00 1.00 1.00 25.58 m3 0% -

A. 48 CB.48 11.50
Excavation 3.09 1.00 1.12 0.70 11.50 27.84 1.00 1.00 1.00 1.00 27.84 m3 0% -
Sand Fill 3.09 1.00 0.50 11.50 17.76 1.00 1.00 1.00 1.00 17.76 m3 0% -
HDPE Installation 11.50 1.00 1.00 1.00 1.00 11.50 m 0% -
Soil Backfill 25.58 1.00 1.00 1.00 1.00 25.58 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
HDPE 200 mm Installation 006 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 49 CB.49 7.50
Excavation 3.09 1.00 1.12 0.70 7.50 18.16 1.00 1.00 1.00 1.00 18.16 m3 0% -
Sand Fill 3.09 1.00 0.50 7.50 11.58 1.00 1.00 1.00 1.00 11.58 m3 0% -
HDPE Installation 7.50 1.00 1.00 1.00 1.00 7.50 m 0% -
Soil Backfill 16.69 1.00 1.00 1.00 1.00 16.69 m3 0% -

A. 50 CB.50 7.50
Excavation 3.09 1.00 1.12 0.70 7.50 18.16 1.00 1.00 1.00 1.00 18.16 m3 0% -
Sand Fill 3.09 1.00 0.50 7.50 11.58 1.00 1.00 1.00 1.00 11.58 m3 0% -
HDPE Installation 7.50 1.00 1.00 1.00 1.00 7.50 m 0% -
Soil Backfill 16.69 1.00 1.00 1.00 1.00 16.69 m3 0% -

A. 51 CB.51 11.50
Excavation 3.09 1.00 1.12 0.70 11.50 27.84 1.00 1.00 1.00 1.00 27.84 m3 0% -
Sand Fill 3.09 1.00 0.50 11.50 17.76 1.00 1.00 1.00 1.00 17.76 m3 0% -
HDPE Installation 11.50 1.00 1.00 1.00 1.00 11.50 m 0% -
Soil Backfill 25.58 1.00 1.00 1.00 1.00 25.58 m3 0% -

A. 52 CB.52 2.70
Excavation 3.09 1.00 1.12 0.70 2.70 6.54 1.00 1.00 1.00 1.00 6.54 m3 0% -
Sand Fill 3.09 1.00 0.50 2.70 4.17 1.00 1.00 1.00 1.00 4.17 m3 0% -
HDPE Installation 2.70 1.00 1.00 1.00 1.00 2.70 m 0% -
Soil Backfill 6.01 1.00 1.00 1.00 1.00 6.01 m3 0% -

A. 53 CB.53 7.50
Excavation 3.09 1.00 1.12 0.70 7.50 18.16 1.00 1.00 1.00 1.00 18.16 m3 0% -
Sand Fill 3.09 1.00 0.50 7.50 11.58 1.00 1.00 1.00 1.00 11.58 m3 0% -
HDPE Installation 7.50 1.00 1.00 1.00 1.00 7.50 m 0% -
Soil Backfill 16.69 1.00 1.00 1.00 1.00 16.69 m3 0% -

A. 54 CB.54 6.20
Excavation 3.09 1.00 1.12 0.70 6.20 15.01 1.00 1.00 1.00 1.00 15.01 m3 0% -
Sand Fill 3.09 1.00 0.50 6.20 9.57 1.00 1.00 1.00 1.00 9.57 m3 0% -
HDPE Installation 6.20 1.00 1.00 1.00 1.00 6.20 m 0% -
Soil Backfill 13.79 1.00 1.00 1.00 1.00 13.79 m3 0% -

A. 55 CB.55 6.80
Excavation 3.09 1.00 1.12 0.70 6.80 16.46 1.00 1.00 1.00 1.00 16.46 m3 0% -
Sand Fill 3.09 1.00 0.50 6.80 10.50 1.00 1.00 1.00 1.00 10.50 m3 0% -
HDPE Installation 6.80 1.00 1.00 1.00 1.00 6.80 m 0% -
Soil Backfill 15.13 1.00 1.00 1.00 1.00 15.13 m3 0% -

A. 56 CB.56 7.40
Excavation 3.09 1.00 1.12 0.70 7.40 17.92 1.00 1.00 1.00 1.00 17.92 m3 0% -
Sand Fill 3.09 1.00 0.50 7.40 11.43 1.00 1.00 1.00 1.00 11.43 m3 0% -
HDPE Installation 7.40 1.00 1.00 1.00 1.00 7.40 m 0% -
Soil Backfill 16.46 1.00 1.00 1.00 1.00 16.46 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
HDPE 200 mm Installation 006 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 57 CB.57 7.30
Excavation 3.09 1.00 1.12 0.70 7.30 17.67 1.00 1.00 1.00 1.00 17.67 m3 0% -
Sand Fill 3.09 1.00 0.50 7.30 11.27 1.00 1.00 1.00 1.00 11.27 m3 0% -
HDPE Installation 7.30 1.00 1.00 1.00 1.00 7.30 m 0% -
Soil Backfill 16.24 1.00 1.00 1.00 1.00 16.24 m3 0% -

A. 58 CB.58 6.70
Excavation 3.09 1.00 1.12 0.70 6.70 16.22 1.00 1.00 1.00 1.00 16.22 m3 0% -
Sand Fill 3.09 1.00 0.50 6.70 10.34 1.00 1.00 1.00 1.00 10.34 m3 0% -
HDPE Installation 6.70 1.00 1.00 1.00 1.00 6.70 m 0% -
Soil Backfill 14.91 1.00 1.00 1.00 1.00 14.91 m3 0% -

A. 59 CB.59 4.50
Excavation 3.09 1.00 1.12 0.70 4.50 10.89 1.00 1.00 1.00 1.00 10.89 m3 0% -
Sand Fill 3.09 1.00 0.50 4.50 6.95 1.00 1.00 1.00 1.00 6.95 m3 0% -
HDPE Installation 4.50 1.00 1.00 1.00 1.00 4.50 m 0% -
Soil Backfill 10.01 1.00 1.00 1.00 1.00 10.01 m3 0% -

A. 60 CB.60 8.70
Excavation 3.09 1.00 1.12 0.70 8.70 21.06 1.00 1.00 1.00 1.00 21.06 m3 0% -
Sand Fill 3.09 1.00 0.50 8.70 13.43 1.00 1.00 1.00 1.00 13.43 m3 0% -
HDPE Installation 8.70 1.00 1.00 1.00 1.00 8.70 m 0% -
Soil Backfill 19.36 1.00 1.00 1.00 1.00 19.36 m3 0% -

A. 61 CB.61 3.00
Excavation 3.09 1.00 1.12 0.70 3.00 7.26 1.00 1.00 1.00 1.00 7.26 m3 0% -
Sand Fill 3.09 1.00 0.50 3.00 4.63 1.00 1.00 1.00 1.00 4.63 m3 0% -
HDPE Installation 3.00 1.00 1.00 1.00 1.00 3.00 m 0% -
Soil Backfill 6.67 1.00 1.00 1.00 1.00 6.67 m3 0% -

A. 62 CB.62 3.00
Excavation 3.09 1.00 1.12 0.70 3.00 7.26 1.00 1.00 1.00 1.00 7.26 m3 0% -
Sand Fill 3.09 1.00 0.50 3.00 4.63 1.00 1.00 1.00 1.00 4.63 m3 0% -
HDPE Installation 3.00 1.00 1.00 1.00 1.00 3.00 m 0% -
Soil Backfill 6.67 1.00 1.00 1.00 1.00 6.67 m3 0% -

A. 63 CB.63 8.70
Excavation 3.09 1.00 1.12 0.70 8.70 21.06 1.00 1.00 1.00 1.00 21.06 m3 0% -
Sand Fill 3.09 1.00 0.50 8.70 13.43 1.00 1.00 1.00 1.00 13.43 m3 0% -
HDPE Installation 8.70 1.00 1.00 1.00 1.00 8.70 m 0% -
Soil Backfill 19.36 1.00 1.00 1.00 1.00 19.36 m3 0% -

A. 64 CB.64 8.70
Excavation 3.09 1.00 1.12 0.70 8.70 21.06 1.00 1.00 1.00 1.00 21.06 m3 0% -
Sand Fill 3.09 1.00 0.50 8.70 13.43 1.00 1.00 1.00 1.00 13.43 m3 0% -
HDPE Installation 8.70 1.00 1.00 1.00 1.00 8.70 m 0% -
Soil Backfill 19.36 1.00 1.00 1.00 1.00 19.36 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
HDPE 200 mm Installation 006 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 65 CB.65 3.00
Excavation 3.09 1.00 1.12 0.70 3.00 7.26 1.00 1.00 1.00 1.00 7.26 m3 0% -
Sand Fill 3.09 1.00 0.50 3.00 4.63 1.00 1.00 1.00 1.00 4.63 m3 0% -
HDPE Installation 3.00 1.00 1.00 1.00 1.00 3.00 m 0% -
Soil Backfill 6.67 1.00 1.00 1.00 1.00 6.67 m3 0% -

A. 66 CB.66 2.40
Excavation 3.09 1.00 1.12 0.70 2.40 5.81 1.00 1.00 1.00 1.00 5.81 m3 0% -
Sand Fill 3.09 1.00 0.50 2.40 3.71 1.00 1.00 1.00 1.00 3.71 m3 0% -
HDPE Installation 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Soil Backfill 5.34 1.00 1.00 1.00 1.00 5.34 m3 0% -

A. 67 CB.67 8.10
Excavation 3.09 1.00 1.12 0.70 8.10 19.61 1.00 1.00 1.00 1.00 19.61 m3 0% -
Sand Fill 3.09 1.00 0.50 8.10 12.51 1.00 1.00 1.00 1.00 12.51 m3 0% -
HDPE Installation 8.10 1.00 1.00 1.00 1.00 8.10 m 0% -
Soil Backfill 18.02 1.00 1.00 1.00 1.00 18.02 m3 0% -

A. 68 CB.68 8.70
Excavation 3.09 1.00 1.12 0.70 8.70 21.06 1.00 1.00 1.00 1.00 21.06 m3 0% -
Sand Fill 3.09 1.00 0.50 8.70 13.43 1.00 1.00 1.00 1.00 13.43 m3 0% -
HDPE Installation 8.70 1.00 1.00 1.00 1.00 8.70 m 0% -
Soil Backfill 19.36 1.00 1.00 1.00 1.00 19.36 m3 0% -

A. 69 CB.69 3.00
Excavation 3.09 1.00 1.12 0.70 3.00 7.26 1.00 1.00 1.00 1.00 7.26 m3 0% -
Sand Fill 3.09 1.00 0.50 3.00 4.63 1.00 1.00 1.00 1.00 4.63 m3 0% -
HDPE Installation 3.00 1.00 1.00 1.00 1.00 3.00 m 0% -
Soil Backfill 6.67 1.00 1.00 1.00 1.00 6.67 m3 0% -

A. 70 CB.70 7.60
Excavation 3.09 1.00 1.12 0.70 7.60 18.40 1.00 1.00 1.00 1.00 18.40 m3 0% -
Sand Fill 3.09 1.00 0.50 7.60 11.73 1.00 1.00 1.00 1.00 11.73 m3 0% -
HDPE Installation 7.60 1.00 1.00 1.00 1.00 7.60 m 0% -
Soil Backfill 16.91 1.00 1.00 1.00 1.00 16.91 m3 0% -

A. 71 CB.71 8.70
Excavation 3.09 1.00 1.12 0.70 8.70 21.06 1.00 1.00 1.00 1.00 21.06 m3 0% -
Sand Fill 3.09 1.00 0.50 8.70 13.43 1.00 1.00 1.00 1.00 13.43 m3 0% -
HDPE Installation 8.70 1.00 1.00 1.00 1.00 8.70 m 0% -
Soil Backfill 19.36 1.00 1.00 1.00 1.00 19.36 m3 0% -

A. 72 CB.72 8.20
Excavation 3.09 1.00 1.12 0.70 8.20 19.85 1.00 1.00 1.00 1.00 19.85 m3 0% -
Sand Fill 3.09 1.00 0.50 8.20 12.66 1.00 1.00 1.00 1.00 12.66 m3 0% -
HDPE Installation 8.20 1.00 1.00 1.00 1.00 8.20 m 0% -
Soil Backfill 18.24 1.00 1.00 1.00 1.00 18.24 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
HDPE 200 mm Installation 006 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 73 CB.73 7.20
Excavation 3.09 1.00 1.12 0.70 7.20 17.43 1.00 1.00 1.00 1.00 17.43 m3 0% -
Sand Fill 3.09 1.00 0.50 7.20 11.12 1.00 1.00 1.00 1.00 11.12 m3 0% -
HDPE Installation 7.20 1.00 1.00 1.00 1.00 7.20 m 0% -
Soil Backfill 16.02 1.00 1.00 1.00 1.00 16.02 m3 0% -

A. 74 CB.74 9.90
Excavation 3.09 1.00 1.12 0.70 9.90 23.97 1.00 1.00 1.00 1.00 23.97 m3 0% -
Sand Fill 3.09 1.00 0.50 9.90 15.29 1.00 1.00 1.00 1.00 15.29 m3 0% -
HDPE Installation 9.90 1.00 1.00 1.00 1.00 9.90 m 0% -
Soil Backfill 22.02 1.00 1.00 1.00 1.00 22.02 m3 0% -

A. 75 CB.75 8.20
Excavation 3.09 1.00 1.12 0.70 8.20 19.85 1.00 1.00 1.00 1.00 19.85 m3 0% -
Sand Fill 3.09 1.00 0.50 8.20 12.66 1.00 1.00 1.00 1.00 12.66 m3 0% -
HDPE Installation 8.20 1.00 1.00 1.00 1.00 8.20 m 0% -
Soil Backfill 18.24 1.00 1.00 1.00 1.00 18.24 m3 0% -

A. 76 CB.76 7.20
Excavation 3.09 1.00 1.12 0.70 7.20 17.43 1.00 1.00 1.00 1.00 17.43 m3 0% -
Sand Fill 3.09 1.00 0.50 7.20 11.12 1.00 1.00 1.00 1.00 11.12 m3 0% -
HDPE Installation 7.20 1.00 1.00 1.00 1.00 7.20 m 0% -
Soil Backfill 16.02 1.00 1.00 1.00 1.00 16.02 m3 0% -

A. 77 CB.77 9.90
Excavation 3.09 1.00 1.12 0.70 9.90 23.97 1.00 1.00 1.00 1.00 23.97 m3 0% -
Sand Fill 3.09 1.00 0.50 9.90 15.29 1.00 1.00 1.00 1.00 15.29 m3 0% -
HDPE Installation 9.90 1.00 1.00 1.00 1.00 9.90 m 0% -
Soil Backfill 22.02 1.00 1.00 1.00 1.00 22.02 m3 0% -

A. 78 CB.77 9.90
Excavation 3.09 1.00 1.12 0.70 9.90 23.97 1.00 1.00 1.00 1.00 23.97 m3 0% -
Sand Fill 3.09 1.00 0.50 9.90 15.29 1.00 1.00 1.00 1.00 15.29 m3 0% -
HDPE Installation 9.90 1.00 1.00 1.00 1.00 9.90 m 0% -
Soil Backfill 22.02 1.00 1.00 1.00 1.00 22.02 m3 0% -

A. 79 CB.78 7.20
Excavation 3.09 1.00 1.12 0.70 7.20 17.43 1.00 1.00 1.00 1.00 17.43 m3 0% -
Sand Fill 3.09 1.00 0.50 7.20 11.12 1.00 1.00 1.00 1.00 11.12 m3 0% -
HDPE Installation 7.20 1.00 1.00 1.00 1.00 7.20 m 0% -
Soil Backfill 16.02 1.00 1.00 1.00 1.00 16.02 m3 0% -

A. 80 CB.79 8.20
Excavation 3.09 1.00 1.12 0.70 8.20 19.85 1.00 1.00 1.00 1.00 19.85 m3 0% -
Sand Fill 3.09 1.00 0.50 8.20 12.66 1.00 1.00 1.00 1.00 12.66 m3 0% -
HDPE Installation 8.20 1.00 1.00 1.00 1.00 8.20 m 0% -
Soil Backfill 18.24 1.00 1.00 1.00 1.00 18.24 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
HDPE 200 mm Installation 006 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 81 CB.80 9.90
Excavation 3.09 1.00 1.12 0.70 9.90 23.97 1.00 1.00 1.00 1.00 23.97 m3 0% -
Sand Fill 3.09 1.00 0.50 9.90 15.29 1.00 1.00 1.00 1.00 15.29 m3 0% -
HDPE Installation 9.90 1.00 1.00 1.00 1.00 9.90 m 0% -
Soil Backfill 22.02 1.00 1.00 1.00 1.00 22.02 m3 0% -

A. 82 CB.81 7.20
Excavation 3.09 1.00 1.12 0.70 7.20 17.43 1.00 1.00 1.00 1.00 17.43 m3 0% -
Sand Fill 3.09 1.00 0.50 7.20 11.12 1.00 1.00 1.00 1.00 11.12 m3 0% -
HDPE Installation 7.20 1.00 1.00 1.00 1.00 7.20 m 0% -
Soil Backfill 16.02 1.00 1.00 1.00 1.00 16.02 m3 0% -

A. 83 CB.82 8.20
Excavation 3.09 1.00 1.12 0.70 8.20 19.85 1.00 1.00 1.00 1.00 19.85 m3 0% -
Sand Fill 3.09 1.00 0.50 8.20 12.66 1.00 1.00 1.00 1.00 12.66 m3 0% -
HDPE Installation 8.20 1.00 1.00 1.00 1.00 8.20 m 0% -
Soil Backfill 18.24 1.00 1.00 1.00 1.00 18.24 m3 0% -

A. 84 CB.83 9.90
Excavation 3.09 1.00 1.12 0.70 9.90 23.97 1.00 1.00 1.00 1.00 23.97 m3 0% -
Sand Fill 3.09 1.00 0.50 9.90 15.29 1.00 1.00 1.00 1.00 15.29 m3 0% -
HDPE Installation 9.90 1.00 1.00 1.00 1.00 9.90 m 0% -
Soil Backfill 22.02 1.00 1.00 1.00 1.00 22.02 m3 0% -

A. 85 CB.84 7.20
Excavation 3.09 1.00 1.12 0.70 7.20 17.43 1.00 1.00 1.00 1.00 17.43 m3 0% -
Sand Fill 3.09 1.00 0.50 7.20 11.12 1.00 1.00 1.00 1.00 11.12 m3 0% -
HDPE Installation 7.20 1.00 1.00 1.00 1.00 7.20 m 0% -
Soil Backfill 16.02 1.00 1.00 1.00 1.00 16.02 m3 0% -

A. 86 CB.85 8.20
Excavation 3.09 1.00 1.12 0.70 8.20 19.85 1.00 1.00 1.00 1.00 19.85 m3 0% -
Sand Fill 3.09 1.00 0.50 8.20 12.66 1.00 1.00 1.00 1.00 12.66 m3 0% -
HDPE Installation 8.20 1.00 1.00 1.00 1.00 8.20 m 0% -
Soil Backfill 18.24 1.00 1.00 1.00 1.00 18.24 m3 0% -

A. 87 CB.86 9.90
Excavation 3.09 1.00 1.12 0.70 9.90 23.97 1.00 1.00 1.00 1.00 23.97 m3 0% -
Sand Fill 3.09 1.00 0.50 9.90 15.29 1.00 1.00 1.00 1.00 15.29 m3 0% -
HDPE Installation 9.90 1.00 1.00 1.00 1.00 9.90 m 0% -
Soil Backfill 22.02 1.00 1.00 1.00 1.00 22.02 m3 0% -

A. 88 CB.87 7.90
Excavation 3.09 1.00 1.12 0.70 7.90 19.13 1.00 1.00 1.00 1.00 19.13 m3 0% -
Sand Fill 3.09 1.00 0.50 7.90 12.20 1.00 1.00 1.00 1.00 12.20 m3 0% -
HDPE Installation 7.90 1.00 1.00 1.00 1.00 7.90 m 0% -
Soil Backfill 17.58 1.00 1.00 1.00 1.00 17.58 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
HDPE 200 mm Installation 006 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 89 CB.88 8.80
Excavation 3.09 1.00 1.12 0.70 8.80 21.30 1.00 1.00 1.00 1.00 21.30 m3 0% -
Sand Fill 3.09 1.00 0.50 8.80 13.59 1.00 1.00 1.00 1.00 13.59 m3 0% -
HDPE Installation 8.80 1.00 1.00 1.00 1.00 8.80 m 0% -
Soil Backfill 19.58 1.00 1.00 1.00 1.00 19.58 m3 0% -

A. 90 CB.89 5.50
Excavation 3.09 1.00 1.12 0.70 5.50 13.32 1.00 1.00 1.00 1.00 13.32 m3 0% -
Sand Fill 3.09 1.00 0.50 5.50 8.49 1.00 1.00 1.00 1.00 8.49 m3 0% -
HDPE Installation 5.50 1.00 1.00 1.00 1.00 5.50 m 0% -
Soil Backfill 12.24 1.00 1.00 1.00 1.00 12.24 m3 0% -

A. 91 CB.90 2.70
Excavation 3.09 1.00 1.12 0.70 2.70 6.54 1.00 1.00 1.00 1.00 6.54 m3 0% -
Sand Fill 3.09 1.00 0.50 2.70 4.17 1.00 1.00 1.00 1.00 4.17 m3 0% -
HDPE Installation 2.70 1.00 1.00 1.00 1.00 2.70 m 0% -
Soil Backfill 6.01 1.00 1.00 1.00 1.00 6.01 m3 0% -

A. 92 CB.91 10.60
Excavation 3.09 1.00 1.12 0.70 10.60 25.66 1.00 1.00 1.00 1.00 25.66 m3 0% -
Sand Fill 3.09 1.00 0.50 10.60 16.37 1.00 1.00 1.00 1.00 16.37 m3 0% -
HDPE Installation 10.60 1.00 1.00 1.00 1.00 10.60 m 0% -
Soil Backfill 23.58 1.00 1.00 1.00 1.00 23.58 m3 0% -

A. 93 CB.92 7.70
Excavation 3.09 1.00 1.12 0.70 7.70 18.64 1.00 1.00 1.00 1.00 18.64 m3 0% -
Sand Fill 3.09 1.00 0.50 7.70 11.89 1.00 1.00 1.00 1.00 11.89 m3 0% -
HDPE Installation 7.70 1.00 1.00 1.00 1.00 7.70 m 0% -
Soil Backfill 17.13 1.00 1.00 1.00 1.00 17.13 m3 0% -

A. 94 CB.93 3.50
Excavation 3.09 1.00 1.12 0.70 3.50 8.47 1.00 1.00 1.00 1.00 8.47 m3 0% -
Sand Fill 3.09 1.00 0.50 3.50 5.40 1.00 1.00 1.00 1.00 5.40 m3 0% -
HDPE Installation 3.50 1.00 1.00 1.00 1.00 3.50 m 0% -
Soil Backfill 7.79 1.00 1.00 1.00 1.00 7.79 m3 0% -

A. 95 CB.94 3.70
Excavation 3.09 1.00 1.12 0.70 3.70 8.96 1.00 1.00 1.00 1.00 8.96 m3 0% -
Sand Fill 3.09 1.00 0.50 3.70 5.71 1.00 1.00 1.00 1.00 5.71 m3 0% -
HDPE Installation 3.70 1.00 1.00 1.00 1.00 3.70 m 0% -
Soil Backfill 8.23 1.00 1.00 1.00 1.00 8.23 m3 0% -

A. 96 CB.B4 - MH.06 28.80


Excavation 3.09 1.00 1.12 0.70 28.80 69.72 1.00 1.00 1.00 1.00 69.72 m3 0% -
Sand Fill 3.09 1.00 0.50 28.80 44.47 1.00 1.00 1.00 1.00 44.47 m3 0% -
HDPE Installation 28.80 1.00 1.00 1.00 1.00 28.80 m 0% -
Soil Backfill 64.07 1.00 1.00 1.00 1.00 64.07 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
HDPE 200 mm Installation 006 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 97 CB.A6 - MH.17 7.70
Excavation 3.09 1.00 1.12 0.70 7.70 18.64 1.00 1.00 1.00 1.00 18.64 m3 0% -
Sand Fill 3.09 1.00 0.50 7.70 11.89 1.00 1.00 1.00 1.00 11.89 m3 0% -
HDPE Installation 7.70 1.00 1.00 1.00 1.00 7.70 m 0% -
Soil Backfill 17.13 1.00 1.00 1.00 1.00 17.13 m3 0% -

A. 98 CB.A3 - MH.16 8.50


Excavation 3.09 1.00 1.12 0.70 8.50 20.58 1.00 1.00 1.00 1.00 20.58 m3 0% -
Sand Fill 3.09 1.00 0.50 8.50 13.12 1.00 1.00 1.00 1.00 13.12 m3 0% -
HDPE Installation 8.50 1.00 1.00 1.00 1.00 8.50 m 0% -
Soil Backfill 18.91 1.00 1.00 1.00 1.00 18.91 m3 0% -

A. 99 CB.A2 - MH.15 10.40


Excavation 3.09 1.00 1.12 0.70 10.40 25.18 1.00 1.00 1.00 1.00 25.18 m3 0% -
Sand Fill 3.09 1.00 0.50 10.40 16.06 1.00 1.00 1.00 1.00 16.06 m3 0% -
HDPE Installation 10.40 1.00 1.00 1.00 1.00 10.40 m 0% -
Soil Backfill 23.14 1.00 1.00 1.00 1.00 23.14 m3 0% -

A. 100 CB.B2 - MH.15 6.10


Excavation 3.09 1.00 1.12 0.70 6.10 14.77 1.00 1.00 1.00 1.00 14.77 m3 0% -
Sand Fill 3.09 1.00 0.50 6.10 9.42 1.00 1.00 1.00 1.00 9.42 m3 0% -
HDPE Installation 6.10 1.00 1.00 1.00 1.00 6.10 m 0% -
Soil Backfill 13.57 1.00 1.00 1.00 1.00 13.57 m3 0% -

A. 101 CB.A8 - MH.04 12.70


Excavation 3.09 1.00 1.12 0.70 12.70 30.75 1.00 1.00 1.00 1.00 30.75 m3 0% -
Sand Fill 3.09 1.00 0.50 12.70 19.61 1.00 1.00 1.00 1.00 19.61 m3 0% -
HDPE Installation 12.70 1.00 1.00 1.00 1.00 12.70 m 0% -
Soil Backfill 28.25 1.00 1.00 1.00 1.00 28.25 m3 0% -

A. 102 CB.A7 - MH.21 14.20


Excavation 3.09 1.00 1.12 0.70 14.20 34.38 1.00 1.00 1.00 1.00 34.38 m3 0% -
Sand Fill 3.09 1.00 0.50 14.20 21.92 1.00 1.00 1.00 1.00 21.92 m3 0% -
HDPE Installation 14.20 1.00 1.00 1.00 1.00 14.20 m 0% -
Soil Backfill 31.59 1.00 1.00 1.00 1.00 31.59 m3 0% -

A. 103 CB.B3 - MH.21 4.20


Excavation 3.09 1.00 1.12 0.70 4.20 10.17 1.00 1.00 1.00 1.00 10.17 m3 0% -
Sand Fill 3.09 1.00 0.50 4.20 6.48 1.00 1.00 1.00 1.00 6.48 m3 0% -
HDPE Installation 4.20 1.00 1.00 1.00 1.00 4.20 m 0% -
Soil Backfill 9.34 1.00 1.00 1.00 1.00 9.34 m3 0% -

A. 104 CB.B1 - MH.02 12.00


Excavation 3.09 1.00 1.12 0.70 12.00 29.05 1.00 1.00 1.00 1.00 29.05 m3 0% -
Sand Fill 3.09 1.00 0.50 12.00 18.53 1.00 1.00 1.00 1.00 18.53 m3 0% -
HDPE Installation 12.00 1.00 1.00 1.00 1.00 12.00 m 0% -
Soil Backfill 26.70 1.00 1.00 1.00 1.00 26.70 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
HDPE 200 mm Installation 006 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 105 CB.A1 - MH.03 14.50
Excavation 3.09 1.00 1.12 0.70 14.50 35.10 1.00 1.00 1.00 1.00 35.10 m3 0% -
Sand Fill 3.09 1.00 0.50 14.50 22.39 1.00 1.00 1.00 1.00 22.39 m3 0% -
HDPE Installation 14.50 1.00 1.00 1.00 1.00 14.50 m 0% -
Soil Backfill 32.26 1.00 1.00 1.00 1.00 32.26 m3 0% -

A. 106 CB.A4 - Outside 2.50


Excavation 3.09 1.00 1.12 0.70 2.50 6.05 1.00 1.00 1.00 1.00 6.05 m3 0% -
Sand Fill 3.09 1.00 0.50 2.50 3.86 1.00 1.00 1.00 1.00 3.86 m3 0% -
HDPE Installation 2.50 1.00 1.00 1.00 1.00 2.50 m 0% -
Soil Backfill 5.56 1.00 1.00 1.00 1.00 5.56 m3 0% -

A. 107 CB.A5 - Outside 2.50


Excavation 3.09 1.00 1.12 0.70 2.50 6.05 1.00 1.00 1.00 1.00 6.05 m3 0% -
Sand Fill 3.09 1.00 0.50 2.50 3.86 1.00 1.00 1.00 1.00 3.86 m3 0% -
HDPE Installation 2.50 1.00 1.00 1.00 1.00 2.50 m 0% -
Soil Backfill 5.56 1.00 1.00 1.00 1.00 5.56 m3 0% -

A. 108 GH-1 1.70


Excavation 3.09 1.00 1.12 0.70 1.70 4.12 1.00 1.00 1.00 1.00 4.12 m3 0% -
Sand Fill 3.09 1.00 0.50 1.70 2.62 1.00 1.00 1.00 1.00 2.62 m3 0% -
HDPE Installation 1.70 1.00 1.00 1.00 1.00 1.70 m 0% -
Soil Backfill 3.78 1.00 1.00 1.00 1.00 3.78 m3 0% -

A. 109 GH-2 1.70


Excavation 3.09 1.00 1.12 0.70 1.70 4.12 1.00 1.00 1.00 1.00 4.12 m3 0% -
Sand Fill 3.09 1.00 0.50 1.70 2.62 1.00 1.00 1.00 1.00 2.62 m3 0% -
HDPE Installation 1.70 1.00 1.00 1.00 1.00 1.70 m 0% -
Soil Backfill 3.78 1.00 1.00 1.00 1.00 3.78 m3 0% -

A. 110 GH-3 1.70


Excavation 3.09 1.00 1.12 0.70 1.70 4.12 1.00 1.00 1.00 1.00 4.12 m3 0% -
Sand Fill 3.09 1.00 0.50 1.70 2.62 1.00 1.00 1.00 1.00 2.62 m3 0% -
HDPE Installation 1.70 1.00 1.00 1.00 1.00 1.70 m 0% -
Soil Backfill 3.78 1.00 1.00 1.00 1.00 3.78 m3 0% -

A. 111 GH-4 - DELETED -


Excavation 3.09 1.00 1.12 0.70 - - 1.00 1.00 1.00 1.00 - m3 0% -
Sand Fill 3.09 1.00 0.50 - - 1.00 1.00 1.00 1.00 - m3 0% -
HDPE Installation - 1.00 1.00 1.00 1.00 - m 0% -
Soil Backfill - 1.00 1.00 1.00 1.00 - m3 0% -

A. 112 GH-5 3.30


Excavation 3.09 1.00 1.12 0.70 3.30 7.99 1.00 1.00 1.00 1.00 7.99 m3 0% -
Sand Fill 3.09 1.00 0.50 3.30 5.10 1.00 1.00 1.00 1.00 5.10 m3 0% -
HDPE Installation 3.30 1.00 1.00 1.00 1.00 3.30 m 0% -
Soil Backfill 7.34 1.00 1.00 1.00 1.00 7.34 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
HDPE 200 mm Installation 006 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 113 GH-6 6.40
Excavation 3.09 1.00 1.12 0.70 6.40 15.49 1.00 1.00 1.00 1.00 15.49 m3 0% -
Sand Fill 3.09 1.00 0.50 6.40 9.88 1.00 1.00 1.00 1.00 9.88 m3 0% -
HDPE Installation 6.40 1.00 1.00 1.00 1.00 6.40 m 0% -
Soil Backfill 14.24 1.00 1.00 1.00 1.00 14.24 m3 0% -

A. 114 GH-7 10.80


Excavation 3.09 1.00 1.12 0.70 10.80 26.15 1.00 1.00 1.00 1.00 26.15 m3 0% -
Sand Fill 3.09 1.00 0.50 10.80 16.68 1.00 1.00 1.00 1.00 16.68 m3 0% -
HDPE Installation 10.80 1.00 1.00 1.00 1.00 10.80 m 0% -
Soil Backfill 24.03 1.00 1.00 1.00 1.00 24.03 m3 0% -

A. 115 GH-8 5.10


Excavation 3.09 1.00 1.12 0.70 5.10 12.35 1.00 1.00 1.00 1.00 12.35 m3 0% -
Sand Fill 3.09 1.00 0.50 5.10 7.87 1.00 1.00 1.00 1.00 7.87 m3 0% -
HDPE Installation 5.10 1.00 1.00 1.00 1.00 5.10 m 0% -
Soil Backfill 11.35 1.00 1.00 1.00 1.00 11.35 m3 0% -

A. 116 GH-9 3.20


Excavation 3.09 1.00 1.12 0.70 3.20 7.75 1.00 1.00 1.00 1.00 7.75 m3 0% -
Sand Fill 3.09 1.00 0.50 3.20 4.94 1.00 1.00 1.00 1.00 4.94 m3 0% -
HDPE Installation 3.20 1.00 1.00 1.00 1.00 3.20 m 0% -
Soil Backfill 7.12 1.00 1.00 1.00 1.00 7.12 m3 0% -

A. 117 GH-10 8.50


Excavation 3.09 1.00 1.12 0.70 8.50 20.58 1.00 1.00 1.00 1.00 20.58 m3 0% -
Sand Fill 3.09 1.00 0.50 8.50 13.12 1.00 1.00 1.00 1.00 13.12 m3 0% -
HDPE Installation 8.50 1.00 1.00 1.00 1.00 8.50 m 0% -
Soil Backfill 18.91 1.00 1.00 1.00 1.00 18.91 m3 0% -

A. 118 GH-11 - DELETED -


Excavation 3.09 1.00 1.12 0.70 - - 1.00 1.00 1.00 1.00 - m3 0% -
Sand Fill 3.09 1.00 0.50 - - 1.00 1.00 1.00 1.00 - m3 0% -
HDPE Installation - 1.00 1.00 1.00 1.00 - m 0% -
Soil Backfill - 1.00 1.00 1.00 1.00 - m3 0% -

A. 119 GH-12 13.10


Excavation 3.09 1.00 1.12 0.70 13.10 31.71 1.00 1.00 1.00 1.00 31.71 m3 0% -
Sand Fill 3.09 1.00 0.50 13.10 20.23 1.00 1.00 1.00 1.00 20.23 m3 0% -
HDPE Installation 13.10 1.00 1.00 1.00 1.00 13.10 m 0% -
Soil Backfill 29.14 1.00 1.00 1.00 1.00 29.14 m3 0% -

A. 120 GH-13 12.50


Excavation 3.09 1.00 1.12 0.70 12.50 30.26 1.00 1.00 1.00 1.00 30.26 m3 0% -
Sand Fill 3.09 1.00 0.50 12.50 19.30 1.00 1.00 1.00 1.00 19.30 m3 0% -
HDPE Installation 12.50 1.00 1.00 1.00 1.00 12.50 m 0% -
Soil Backfill 27.81 1.00 1.00 1.00 1.00 27.81 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
HDPE 200 mm Installation 006 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 121 GH-14 11.70
Excavation 3.09 1.00 1.12 0.70 11.70 28.33 1.00 1.00 1.00 1.00 28.33 m3 0% -
Sand Fill 3.09 1.00 0.50 11.70 18.06 1.00 1.00 1.00 1.00 18.06 m3 0% -
HDPE Installation 11.70 1.00 1.00 1.00 1.00 11.70 m 0% -
Soil Backfill 26.03 1.00 1.00 1.00 1.00 26.03 m3 0% -

B HDPE FOR SEWAGE (SECTION 1)


B. 1 SM.A1 - SM.01 2.20
Excavation Sewage 3.09 1.00 1.12 0.70 2.20 5.33 1.00 1.00 1.00 1.00 5.33 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 2.20 3.40 1.00 1.00 1.00 1.00 3.40 m3 0% -
HDPE Installation Sewage 2.20 1.00 1.00 1.00 1.00 2.20 m 0% -
Soil Backfill Sewage 4.89 1.00 1.00 1.00 1.00 4.89 m3 0% -

B. 2 SM.01 - SM.02 22.60


Excavation Sewage 3.09 1.00 1.12 0.70 22.60 54.71 1.00 1.00 1.00 1.00 54.71 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 22.60 34.89 1.00 1.00 1.00 1.00 34.89 m3 0% -
HDPE Installation Sewage 22.60 1.00 1.00 1.00 1.00 22.60 m 0% -
Soil Backfill Sewage 50.28 1.00 1.00 1.00 1.00 50.28 m3 0% -

B. 3 SM.A2 - SM.13 2.20


Excavation Sewage 3.09 1.00 1.12 0.70 2.20 5.33 1.00 1.00 1.00 1.00 5.33 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 2.20 3.40 1.00 1.00 1.00 1.00 3.40 m3 0% -
HDPE Installation Sewage 2.20 1.00 1.00 1.00 1.00 2.20 m 0% -
Soil Backfill Sewage 4.89 1.00 1.00 1.00 1.00 4.89 m3 0% -

B. 4 SM.13 - SM.02 13.00


Excavation Sewage 3.09 1.00 1.12 0.70 13.00 31.47 1.00 1.00 1.00 1.00 31.47 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 13.00 20.07 1.00 1.00 1.00 1.00 20.07 m3 0% -
HDPE Installation Sewage 13.00 1.00 1.00 1.00 1.00 13.00 m 0% -
Soil Backfill Sewage 28.92 1.00 1.00 1.00 1.00 28.92 m3 0% -

B. 5 SM.02 - SM.03 11.40


Excavation Sewage 3.09 1.00 1.12 0.70 11.40 27.60 1.00 1.00 1.00 1.00 27.60 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 11.40 17.60 1.00 1.00 1.00 1.00 17.60 m3 0% -
HDPE Installation Sewage 11.40 1.00 1.00 1.00 1.00 11.40 m 0% -
Soil Backfill Sewage 25.36 1.00 1.00 1.00 1.00 25.36 m3 0% -

B. 6 SM.03 - SM.04 45.80


Excavation Sewage 3.09 1.00 1.12 0.70 45.80 110.88 1.00 1.00 1.00 1.00 110.88 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 45.80 70.72 1.00 1.00 1.00 1.00 70.72 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
HDPE 200 mm Installation 006 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
HDPE Installation Sewage 45.80 1.00 1.00 1.00 1.00 45.80 m 0% -
Soil Backfill Sewage 101.89 1.00 1.00 1.00 1.00 101.89 m3 0% -

B. 7 SM.04 - SM.05 12.80


Excavation Sewage 3.09 1.00 1.12 0.70 12.80 30.99 1.00 1.00 1.00 1.00 30.99 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 12.80 19.76 1.00 1.00 1.00 1.00 19.76 m3 0% -
HDPE Installation Sewage 12.80 1.00 1.00 1.00 1.00 12.80 m 0% -
Soil Backfill Sewage 28.48 1.00 1.00 1.00 1.00 28.48 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
HDPE 200 mm Installation 006 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
B. 8 SM.05 - SM.06 5.30
Excavation Sewage 3.09 1.00 1.12 0.70 5.30 12.83 1.00 1.00 1.00 1.00 12.83 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 5.30 8.18 1.00 1.00 1.00 1.00 8.18 m3 0% -
HDPE Installation Sewage 5.30 1.00 1.00 1.00 1.00 5.30 m 0% -
Soil Backfill Sewage 11.79 1.00 1.00 1.00 1.00 11.79 m3 0% -

B. 9 SM.06 - SM.07 18.70


Excavation Sewage 3.09 1.00 1.12 0.70 18.70 45.27 1.00 1.00 1.00 1.00 45.27 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 18.70 28.87 1.00 1.00 1.00 1.00 28.87 m3 0% -
HDPE Installation Sewage 18.70 1.00 1.00 1.00 1.00 18.70 m 0% -
Soil Backfill Sewage 41.60 1.00 1.00 1.00 1.00 41.60 m3 0% -

B. 10 SM.14 - SM.07 9.20


Excavation Sewage 3.09 1.00 1.12 0.70 9.20 22.27 1.00 1.00 1.00 1.00 22.27 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 9.20 14.20 1.00 1.00 1.00 1.00 14.20 m3 0% -
HDPE Installation Sewage 9.20 1.00 1.00 1.00 1.00 9.20 m 0% -
Soil Backfill Sewage 20.47 1.00 1.00 1.00 1.00 20.47 m3 0% -

B. 11 SM.B3 - SM.14 2.00


Excavation Sewage 3.09 1.00 1.12 0.70 2.00 4.84 1.00 1.00 1.00 1.00 4.84 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 2.00 3.09 1.00 1.00 1.00 1.00 3.09 m3 0% -
HDPE Installation Sewage 2.00 1.00 1.00 1.00 1.00 2.00 m 0% -
Soil Backfill Sewage 4.45 1.00 1.00 1.00 1.00 4.45 m3 0% -

B. 12 SM.07 - SM.08 35.00


Excavation Sewage 3.09 1.00 1.12 0.70 35.00 84.73 1.00 1.00 1.00 1.00 84.73 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 35.00 54.04 1.00 1.00 1.00 1.00 54.04 m3 0% -
HDPE Installation Sewage 35.00 1.00 1.00 1.00 1.00 35.00 m 0% -
Soil Backfill Sewage 77.87 1.00 1.00 1.00 1.00 77.87 m3 0% -

B. 13 SM.08 - SM.09 33.40


Excavation Sewage 3.09 1.00 1.12 0.70 33.40 80.86 1.00 1.00 1.00 1.00 80.86 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 33.40 51.57 1.00 1.00 1.00 1.00 51.57 m3 0% -
HDPE Installation Sewage 33.40 1.00 1.00 1.00 1.00 33.40 m 0% -
Soil Backfill Sewage 74.31 1.00 1.00 1.00 1.00 74.31 m3 0% -

B. 14 SM.09 - SM.10 27.00


Excavation Sewage 3.09 1.00 1.12 0.70 27.00 65.37 1.00 1.00 1.00 1.00 65.37 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 27.00 41.69 1.00 1.00 1.00 1.00 41.69 m3 0% -
HDPE Installation Sewage 27.00 1.00 1.00 1.00 1.00 27.00 m 0% -
Soil Backfill Sewage 60.07 1.00 1.00 1.00 1.00 60.07 m3 0% -

B. 15 SM.B4 - SM.15 3.00


Excavation Sewage 3.09 1.00 1.12 0.70 3.00 7.26 1.00 1.00 1.00 1.00 7.26 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 3.00 4.63 1.00 1.00 1.00 1.00 4.63 m3 0% -
HDPE Installation Sewage 3.00 1.00 1.00 1.00 1.00 3.00 m 0% -
Soil Backfill Sewage 6.67 1.00 1.00 1.00 1.00 6.67 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
HDPE 200 mm Installation 006 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
B. 16 SM.15 - SM.11 14.40
Excavation Sewage 3.09 1.00 1.12 0.70 14.40 34.86 1.00 1.00 1.00 1.00 34.86 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 14.40 22.23 1.00 1.00 1.00 1.00 22.23 m3 0% -
HDPE Installation Sewage 14.40 1.00 1.00 1.00 1.00 14.40 m 0% -
Soil Backfill Sewage 32.04 1.00 1.00 1.00 1.00 32.04 m3 0% -

B. 17 SM.B5 - SM.18 20.00


Excavation Sewage 3.09 1.00 1.12 0.70 20.00 48.42 1.00 1.00 1.00 1.00 48.42 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 20.00 30.88 1.00 1.00 1.00 1.00 30.88 m3 0% -
HDPE Installation Sewage 20.00 1.00 1.00 1.00 1.00 20.00 m 0% -
Soil Backfill Sewage 44.49 1.00 1.00 1.00 1.00 44.49 m3 0% -

B. 18 SM.19 - SM.11 28.00


Excavation Sewage 3.09 1.00 1.12 0.70 28.00 67.79 1.00 1.00 1.00 1.00 67.79 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 28.00 43.23 1.00 1.00 1.00 1.00 43.23 m3 0% -
HDPE Installation Sewage 28.00 1.00 1.00 1.00 1.00 28.00 m 0% -
Soil Backfill Sewage 62.29 1.00 1.00 1.00 1.00 62.29 m3 0% -

B. 19 SM.11 - SM.10 6.50


Excavation Sewage 3.09 1.00 1.12 0.70 6.50 15.74 1.00 1.00 1.00 1.00 15.74 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 6.50 10.04 1.00 1.00 1.00 1.00 10.04 m3 0% -
HDPE Installation Sewage 6.50 1.00 1.00 1.00 1.00 6.50 m 0% -
Soil Backfill Sewage 14.46 1.00 1.00 1.00 1.00 14.46 m3 0% -

B. 20 SM.10 - SM.12 9.00


Excavation Sewage 3.09 1.00 1.12 0.70 9.00 21.79 1.00 1.00 1.00 1.00 21.79 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 9.00 13.90 1.00 1.00 1.00 1.00 13.90 m3 0% -
HDPE Installation Sewage 9.00 1.00 1.00 1.00 1.00 9.00 m 0% -
Soil Backfill Sewage 20.02 1.00 1.00 1.00 1.00 20.02 m3 0% -

B. 21 SM.B6 - SM.B7 31.40


Excavation Sewage 3.09 1.00 1.12 0.70 31.40 76.02 1.00 1.00 1.00 1.00 76.02 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 31.40 48.48 1.00 1.00 1.00 1.00 48.48 m3 0% -
HDPE Installation Sewage 31.40 1.00 1.00 1.00 1.00 31.40 m 0% -
Soil Backfill Sewage 69.86 1.00 1.00 1.00 1.00 69.86 m3 0% -

B. 22 SM.B7 - SM.B8 13.30


Excavation Sewage 3.09 1.00 1.12 0.70 13.30 32.20 1.00 1.00 1.00 1.00 32.20 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 13.30 20.54 1.00 1.00 1.00 1.00 20.54 m3 0% -
HDPE Installation Sewage 13.30 1.00 1.00 1.00 1.00 13.30 m 0% -
Soil Backfill Sewage 29.59 1.00 1.00 1.00 1.00 29.59 m3 0% -

B. 23 SM.B8 - SM.16 2.00


Excavation Sewage 3.09 1.00 1.12 0.70 2.00 4.84 1.00 1.00 1.00 1.00 4.84 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 2.00 3.09 1.00 1.00 1.00 1.00 3.09 m3 0% -
HDPE Installation Sewage 2.00 1.00 1.00 1.00 1.00 2.00 m 0% -
Soil Backfill Sewage 4.45 1.00 1.00 1.00 1.00 4.45 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
HDPE 200 mm Installation 006 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
B. 24 SM.16 - SM.12 4.20
Excavation Sewage 3.09 1.00 1.12 0.70 4.20 10.17 1.00 1.00 1.00 1.00 10.17 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 4.20 6.48 1.00 1.00 1.00 1.00 6.48 m3 0% -
HDPE Installation Sewage 4.20 1.00 1.00 1.00 1.00 4.20 m 0% -
Soil Backfill Sewage 9.34 1.00 1.00 1.00 1.00 9.34 m3 0% -

B. 25 SM.12 - SEWAGE 4.70


Excavation Sewage 3.09 1.00 1.12 0.70 4.70 11.38 1.00 1.00 1.00 1.00 11.38 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 4.70 7.26 1.00 1.00 1.00 1.00 7.26 m3 0% -
HDPE Installation Sewage 4.70 1.00 1.00 1.00 1.00 4.70 m 0% -
Soil Backfill Sewage 10.46 1.00 1.00 1.00 1.00 10.46 m3 0% -

C HDPE FOR SEWAGE (SECTION 2)


C. 1 SMH.01 - SMH.02 24.80
Excavation Sewage 3.09 1.00 1.12 0.70 24.80 60.04 1.00 1.00 1.00 1.00 60.04 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 24.80 38.29 1.00 1.00 1.00 1.00 38.29 m3 0% -
HDPE Installation Sewage 24.80 1.00 1.00 1.00 1.00 24.80 m 0% -
Soil Backfill Sewage 55.17 1.00 1.00 1.00 1.00 55.17 m3 0% -

C. 2 SMH.02 - SMH.03 18.00


Excavation Sewage 3.09 1.00 1.12 0.70 18.00 43.58 1.00 1.00 1.00 1.00 43.58 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 18.00 27.79 1.00 1.00 1.00 1.00 27.79 m3 0% -
HDPE Installation Sewage 18.00 1.00 1.00 1.00 1.00 18.00 m 0% -
Soil Backfill Sewage 40.05 1.00 1.00 1.00 1.00 40.05 m3 0% -

C. 3 SMH.10 - SMH.03 4.80


Excavation Sewage 3.09 1.00 1.12 0.70 4.80 11.62 1.00 1.00 1.00 1.00 11.62 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 4.80 7.41 1.00 1.00 1.00 1.00 7.41 m3 0% -
HDPE Installation Sewage 4.80 1.00 1.00 1.00 1.00 4.80 m 0% -
Soil Backfill Sewage 10.68 1.00 1.00 1.00 1.00 10.68 m3 0% -

C. 4 SMH.03 - SMH.04 21.70


Excavation Sewage 3.09 1.00 1.12 0.70 21.70 52.54 1.00 1.00 1.00 1.00 52.54 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 21.70 33.50 1.00 1.00 1.00 1.00 33.50 m3 0% -
HDPE Installation Sewage 21.70 1.00 1.00 1.00 1.00 21.70 m 0% -
Soil Backfill Sewage 48.28 1.00 1.00 1.00 1.00 48.28 m3 0% -

C. 5 SMH.11 - SMH.12 21.20


Excavation Sewage 3.09 1.00 1.12 0.70 21.20 51.33 1.00 1.00 1.00 1.00 51.33 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 21.20 32.73 1.00 1.00 1.00 1.00 32.73 m3 0% -
HDPE Installation Sewage 21.20 1.00 1.00 1.00 1.00 21.20 m 0% -
Soil Backfill Sewage 47.16 1.00 1.00 1.00 1.00 47.16 m3 0% -

C. 6 SMH.12 - SMH.13 8.00


Excavation Sewage 3.09 1.00 1.12 0.70 8.00 19.37 1.00 1.00 1.00 1.00 19.37 m3 100% 19.37
Sand Fill Sewage 3.09 1.00 0.50 8.00 12.35 1.00 1.00 1.00 1.00 12.35 m3 0% -
HDPE Installation Sewage 8.00 1.00 1.00 1.00 1.00 8.00 m 100% 8.00
Soil Backfill Sewage 17.80 1.00 1.00 1.00 1.00 17.80 m3 100% 17.80
Progress Calculation PROGRESS CALCULATION FORM Progress Date
HDPE 200 mm Installation 006 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
C. 7 SMH.13 - SMH.04 4.10
Excavation Sewage 3.09 1.00 1.12 0.70 4.10 9.93 1.00 1.00 1.00 1.00 9.93 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 4.10 6.33 1.00 1.00 1.00 1.00 6.33 m3 0% -
HDPE Installation Sewage 4.10 1.00 1.00 1.00 1.00 4.10 m 0% -
Soil Backfill Sewage 9.12 1.00 1.00 1.00 1.00 9.12 m3 0% -

C. 8 SMH.04 - SMH.05 20.00


Excavation Sewage 3.09 1.00 1.12 0.70 20.00 48.42 1.00 1.00 1.00 1.00 48.42 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 20.00 30.88 1.00 1.00 1.00 1.00 30.88 m3 0% -
HDPE Installation Sewage 20.00 1.00 1.00 1.00 1.00 20.00 m 0% -
Soil Backfill Sewage 44.49 1.00 1.00 1.00 1.00 44.49 m3 0% -

C. 9 SMH.05 - SMH.06 23.20


Excavation Sewage 3.09 1.00 1.12 0.70 23.20 56.17 1.00 1.00 1.00 1.00 56.17 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 23.20 35.82 1.00 1.00 1.00 1.00 35.82 m3 0% -
HDPE Installation Sewage 23.20 1.00 1.00 1.00 1.00 23.20 m 0% -
Soil Backfill Sewage 51.61 1.00 1.00 1.00 1.00 51.61 m3 0% -

C. 10 SMH.06 - SMH.07 30.00


Excavation Sewage 3.09 1.00 1.12 0.70 30.00 72.63 1.00 1.00 1.00 1.00 72.63 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 30.00 46.32 1.00 1.00 1.00 1.00 46.32 m3 0% -
HDPE Installation Sewage 30.00 1.00 1.00 1.00 1.00 30.00 m 0% -
Soil Backfill Sewage 66.74 1.00 1.00 1.00 1.00 66.74 m3 0% -

C. 11 SMH.07 - SMH.09 34.90


Excavation Sewage 3.09 1.00 1.12 0.70 34.90 84.49 1.00 1.00 1.00 1.00 84.49 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 34.90 53.89 1.00 1.00 1.00 1.00 53.89 m3 0% -
HDPE Installation Sewage 34.90 1.00 1.00 1.00 1.00 34.90 m 0% -
Soil Backfill Sewage 77.64 1.00 1.00 1.00 1.00 77.64 m3 0% -

C. 12 SMH.08 - SMH.09 8.80


Excavation Sewage 3.09 1.00 1.12 0.70 8.80 21.30 1.00 1.00 1.00 1.00 21.30 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 8.80 13.59 1.00 1.00 1.00 1.00 13.59 m3 0% -
HDPE Installation Sewage 8.80 1.00 1.00 1.00 1.00 8.80 m 0% -
Soil Backfill Sewage 19.58 1.00 1.00 1.00 1.00 19.58 m3 0% -

C. 13 SMH.14 - SMH.15 14.40


Excavation Sewage 3.09 1.00 1.12 0.70 14.40 34.86 1.00 1.00 1.00 1.00 34.86 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 14.40 22.23 1.00 1.00 1.00 1.00 22.23 m3 0% -
HDPE Installation Sewage 14.40 1.00 1.00 1.00 1.00 14.40 m 0% -
Soil Backfill Sewage 32.04 1.00 1.00 1.00 1.00 32.04 m3 0% -

C. 14 SMH.15 - SMH.09 25.90


Excavation Sewage 3.09 1.00 1.12 0.70 25.90 62.70 1.00 1.00 1.00 1.00 62.70 m3 100% 62.70
Sand Fill Sewage 3.09 1.00 0.50 25.90 39.99 1.00 1.00 1.00 1.00 39.99 m3 0% -
HDPE Installation Sewage 25.90 1.00 1.00 1.00 1.00 25.90 m 100% 25.90
Soil Backfill Sewage 57.62 1.00 1.00 1.00 1.00 57.62 m3 100% 57.62
Progress Calculation PROGRESS CALCULATION FORM Progress Date
HDPE 200 mm Installation 006 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
D HDPE FOR SEWAGE (SECTION 3)
C. 1 SMH.01 - SMH.02 8.70
Excavation Sewage 3.09 1.00 1.12 0.70 8.70 21.06 1.00 1.00 1.00 1.00 21.06 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 8.70 13.43 1.00 1.00 1.00 1.00 13.43 m3 0% -
HDPE Installation Sewage 8.70 1.00 1.00 1.00 1.00 8.70 m 0% -
Soil Backfill Sewage 19.36 1.00 1.00 1.00 1.00 19.36 m3 0% -

C. 2 SMH.02 - SMH.03 18.20


Excavation Sewage 3.09 1.00 1.12 0.70 18.20 44.06 1.00 1.00 1.00 1.00 44.06 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 18.20 28.10 1.00 1.00 1.00 1.00 28.10 m3 0% -
HDPE Installation Sewage 18.20 1.00 1.00 1.00 1.00 18.20 m 0% -
Soil Backfill Sewage 40.49 1.00 1.00 1.00 1.00 40.49 m3 0% -

C. 3 SMH.02 - SEWAGE 53.00


Excavation Sewage 3.09 1.00 1.12 0.70 53.00 128.31 1.00 1.00 1.00 1.00 128.31 m3 0% -
Sand Fill Sewage 3.09 1.00 0.50 53.00 81.83 1.00 1.00 1.00 1.00 81.83 m3 0% -
HDPE Installation Sewage 53.00 1.00 1.00 1.00 1.00 53.00 m 0% -
Soil Backfill Sewage 117.91 1.00 1.00 1.00 1.00 117.91 m3 0% -

RECAP FOR MAIN PROGRESS (BOQ ITEMS) Notes :


Progress Date 1. The Quantity Calculation is Still PT. SSA Version, It is Not Yet Together Measurement With KINE's Quantity Surveyor.
31/08/2023 2. Quantity Calculation Based On Approved Shop Drawing and Lotte Chemical E & C For Construction Drawing.

Progress Progress
No. Description Unit Total Quantity Remarks
Quantity Percentages
1 Excavation m3 2,181.80 - 0.0000%
2 Sand Fill m3 1,391.45 - 0.0000%
3 HDPE Installation m 901.20 - 0.0000%
4 Soil Backfill m3 2,004.94 - 0.0000%
5 Excavation Sewage m3 1,735.37 82.07 4.7294% ARITMATH CHECKING
6 Sand Fill Sewage m3 1,106.74 - 0.0000% RECAP 11,632.99
7 HDPE Installation Sewage m 716.80 33.90 4.7294% BREAKDOWN 11,632.99
8 Soil Backfill Sewage m3 1,594.70 75.42 4.7294% IF ZERO = OK! -

GLOBAL PROGRESS FOR HDPE 200 mm Installation (AVERAGE PRORATE BY ITEMS) 1.7735%

31/08/2023
Checked by,
PT. Sepuluh Sumber Anugerah

Herdy Dwiyana
Quantity Surveyor
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A CATCH BASIN PRECAST
A. 1 Catch Basin CB-01
Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 2 Catch Basin CB-02


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 3 Catch Basin CB-03


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 4 Catch Basin CB-04


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 5 Catch Basin CB-05


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 6 Catch Basin CB-06


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 7 Catch Basin CB-07


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 8 Catch Basin CB-08


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 9 Catch Basin CB-09


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 10 Catch Basin CB-10


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 11 Catch Basin CB-11


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 12 Catch Basin CB-12


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 13 Catch Basin CB-13


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 14 Catch Basin CB-14


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 15 Catch Basin CB-15


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 16 Catch Basin CB-16
Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 17 Catch Basin CB-17


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 18 Catch Basin CB-18


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 19 Catch Basin CB-19


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 20 Catch Basin CB-20


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 21 Catch Basin CB-21


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 22 Catch Basin CB-22


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 23 Catch Basin CB-23


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 24 Catch Basin CB-24


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 25 Catch Basin CB-25


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 26 Catch Basin CB-26


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 27 Catch Basin CB-27


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 28 Catch Basin CB-28


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 29 Catch Basin CB-29


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 30 Catch Basin CB-30


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 31 Catch Basin CB-31
Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 32 Catch Basin CB-32


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 33 Catch Basin CB-33


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 34 Catch Basin CB-34


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 35 Catch Basin CB-35


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 36 Catch Basin CB-36


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 37 Catch Basin CB-37


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 38 Catch Basin CB-38


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 39 Catch Basin CB-39


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 40 Catch Basin CB-40


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 41 Catch Basin CB-41


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 42 Catch Basin CB-42


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 43 Catch Basin CB-43


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 44 Catch Basin CB-44


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 45 Catch Basin CB-45


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 46 Catch Basin CB-46
Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 47 Catch Basin CB-47


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 48 Catch Basin CB-48


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 49 Catch Basin CB-49


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 50 Catch Basin CB-50


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 51 Catch Basin CB-51


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 52 Catch Basin CB-52


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 53 Catch Basin CB-53


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 54 Catch Basin CB-54


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 55 Catch Basin CB-55


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 56 Catch Basin CB-56


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 57 Catch Basin CB-57


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 58 Catch Basin CB-58


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 59 Catch Basin CB-59


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 60 Catch Basin CB-60


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 61 Catch Basin CB-61
Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 62 Catch Basin CB-62


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 63 Catch Basin CB-63


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 64 Catch Basin CB-64


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 65 Catch Basin CB-65


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 66 Catch Basin CB-66


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 67 Catch Basin CB-67


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 68 Catch Basin CB-68


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 69 Catch Basin CB-69


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 70 Catch Basin CB-70


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 71 Catch Basin CB-71


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 72 Catch Basin CB-72


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 73 Catch Basin CB-73


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 74 Catch Basin CB-74


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 75 Catch Basin CB-75


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 76 Catch Basin CB-76
Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 77 Catch Basin CB-77


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 78 Catch Basin CB-78


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 79 Catch Basin CB-79


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 80 Catch Basin CB-80


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 81 Catch Basin CB-81


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 82 Catch Basin CB-82


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 83 Catch Basin CB-83


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 84 Catch Basin CB-84


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 85 Catch Basin CB-85


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 86 Catch Basin CB-86


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 87 Catch Basin CB-87


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 88 Catch Basin CB-88


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 89 Catch Basin CB-89


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 90 Catch Basin CB-90


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 91 Catch Basin CB-91
Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 92 Catch Basin CB-92


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 93 Catch Basin CB-93


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 94 Catch Basin CB-94


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 95 Catch Basin CB-95


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 96 Catch Basin CB-96


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 97 Catch Basin CB-97


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 98 Catch Basin CB-98


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 99 Catch Basin CB-99


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 100 Catch Basin CB-100


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 101 Catch Basin CB-101


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 102 Catch Basin CB-102


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 103 Catch Basin CB-103


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 104 Catch Basin CB-104


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 105 Catch Basin CB-105


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -
Progress Calculation PROGRESS CALCULATION FORM Progress Date
CATCH BASIN (PRECAST) 008 Calculation 31/08/2023
WP 6 - Civil & Landscape
PT. Sepuluh Sumber Anugerah

Progress Quantity
Cummulative
No. Description x (m) y (m) z (m) Shape Factor perim. (m) area (m2) cubic (m3) kg/m kg/m2 n1 n2 n3 n Total Total Unit Remarks Progress Qty
Progress
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A. 106 Catch Basin CB-106
Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -

A. 107 Catch Basin CB-107


Precast Formwork 0.80 0.80 0.75 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Bottom Slab Rebar 1.10 1.10 1.04 6.00 2.00 1.00 12.00 13.75 kg 0% -
Wall Rebar (Horizontal) 1.22 1.04 3.00 4.00 1.00 12.00 15.25 kg 0% -
Wall Rebar (Vertical) 0.98 1.04 4.00 4.00 1.00 16.00 16.25 kg 0% -
L Angle Galvanized Install 0.60 0.60 2.40 1.00 1.00 1.00 1.00 2.40 m 0% -
Pouring Concrete 0.80 0.80 0.60 0.44 1.00 1.00 1.00 1.00 0.44 m3 0% -
Precast Formwork Dismantle 6.28 1.00 1.00 1.00 1.00 6.28 m2 0% -
Excavation 3.30 3.30 0.90 0.80 7.84 1.00 1.00 1.00 1.00 7.84 m3 0% -
Put Catch Basin in Hole 1.00 1.00 1.00 1.00 1.00 unit 0% -
Backfill 7.36 1.00 1.00 1.00 1.00 7.36 m3 0% -
Steel Grating Instalation 1.00 1.00 1.00 1.00 1.00 unit 0% -
0.00
RECAP FOR MAIN PROGRESS (BOQ ITEMS) Notes :
Progress Date 1. The Quantity Calculation is Still PT. SSA Version, It is Not Yet Together Measurement With KINE's Quantity Surveyor.
31/08/2023 2. Quantity Calculation Based On Approved Shop Drawing and Lotte Chemical E & C For Construction Drawing.

Progress Progress
No. Description Unit Total Quantity Remarks
Quantity Percentages
1 Precast Formwork m2 671.96 - 0.0000%
2 Bottom Slab Rebar kg 1,471.56 - 0.0000%
3 Rebar kg 3,371.21 - 0.0000%
Wall Rebar (Horizontal) kg 1,632.09 -
Wall Rebar (Vertical) kg 1,739.11 -
4 L Angle Galvanized Install m 256.80 - 0.0000%
5 Pouring Concrete m3 46.87 - 0.0000%
6 Precast Formwork Dismantle m2 671.96 - 0.0000% Method
7 Excavation m3 838.97 - 0.0000% ARITMATH CHECKING
8 Put Catch Basin in Hole unit 107.00 - 0.0000% Method RECAP 8,330.92
9 Backfill m3 787.61 - 0.0000% BREAKDOWN 8,330.92
10 Steel Grating Instalation unit 107.00 - 0.0000% NOT OK!! - 0.00

GLOBAL PROGRESS FOR CATCH BASIN (PRECAST) (AVERAGE PRORATE BY ITEMS) 0.0000%

31/08/2023
Checked by,
PT. Sepuluh Sumber Anugerah

Herdy Dwiyana
Quantity Surveyor