You are on page 1of 2

R A B PEMBANGUNAN TEMPAT WUDHU & TOILET MASJID NURUL IMAN - DESA PEPEDAN

HARGA SAT JUMLAH HARGA


NO JENIS PEKERJAAN VOL SAT TOTAL HARGA
(Rp) SAT
I PEKERJAAN PERSIAPAN
1 Bowplank 19,0 m¹ 41.864 795.408
795.407,77
II PEKERJAAN TANAH
1 Galian Pondasi Footplat 0,43 m³ 66.750 28.703
2 Galian Pondasi Batu belah 6,47 m³ 66.750 431.873
460.575,00
III PEKERJAAN PASANGAN
1 Pek. Pondasi Batu belah 8,10 m³ 609.294 4.935.277
2 Pas Bata Merah 73,86 m² 124.386 9.187.184
3 Pas. Granit Lantai 60x60 14,0 m² 220.978 3.093.692
4 Pas . Granit dinding 30x60 46,9 m² 223.062 10.450.452
5 Pas . Roaster angin angin 144,0 bh 25.580 3.683.578
6 Plesteran 99,0 m² 58.764 5.818.188
7 Acian 99,0 m² 32.322 3.200.152
40.368.522,17
III PEKERJAAN STRUKTUR BETON
1 Pek. Pondasi FootPlat 0,61 m³ 3.335.129 2.034.429
2 Pek. Sloop Beton 15/20 0,82 m² 3.133.752 2.569.676
3 Pek. Kolom 15/20 1,16 m³ 3.040.837 3.527.371
4 Pek. Balok 15/20 0,77 m³ 3.040.837 2.341.444
5 Pek. Plat Dak 0,90 m³ 3.030.939 2.727.845
13.200.765,15
IV PEK. SANITASI
1 Pipa PVC 2' 13,0 m¹ 39.104 508.357
2 Pipa PVC 3/4' 23,00 m¹ 13.880 319.249
3 Kran 3/4 14,0 bh 36.435 510.090
4 Closet jongkok 2,00 bh 226.250 452.500
5 Pipa PVC 3' 8,0 m¹ 39.104 312.835
6 Floordrain 2,0 bh 31.425 62.850
7 Septicktank 1,0 ls 720.000 720.000
8 Resapan 1,0 ls 720.000 720.000
3.605.880,50
V PEKERJAAN PINTU
1 Pintu KM/WC PVC 2,0 bh 437.695 875.390,00
875.390,00
VI PEKERJAAN ATAP
1 Atap Galvalum rangka besi 18,9 m² 600.000 11.340.000,00
2 Plafon atap 16,0 m² 60.000 960.000,00
12.300.000,00
VII PEKERJAAN TITIK LAMPU
1 Lampu 4,0 ttk 130.000 520.000,00
520.000,00
JUMLAH HARGA 72.126.540,60
PEMBULATAN 72.126.000,00
Tegal, 29 Mei 2022

KETERANGAN;
1. Pintu Area Tempat wudhu/stainlees belum masuk RAB
2. Grill bawah kran wudhu belum masuk RAB
3. Cetak Huruf Stainlees belum masuk RAB
4. Torn Air/Tandon Air belum masuk RAB
5. Mesin Pompa Air belum mauk RAB