You are on page 1of 36

Kabupaten : Aceh Utara Jenis Prasarana : MCK

Kecamatan : Tanah Luas Take Of Sheet Lokasi : Alue Sijuek


Desa : Alue Sijuek Volume : 7.5 x 3 M

1. Galian Tanah Pondasi 29 M Volume


Dimensi = PxLxT
Dimensi = 0.45 x 0.6 x 29
Volume = 0.27 m2 x 29

0.45 = 7.83 M3 7.83 M3

0.60
2. Pondasi Batu Kali
29 Dimensi = a+b x t

0.20
2
= 0.35 x 0.45
= 0.1575 m2
Volume = 0.1575 m2 x 29

0.45 = 4.5675 M3 4.5675 M3

0.50
3. Batu Kosong
13 Unit

0.15
Dimensi = PxL
= 0.6 x 0.15 x 13

0.60 Volume
=
=
1.17
1.17
0.702
M2
M2
M3
x 0.6
0.702 M3

4. Urugan Pasir 13 Unit Dimensi = Luas + Luas II


= 18 + 9
0.05
= 27 M2
0.6 29 Volume = 27 M3 x 0.1
= 2.7 M3
13 Unit
Dimensi = PxL
0.05 0.6 = 0.6 x 0.6
= 0.36 M2
0.6 Volume = 0.018 M3 x 13
= 0.234 M3 2.934 M3

5. Urugan Tanah Kembali


= Galian tanah pondasi - (pondasi+batu kosong+urugan pasir)
= 2.3265 m3 2.3265 M3

6. Tanah Timbun
Luas I Dimensi = PxL
= 2x 1.5
= 3 M2
V = 0.66 M3

Luas II Dimensi = PxL


= 2x 3
= 6 M2
V = 3.42 M3

Luas III Dimensi = PxL


= 2.5 x 4
= 10 M2
V = 2.5 M3

Luas IV Dimensi = PxL


= 1x 5
= 5 M2
V = 1.25 M3 7.83 M3
Kabupaten : Aceh Utara Jenis Prasarana : MCK
Kecamatan : Tanah Luas Take Of Sheet Lokasi : Alue Sijuek
Desa : Alue Sijuek Volume : 7.5 x 3 M

Pekerjaan Beton Bertulang

1. Sloof'
29 M

0.2

0.15
Dimensi = PxL
= 0.2 x 0.13
= 0.026 M2
Luas total = 0.026 M2 x 29 m
Volume = 0.754 M3 0.754 M3

2. Kolom 9 Unit

Dimensi = PxL
= 0.13 x 0.18
= 0.0234 M2
4 Unit Luas total = 0.2106 M2 x 2.82 m
Volume = 0.593892 M3

Dimensi = PxL
= 0.13 x 0.18
= 0.0234 M2
Luas total = 0.0936 M2
Volume = 0.0936 M3 0.69 M3

3. Ring Balok 10 m
Dimensi = PxL
= 0.13 x 0.18
= 0.0234 M2
Luas total = 0.0234 M2
Volume = 0.234 M3 0.234 M3

1. beton cor lantai


Dimensi = Luas I + Luas II
= 18 + 9
= 27 M2
Volume = 27 x 0.05
= 1.35 M3 1.35 M3

Pejerjaan Dinding
1. dindig 1 12 m
Dimensi = PxL
= 12 x 2.82
= 33.84 M2
Luas total = 33.84 M2

dindig 2 7m
Dimensi = PxL
= 7x 1.63
= 11.41 M2
Luas total = 11.41 M2

dindig 3 9m
Dimensi = PxL
= 9x 1
= 9 M2
Luas total = 9 M2
Kabupaten : Aceh Utara Jenis Prasarana : MCK
Kecamatan : Tanah Luas Take Of Sheet Lokasi : Alue Sijuek
Desa : Alue Sijuek Volume : 7.5 x 3 M

2. Bak Air 2 Unit


Dimensi = PxL
= 1x 1
= 1 M2
Luas total = 2 M2

3. Dinding kuda-kuda 2 Unit


Dimensi = 1/2 a x t
= 0.5 1 x 0.93
= 0.465 M2
V = 0.93 M2 57.18 M2

4. Keramik
Bak Air Dimensi = PxL
4 sisi = 1x 1.5
= 1.5 M2
= 6 M2
4 sisi Dimensi = PxL
= 1x 1
= 1 M2
= 4
dinding Dimensi = PxL
4 sisi = 1x 1.5
= 1.5 M2
= 6 M2
3 2 sisi Dimensi = PxL
= 1 x 2
= 2 M2
= 12 M2
4 sisi = 1.63 x 2
= 3.26 M2
= 13.04 M2
4 sisi Dimensi = PxL
= 1.63 x 3
= 4.89 M2
= 19.56
4 sisi = 1 x 2.5
= 2.5 M2
= 10 M2
4 sisi Dimensi = PxL
= 1x 3
= 3 M2
= 12 82.6 M2

Pekerjaan Atap
1. Luas Atap
Luas I Dimensi = PxL
= 7.18 x 2.39
= 17.1602 M2
Lus II Dimensi = PxL
= 7.18 x 2.97
= 21.3246 M2
V = 38.4848 M2 38.4848 M2

Luas seng
Dimensi = PxL
= 1.8 x 1.02
= 1.836 M2
kebutuhan = 20.96122004357 + 10%
= 23.05734204793 lembar
2. Kuda-kuda
Kayu 6/12 3 btg
5.36 m 16.08 m = 4.02 btg

Kayu 5/10
balok tarik 3
2.6 m 7.8 m = 1.95 btg

Kayu 5/10
Makelar 3
1.3 m 3.9 m = 0.975 btg

Kayu 5/10
Gording 7
7.2 m 50.4 m = 12.6 btg

Papan listplank 2 unit


7.2 m 14.4 m = 3.6 Btg

Gording 6 unit
5m 30 m = 7.5 Btg
Gording 7 unit
2m 14 m = 3.5 Btg
Kabupaten : Aceh Utara Jenis Prasarana : MCK
Kecamatan : Tanah Luas Take Of Sheet Lokasi : Alue Sijuek
Desa : Alue Sijuek Volume : 7.5 x 3 M

Tripleks 3 mm
Luas Plafond 32.4 m2
Luas tripleks
Dimensi = PxL
= 1.6 x 2.4
= 3.84 M2
Kebutuhan = 8.4375 Lembar

pekerjaanseptictank
galian tanah Dimensi = a+b x t
2
1.36 = 1.13 x 1.32
= 1.4916 M2
Volume = 1.4916 x 1.1
= 1.64076 M3

1.32 Dimensi = PxL


= 1.15 x 2.47
= 2.8405 M2
Volume = 2.8405 x 1.1
0.96 = 3.12455 M3

Dimensi = a+b x t
2
= 1.935 x 0.62
= 1.1997 M2
Volume = 1.1997 x 1.1
= 1.31967 M3

Beton 5.04 m
Dimensi = PxL
= 5.04 x 1.1
= 5.544 M2
Volume = 5.544 x 0.13
= 0.72072 M3 0.72072 M3

ijuk 4.96 m Dimensi = PxL


= 4.96 x 0.13
= 0.6448 M2
Volume = 0.6448 x 0
= 0 M3

Pelat lantai
Dimensi = PxL
= 2.47 x 0.1
= 0.247 M2
Volume = 0.247 x 1.1
= 0.2717 M3 0.2717 M3
Kabupaten : Aceh Utara Jenis Prasarana : MCK
Kecamatan : Tanah Luas Take Of Sheet Lokasi : Alue Sijuek
Desa : Alue Sijuek Volume : 7.5 x 3 M

Bekisting

Kolom 13 Unit 0.45


Papan = 146.64 m
= 16.497 lmbar

sloof 2 unit
Papan = 58 m
= 14.5 lmbar

sloof 2 unit
Papan = 20 m
= 5 lmbar 35.997 Lembar

Total panjang 224.64


449.28 bh

41.82
83.64
Kayu 2/2 20.91
Kabupaten : Aceh Utara Jenis Prasarana : MCK
Kecamatan : Tanah Luas Take Of Sheet Lokasi : Alue Sijuek
Desa : Alue Sijuek Volume : 7.5 x 3 M

3. Balok
Vertikal
b
a
30 ɸ 12
a
a b c
0.05 5 0.05 = 5.4 m
= 162 m : 10
ɸ 12 = 16.2 btg

5 Ø 12
a
f
Ø 8 - 100 e

0,3
d b

0,2
a b c d e f
0.24 0.14 0.24 0.14 0.05 0.05 = 0.86 m
bh 228 = 196.08 m : 10
ɸ8 = 19.608 btg

Horizontal

b
a
40 ɸ 12
a
a b c
0.05 4.5 0.05 = 4.9 m
= 196 m : 10
ɸ 12 = 19.6 btg

5 Ø 12
a
f
Ø 8 - 100 e
0,3

d b

0,2
a b c d e f
0.24 0.14 0.24 0.14 0.05 0.05 = 0.86 m
bh 288 = 247.68 m : 10
ɸ8 = 24.768 btg

4. Pelat lantai
Tipe 1 4 unit

ɸ8 80
81
37.8
36.75

ɸ 10 115
4,5

108

5
Horizontal
ɸ8 235.55 m = 942.2 m : 10 = 94.22 btg

1,21 2,292 1,21


ɸ 10 223 m = 892 m : 10 = 89.2 btg
Kabupaten : Aceh Utara Jenis Prasarana : MCK
Kecamatan : Tanah Luas Take Of Sheet Lokasi : Alue Sijuek
Desa : Alue Sijuek Volume : 7.5 x 3 M

tipe 2 2 unit

ɸ8 48
54
23.8
22.05

3
ɸ 10 99
42

4,5

1,21 2,292 1,21


Horizontal
ɸ8 147.85 m = 295.7 m : 10 = 29.57 btg

ɸ 10 141 m = 282 m : 10 = 28.2 btg

tipe 3 2 unit

ɸ8 24
27

1,5
11.25
9

ɸ 10 36
33

4,325

1,21 2,292 1,21


Horizontal
ɸ8 71.25 m = 142.5 m : 10 = 14.25 btg

ɸ 10 69 m = 138 m : 10 = 13.8 btg

5. Tangga
Balok

b
a a
15 ɸ 12

a b c
0.05 1.6 0.05 = 1.7 m
= 25.5 m : 10
ɸ 12 = 2.55 btg

a Ø 8 - 100 mm
f 5 Ø 12 mm
de b
0,2

c
0,15
a b c d e f
0.09 0.14 0.09 0.14 0.05 0.05 = 0.56 m
bh 32 = 17.92 m : 10
ɸ8 = 1.792 btg
Kabupaten : Aceh Utara Jenis Prasarana : MCK
Kecamatan : Tanah Luas Take Of Sheet Lokasi : Alue Sijuek
Desa : Alue Sijuek Volume : 7.5 x 3 M

Sloof tangga

b
a a
5 ɸ 12

a b c
0.05 1.6 0.05 = 1.7 m
= 8.5 m : 10
ɸ 12 = 0.85 btg
5 Ø 12
a
f
Ø 8 - 100 e

0,3
d b

0,2
a b c d e f
0.24 0.14 0.24 0.14 0.05 0.05 = 0.86 m
bh 10.67 = 9.1762 m : 10
ɸ8 = 0.91762 btg

Pelat tangga
Pelat 1
3.616

b
a a
12

a b c
0.05 3.616 0.05 = 3.716 m
= 44.592 m : 10
ɸ 10 = 4.4592 btg

Anak tangga ɸ8 = 0.23 x 13 = 3.090 m


0.18 x 13 = 2.440 m
0.90 x 24 = 21.700 m
0.90 x 46 = 41.500 m
total = 824.76 m : 10
= 82.476 btg

Pelat 2
3.5

b
a a
12

a b c
0.05 3.5 0.05 = 3.6 m
= 43.2 m : 10
ɸ 10 = 4.32 btg

Anak tangga ɸ8 = 0.23 x 12 = 2.860 m


0.18 x 12 = 2.260 m
0.90 x 24 = 21.700 m
0.90 x 46 = 41.500 m
total = 819.84 m : 10
= 81.984 btg
Pelat borders

b
a a
11

a b c
0.05 1.2 0.05 = 1.3 m
= 14.3 m : 10
ɸ 10 = 1.43 btg

b
a a
b
24
a a
a b c
0.05 1.6 0.05 = 1.7 m
ɸ8 = 40.8 m : 10
4.08 btg

6. Pondasi 0,3

0,8

0,15
0,15
0,8 0,74
ɸ 12 326.4 m : 10 174.144 m : 10
ɸ 12 32.64 btg 17.4144 btg
Kabupaten : Aceh Utara Jenis Prasarana : MCK
Kecamatan : Tanah Luas Take Of Sheet Lokasi : Alue Sijuek
Desa : Alue Sijuek Volume : 7.5 x 3 M

m 535 = Ø 12 = 53.4544 tangga


m 102 = Ø 10 = 10.2092 tangga
m 1672 = Ø 8= 171.2496 tangga

Total Pembesian pada Gelagar memanjang = Ø 16 = 0 Batang


Ø 12 = 69.6544 Batang tangga
Ø 10 = 141.409 Batang tangga
Ø 8 = 354 Batang tangga

Total Panjang Ø 16 = 0 M
Ø 12 = 696.544 M
Ø 10 = 1414.092 M
Ø 8 = 3495.86 M

Berat/M Jlh panjang Total berat dibulatkan


berat besi Ø 16 mm 1.579 0 0.000 0.00 Kg
berat besi Ø 12 mm 0.888 696.544 618.531 619.00 Kg
berat besi Ø 10 mm 0.617 1414.092 872.023 872.00 Kg
berat besi Ø 8 mm 0.395 3495.8562 1379.698 1380.00 Kg
2871.00 Kg 2871.00 kg
ANALISA DAN TABEL PERHITUNGAN

Jenis kegiatan Pembanguan Prasarana


Lokasi Alue Sijuek
Ukuran 7.5 x 3 M

SNI 2835-2008 6.1 1.1 Menggali 1 m3 tanah biasa sedalam 1 meter 7.83 Volume
0.750 OH Pekerja x 7.83 = 5.873
0.025 OH Mandor x 7.83 = 0.196

SNI 2835-2008 6.9 1 m3 Urugan Kembali Galian 2.33 Volume


0.250 OH Pekerja x 2.33 = 0.582
0.008 OH Mandor x 2.33 = 0.019

SNI 2835-2008 6.11a 1 m³ Mengurug Tanah Timbun 7.83 Volume


1.200 m3 Tanah Timbun x 7.83 = 9.396
0.300 OH Pekerja x 7.83 = 2.349
0.010 OH Mandor x 7.83 = 0.078

SNI 2835 - 2008 1.11 Mengurug 1 m3 pasir urug 2.93 Volume


1.2000 M3 Pasir Urug x 2.93 = 3.521
0.3000 Org Pekerja x 2.93 = 0.880
0.0100 Org Kepala Kelompok x 2.93 = 0.029

SNI 2836-2008 6.2 1 m³ Memasang Pondasi Batu Kali, Campuran 1 PC : 4 PP 4.57 Volume
1.200 m3 Batu Kali x 4.57 = 5.481
4.075 Zak Semen x 4.57 = 18.613
0.520 m3 Pasir Pasang x 4.57 = 2.375
1.500 OH Pekerja x 4.57 = 6.851
0.750 OH Tukang Batu x 4.57 = 3.426
0.075 OH Kepala Tukang x 4.57 = 0.343
0.075 OH Mandor x 4.57 = 0.343
SNI 7394:2008.3.2 1 M3 Membuat beton mutu f'c = 9,8 Mpa (K 125), slump (12 ± 2) cm, w/c=0,78 1 : 2 : 3
3.03 M3
6.900 Zak Semen x 3.0 = 20.876
0.591 M3 Pasir Beton x 3.0 = 1.789
0.750 M3 Kerikil (Maksimum 30 mm) x 3.0 = 2.268
215 Ltr Air x 3.0 = 650.481
1.650 Org Pekerja x 3.0 = 4.992
0.275 Org Tukang Batu x 3.0 = 0.832
0.028 Org Kepala Tukang x 3.0 = 0.085
0.083 Org Mandor x 3.0 = 0.251

SNI 2837-2008 6.4 1 m² Membuat Plesteran 1 PC : 4 PP, Tebal 15 mm 210 M2 Volume

0.024 M3 Pasir Beton x 210 = 0.503


0.156 Zak Semen PC x 210 = 3.271
0.150 OH Tukang Batu x 210 = 3.145
0.300 OH Pekerja x 210 = 6.290
0.015 OH Mandor x 210 = 0.315

SNI 7394-2008-6.17 Pembesian 10 kg dengan besi polos / besi ulir 113 Kg Volume

0.0150 Kg Kawat Beton x 113 = 1.695


0.070 Org Pekerja x 113 = 7.910
0.070 Org Tukang Besi x 113 = 7.910
0.011 Org Kepala Kelompok x 113 = 1.243

SNI 6897-2008-6.9 1 M2 Pasangan Bata Merah Tebal 1/2 Bata Adukan 1 PC : 4 PP 140 M2 Volume
0.0430 M3 Pasir beton x 140 = 0.601
70.0000 Buah Batu Bata x 140 = 9784.600
0.2875 Kg Semen x 140 = 4.019
0.3000 OH Pekerja x 140 = 4.193
0.1000 OH Tukang Batu x 140 = 1.398
0.0100 OH Kepala Tukang x 140 = 0.140
0.0150 OH Mandor x 140 = 0.210

Anl. SNI 7394-2008 6.21 1 m2 Memasang Bekisting Untuk Sloof 5.800 M2 Volume
0.300 Kg Paku x 5.800 = 1.740
0.100 Liter Minyak Bekisting x 5.800 = 0.580
0.520 OH Pekerja x 5.800 = 3.016
0.260 OH Tukang x 5.800 = 1.508
0.026 OH Kepala Tukang x 5.800 = 0.151
0.026 OH Mandor x 5.800 = 0.151

Anl. SNI 7394-2008 6.22 1 m2 Memasang Bekisting Untuk Kolom 3.299 M2 Volume
0.400 Kg Paku x 3.299 = 1.320
0.200 Liter Minyak Bekisting x 3.299 = 0.660
0.660 OH Pekerja x 3.299 = 2.178
0.330 OH Tukang x 3.299 = 1.089
0.033 OH Kepala Tukang x 3.299 = 0.109
0.033 OH Mandor x 3.299 = 0.109

Anl. SNI 7394-2008 6.24 1 m2 Memasang Bekisting Untuk Plat Lantai 2.72 M2 Volume
0.400 Kg Paku x 2.72 = 1.087
0.200 Liter Minyak Bekisting x 2.72 = 0.543
0.350 Lembar Plywood Tebal 9 mm x 2.72 = 0.951
0.660 OH Pekerja x 2.72 = 1.793
0.330 OH Tukang x 2.72 = 0.897
0.033 OH Kepala Tukang x 2.72 = 0.090
0.033 OH Mandor x 2.72 = 0.090

A. 4.4.3.54 Pemasangan 1 m2 Dinding Keramik ukuran 20 x 20 cm 82.60 M2 Volume


0.090 OH Pekerja x 82.60 = 7.434
0.045 OH Tukang batu x 82.60 = 3.717
0.045 OH Kepala Tukang x 82.60 = 3.717
0.045 OH Mandor x 82.60 = 3.717
26.500 Bh Keramik x 82.60 = 2188.900
9.300 kg Semen Portland x 82.60 = 768.180
0.018 m3 Pasir Pasang x 82.60 = 1.487
1.940 kg Semen Warna x 82.60 = 160.244

A. 4.7.1.10 Pengecatan 1 m2 tembok baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
55.18 M2 Volume
0.020 OH Pekerja x 55.18 = 1.104
0.063 OH Tukang Cat x 55.18 = 3.476
0.0063 OH Kepala Tukang x 55.18 = 0.348
0.003 OH Mandor x 55.18 = 0.166
0.100 kg Plamur tembok x 55.18 = 5.518
0.100 kg Cat Dasar x 55.18 = 5.518
0.260 kg Cat Penutup x 55.18 = 14.347

Bahan/Material : Jumlah Volume Dibulatkan


1 Batu Kali/Gunung 5.481 5.00
2 Pasir Pasangan 4.625 5.00
3 Pasir Urug 2.934 3.00
4 Kerikil Beton 2.268 2.00
5 Semen PC @ 40 Kg 46.778 47.00
6 Timbunan 9.396 9.00
7 Kawat Beton 1.695 2.00
8 Plywod 9 mm 9.438 9.00
9 Paku 4.147 4.00
10 Kayu 5/7 0.000 0.00
11 Balok kayu 2/2 20.910 21.00
12 Batu bata 9784.600 9785.00
13 Minyak bekisting 1.783 2.00
14 Papan 16.000 16.00
15 Cat Tembok 19.865 20.00
16 Keramik 2188.900 2189.00

Upah :
1 Pekerja 55.445 55.00
2 Tukang 27.397 27.00
3 Kepala Tukang 4.981 5.00
4 Kepala kelompok/Mandor 7.000 7.00

Rekapitulasi Bahan Untuk 3 Unit MCK


Bahan/Material : Volume Jumlah Unit Total
1 Batu Kali/Gunung 5.000 3 15.00
2 Pasir Pasangan 5.000 3 15.00
3 Pasir Urug 3.000 3 9.00
4 Kerikil Beton 2.000 3 6.00
5 Semen PC @ 40 Kg 47.000 3 141.00
6 Timbunan 9.000 3 27.00
7 Kawat Beton 2.000 3 6.00
8 Plywod 9 mm 9.000 3 27.00
9 Paku 4.000 3 12.00
10 Kayu 5/7 0.000 3 0.00
11 Balok kayu 2/2 21.000 3 63.00
12 Batu bata 9785.000 3 29355.00
13 Minyak bekisting 2.000 3 6.00
14 Papan 16.000 3 48.00
15 Cat Tembok 20.000 3 60.00
16 Keramik 2189.000 3 6567.00

Upah :
1 Pekerja 55.000 3 165.00
2 Tukang 27.000 3 81.00
3 Kepala Tukang 5.000 3 15.00
4 Kepala kelompok/Mandor 7.000 3 21.00
DAFTAR UPAH DAN HARGA BAHAN/ALAT BERAT

NO. URAIAN SATUAN

1 2 3
A. UPAH KERJA
1 Tukang Orang / hari
2 Kepala Tukang Orang / hari
3 Mandor Orang / hari
4 Pekerja Orang / hari

B. HARGA BAHAN
1 Bata merah Biji
2 Batu Kali / Belah M3
3 Besi Beton polos Ǿ 16 mm Btg
4 Besi Beton polos Ǿ 14 mm Btg
5 Besi Beton polos Ǿ 12 mm Btg
6 Besi Beton Polos Ǿ 10 mm Btg
7 Besi Beton Polos Ǿ 8 mm Btg
8 Besi Beton Polo sǾ 6 mm Btg
9 Bonbon Keramik M1
10 Cat Minyak ( Dulax V-Glass/Super RJ ) Kg
11 Cat Tembok Kg
12 Kerikil bersih M3
13 Kayu Balok 6 /12 Btg
14 Kayu Balok 5 /7 Btg
15 Kayu Balok 5 /5 Btg
16 Kayu Balok lat 1/2 Btg
17 Kayu Balok Lat 2/2 Btg
18 Kawat Beton Kg
19 Keramik 40 x 40 (setara Garuda) Ktk
Keramik 20 x 25 (setara Garuda) Ktk
20 Pasir Beton M3
21 Pasir Plasteran M3
22 Pasir Urug M3
23 Papan Lantai Lbr
24 Tanah Timbun M3
25 Tasirtu M3
26 Tepung Keramik Kg
27 Papan Cor Lbr
28 Paku Kayu Kg
29 Semen ( PC) 40 Kg/Zak Zak
30 Seng ( Bjls ) Crown Lbr
31 Multiplek 4 mm Lbr
32 Pagar BRC Tinggi 0.90 M Keping
33 Tiang Besi/Pipa Stick Galvanis BRC Ø 1,5''
34 Paving Blok Buah
35 Tiang Besi/Pipa Galvanis BRC Ø 3''
36 Kloset Jongkok Buah
37 Ijuk Kg
38 Keran air Buah
39 floor drain Buah
40 Pipa PVC 3 Inchi Btg
41 Multiplek 9 mm Lbr
42 Minyak Bekisting (Melamin) Liter
43 Pipa PVC 1 Inchi Btg
44 Kereta sorong Unit
45 Cangkul Bh

ALAT-ALAT

1 Motor Graider Jam


2 Vibrator Roller Jam
3 Excavator Jam
4 Mobilisasi Alat Berat Ls ( PP )
5 Molen Hari
6 Mobilisasi Molen Ls ( PP )
7 Truk Tangki Air Hari

Geuchiek Gampong Disurvey Oleh


Tenaga Teknik

Ibrahim Muttaqien, ST
BERAT

HARGA
(Rp.)
4

100,000
125,000
95,000
75,000

Rp 800
Rp 247,000
Rp 110,000
Rp 86,000
Rp 80,000
Rp 65,000
Rp 40,000
Rp 25,000
Rp 20,000
Rp 65,000
Rp 12,000
Rp 220,000
Rp 122,000
Rp 95,000
Rp 61,000
Rp 40,000
Rp 45,000
Rp 19,000
Rp 70,000
Rp 50,000
Rp 170,000
Rp 160,000
Rp 130,000
Rp 170,000
Rp 76,000
Rp 200,000
Rp 14,000
Rp 60,000
Rp 19,000
Rp 60,000
Rp 75,000
Rp 80,000
Rp 195,000
Rp 90,000
Rp 2,000
Rp 402,000
Rp 156,000
Rp 15,000
Rp 18,000
Rp 30,000
Rp 140,000
Rp 172,000
Rp 14,000
Rp 83,000
Rp 506,000
Rp 80,000

Rp 500,000
Rp 500,000
Rp 600,000
Rp 3,000,000
Rp 250,000
Rp 200,000
Rp 1,000,000

Disurvey Oleh
Tenaga Teknik

Muttaqien, ST
RENCANA ANGGARAN BIAYA PROGRAM DANA DESA
(KEGIATAN PRASARANA)
TAHUN ANGGARAN 2017

Provinsi : Aceh No. RAB :


Kabupaten : Aceh Utara Program : Program Dana Desa
Kecamatan : Tanah Luas Jenis Kegiatan : Sarana Prasarana
Desa : Alue Sijuek Sub Kegiatan : MCK
Ukuran/dimensi : 7.5 x 3 M
Jumlah : 3 Unit

Volume
Jumlah Total
No. URAIAN Dari Dana Satuan Harga Satuan (Rp.)
(Rp.)
Total
Desa

1 PERSIAPAN

1.1 Pengukuran/Bowplank 1 1 LS 200,000 200,000


1.2 Papan Nama Proyek 1 1 LS 300,000 300,000
1.3 Prasasti 1 1 Ls 300,000 300,000
800,000
2 BAHAN
2.1 Semen 141 141 Zak 70,000 9,870,000
2.2 Pasir 15 15 M3 170,000 2,550,000
2.3 Pasir Urug 9 9 M4 130,000 1,170,000
2.4 Kerikil 6 6 M3 220,000 1,320,000
2.5 Batu Kali 15 15 M3 247,000 3,705,000
2.6 Besi Beton Ǿ 10 mm, P = 10 M 8 8 Btg 65,000 520,000
2.7 Besi Beton Ǿ 8 mm, P = 10 M 9 9 Btg 40,000 360,000
2.8 Besi Beton Ǿ 12 mm, P = 10 M 15 15 Btg 80,000 1,200,000
2.9 Minyak Bekesting 6 6 Ltr 14,000 84,000
2.10 Paku 12 12 Kg 19,000 228,000
2.11 Kawat Ikat 6 6 Kg 19,000 114,000
2.12 Papan Mall 33 33 Lbr 60,000 1,980,000
2.13 Kayu Perancah 2x2 42 42 Btg 45,000 1,890,000
2.14 Kayu Stut 32 32 Btg 40,000 1,280,000
2.15 plywood 3 mm 18 18 Kg 80,000 1,440,000
2.16 Tanah Timbun 30 30 M3 100,000 3,000,000
2.17 Kusen Pintu 6 6 Unit 250,000 1,500,000
2.18 Daun Pintu 18 18 Unit 300,000 5,400,000
2.19 Engsel 12 12 Set 10,000 120,000
2.20 Batu bata 29355 29355 biji 800 23,484,000
2.21 Ventilasi 6 6 Unit 200,000 1,200,000
2.22 Keran Air 6 6 Bh 18,000 108,000
2.23 floor drain 9 9 Bh 30,000 270,000
2.24 closed jongkok keramik 6 6 Bh 156,000 936,000
2.25 Cat tembok 60 60 Kg 12,000 720,000
2.26 Pipa Hawa 2 inchi 3 3 Btg 100,000 300,000
2.27 Pipa PVC 3 inchi 3 3 Btg 120,000 360,000
2.28 Ijuk 3 3 Kg 15,000 45,000
2.29 Keramik 546 546 Ktk 50,000 27,300,000
2.30 Pipa PVC air 1 inchi 6 6 Btg 25,000 150,000
2.31 Seng Gelombang 6 kaki 23 23 Lbr 75,000 1,725,000
2.32 Papan Listplank 12 12 lbr 150,000 1,800,000
2.33 Kayu 6/12 12 12 btg 100,000 1,200,000
2.34 Kayu 5/10 48 48 Btg 95,000 4,560,000
2.35 Kayu 5/5 33 33 Btg 61,000 2,013,000

103,902,000
3 PERALATAN

3.1 Kereta Sorong 1 1 Unit 506,000 506,000


3.2 Cangkul 1 1 Unit 80,000 80,000
3.3 Sekop 1 1 Unit 80,000 80,000
3.4 Timba Plastik 3 3 Bh 15,000 45,000
3.5 Raskam 1 1 Bh 17,000 17,000
3.6 Kuas 2 2 Bh 45,000 90,000
3.7 Benang 1 1 Rol 5,000 5,000
3.8 Selang (water pass) 1 1 Rol 50,000 50,000
873,000
4 UPAH
4.2 Kepala Tukang 15 15 HOK 130,000 1,950,000
4.3 Tukang 81 81 HOK 120,000 9,720,000
4.4 Pekerja 165 165 HOK 100,000 16,500,000
165 28,170,000
5 OP TOTAL BIAYA 133,745,000
5.1 Perencanaan 7% 133,745,000 9,362,000

Jumlah 9,362,000
Jumlah Total 143,107,000

Alue Sijuek, 2017


Disetejui/Mengesahkan Diverivikasi Oleh Dibuat Oleh;
Geuchik Sekdes Tim Pelaksana Kegiatan
KEGIATAN PROGRAM DANA DESA
KECAMATAN TANAH LUAS KABUPATEN ACEH UTARA
TAHUN ANGGARAN 2016
REKAPITULASI ANGGARAN BIAYA
PEMBANGUNAN MCK DESA
Provinsi : Aceh
Kabupaten : Aceh Utara
Kecamatan : Tanah Luas
Desa : Blang Trieng
Jenis Kegiatan : MCK
Ukuran/ Dimensi : 7.5 x 3 M
Jumlah Total
No. Uraian Jumlah : 1 Unit
No. RAB :
Program Dana Desa Keterangan Program Dana Desa Keterangan

I PERSIAPAN 800,000 800,000

II BAHAN 103,902,000 103,902,000

III PERALATAN 873,000 873,000

IV UPAH 28,170,000 28,170,000

JUMLAH 133,745,000 133,745,000


V Administrasi dan Dokumentasi 2 % 2,675,000
VI Operasional Perencanaan 3 % 4,012,000
VII Operasional Pengawasan 2 % 2,675,000
JUMLAH TOTAL 143,107,000
Jumlah Biaya Upah 28,170,000
Jumlah HOK Kontruksi - HOK

Alue Sijuek, 2017


Diverifikasi Oleh, Disetujui/Mengesahkan Dibuat Oleh;
TPK Desa Punti Sekdes Konsultan Perencana

________________________ ________________________ MUHAMMAD IQBAL


Daftar Penggunaan Besi pada Plat Lantai

Diameter Panjang Jumlah Total


No. Dimensi Jarak a b c d e f g h i Btg 1 bh Balok
Besi (m) (Btg) (m)
1. Beton Bertulang
Kolom Ø 12 mm 0.10 0.05 2.85 0.05 2.95 16 47.00 5 5
Beughel Ø 8 mm 0.2 0.07 0.07 0.12 0.12 0.05 0.05 0.48 56.4 27.00 3 3

a
d ef b
c

2. Pelat beton

b Ø 10 mm 0.15 2.5 0.05 2.55 7.33333 19.00 2 2

a a Ø 10 mm 0.15 1.1 0.05 1.15 16.6667 19.00 2 2

Jumlah Panjang Besi 10 ( M) 38.00


Jumlah Panjang Besi 12 ( M) 47.00
Jumlah Panjang Besi 8 ( M) 27.00
Jumlah Batang (Btg) 12.00
Perhitungan Berat Besi Berat/M Jumlah Pjg (M) Total Berat Dibulatkan 3 Unit 36.00
Berat Besi Ø10 mm 1.579 38.00 59.989 60.00 Kg
Berat Besi Ø12 mm 0.888 47.00 41.736 42.00 Kg
Berat Besi Ø8 mm 0.395 27.00 10.656 11.00 Kg
Besi Per M3 Beton = Kg
Jadi Berat 1 Batang Besi Ø16 mm = 15.16 Kg/Btg
Jadi Berat 1 Batang Besi Ø12 mm = 8.52 Kg/Btg
Jadi Berat 1 Batang Besi Ø8 mm = 3.79 Kg/Btg
DATA PERHITUNGAN VOLUME DAN HOK

I Jenis kegiatan : Perkerasan jalan


Bahan : Tasirtu
Nomor RAB : 01

Jenis material Panjang Lebar Tebal Volume Koefisien Volume Sat


Tasirtu 2580 3.50 0.15 1354.50 1.20 1619 M3

Keofisien Vol Satuan


Penghamparan
Pekerja 0.200 1,619.00 323.80 HOK

II Jenis kegiatan : Buis Beton


Dimensi : dia 60 cm x 4 m ( 6 unit )
Nomor RAB : 02

Galian Tanah : (Analisa A.1)


5 X 0.7 X 1.4 = 29.40
Pekerja = 29.40 x 0.670 = 19.70 HOK

Timbunan Kembali : (Analisa A.17a.)


29.40/2 = 14.70
Pekerja = 14.70 x 0.750 = 5.51 HOK

Pasir Urug : (Analisa A.18.b.)


0.05 X 5 X 0.7 = 1.05
Pasir = 1.05 x 1.200 = 1.26 M3
Pekerja = 1.05 x 0.300 = 0.32 HOK

Pasangan Batu Kali : (Analisa K-810)


(0.35 X 1 X 1) - (3.14 X 0.25 X 0.25) X 2 + (0.25 X 5 X 0.7) = 5.00
Batu Kali = 5.00 x 1.10 = 5.49 M3
Semen PC 40 Kg = 5.00 x 3.60 = 17.98 Zak
Pasir Pasang = 5.00 x 0.24 = 1.20 M3
Pekerja = 5.00 x 1.00 = 5.00 HOK
Tukang = 5.00 x 0.80 = 4.00 HOK

Pemasangan Gorong - gorong : (Analisa K-123)


Gorong-Gorong dia 60 c = 6.00 x 4.00 = 24.00 Unit
Kerikil = 24.00 x 0.30 = 7.20 M3
Pasir Beton = 24.00 x 0.36 = 8.64 M3
Semen PC 40 Kg = 24.00 x 0.50 = 12.00 Zak
Pekerja = 24.00 x 1.00 = 24.00 HOK
Tukang = 24.00 x 0.20 = 4.80 HOK

Plasteran : (Analisa G.50.q)


(0.25 X 1 X 2) + (0.4 X 1 X 4) = 12.60
Semen PC 40 Kg = 12.60 x 0.09 = 1.10 Zak
Pasir Pasang = 12.60 x 0.01 = 0.18 M3
Pekerja = 12.60 x 0.40 = 5.04 Zak
Tukang = 12.60 x 0.20 = 2.52 Zak

REKAPITULASI BAHAN DAN UPAH


BAHAN dibulatkan
1. Semen = 31.08 M3 ≈ 31 M3
2. Pasir = 11.28 M3 ≈ 12 M3
3. Kerikil = 7.20 Zak ≈ 7 Zak
4. Batu Kali 5.49 M3 ≈ 6 M3
5. Gorong - gorong = 24.00 Bh ≈ 24 Bh
UPAH
1. Pekerja = 59.56 HOK ≈ 59 HOK
2. Tukang = 11.32 HOK ≈ 11 HOK

III Jenis kegiatan : Plat beton


Dimensi : 4 x 2 m2 ( 1 unit )
Nomor RAB : 03

a Plat Beton Panjang Tinggi Lebar Volume


Volume 4.00 0.20 2.00 1.60 M3
b Pondasi
Volume #REF! M3
c Tembok Sandaran
Volume 4.00 0.50 0.20 0.40 M3
d Balok Gelagar
Volume 4.00 0.30 0.25 0.30 M3
Volume Total Pengecoran #REF! M3

Beton Bertulang 1 : 2 : 3
Bahan : Volume
Pasir 0.54 #REF! #REF! M3
Kerikil 0.82 #REF! #REF! M3
Semen 6.80 #REF! #REF! Zak
Upah : -
Pekerja 6.00 #REF! #REF! Hok
Tukang 1.00 #REF! #REF! Hok
Kep. Tuk 0.40 #REF! #REF! Hok
Galian Tanah
Pekerja 0.10 16.80 1.68 Hok

Pasangan Batu Kali


Bahan:
Batu Kali 1.20 #REF! #REF! M3
Pasir 0.52 #REF! #REF! M3
Semen 3.26 #REF! #REF! M3
Upah:
Kepala Tukang 0.12 #REF! #REF! HOK
Tukang 1.20 #REF! #REF! HOK
Pekerja 3.60 #REF! #REF! HOK

Rekapitulasi Bulat
Batu Kali #REF! M3 #REF! M3
Pasir #REF! M3 4.50 M3
Kerikil #REF! M3 5.50 M3
Semen #REF! Zak #REF! Zak
Upah
Pekerja #REF! Hok #REF! Hok
Tukang #REF! Hok #REF! Hok
Kep. Tuk #REF! Hok #REF! Hok
V Jembatan
Dimensi :7x4m
No. RAB

Koefisien Volume Total Volume

1 M3 Beton Bertulang 1 : 2 : 3

Pekerja 5.0000 0.00 0.00


Tukang 0.5000 0.00 0.00

Semen 8.5000 0.00 0.00


Pasir 0.5400 0.00 0.00
Kerikil 0.8200 0.00 0.00
Kawat Ikat 2.0000 0.00 0.00
Paku 0.4000 0.00 0.00

1 M3 Pasangan Batu Kali

Pekerja 5.0000 0.00 0.00


Tukang 0.5000 0.00 0.00

Semen 5.2960 0.00 0.00


Pasir 0.5000 0.00 0.00
Kerikil 0.7500 0.00 0.00
Batu Kali 0.2000 0.00 0.00

1 M2 Plesteran

Pekerja 0.3800 0.00 0.00


Tukang 0.1500 0.00 0.00

Semen 0.1300 0.00 0.00


Pasir 0.0200 0.00 0.00

REKAPITULASI BAHAN DAN HOK


HOK BAHAN
Bulat
Pekerja #REF! Semen 0.00 -
Tukang #REF! Pasir 0.00 -
Kerikil 0.00 -
Batu Kali 0.00 -
Paku 0.00 -
Kawat Ikat 0.00 -
1618.63 1619

0
ANALISA DAN TABEL PERHITUNGAN
I. SALURAN

Volume Kegiatan : 168.00 M3


SNI 7394 - 2008 : 1 M3 GALIAN TANAH BIASA SEDALAM 1 METER
0.750 Org Pekerja
0.025 Org Kepala kelompok

No Bahan/HOK Volume Dibulatkan


I. Bahan
1. - 0.00 0.00
II. ALAT
1. - 0.00 0.00
III. HOK
1. Pekerja 126.00 126.00
2. Kepala kelompok 4.20 4.00

Volume Kegiatan : 30.00 M2


SNI 7394:2008.6.18 : 1 M2 MEMASANG BEKISTING UNTUK SLOOF
0.300 Kg Paku 5 cm – 10 cm
0.100 Ltr Minyak Bekisting
0.520 Org Pekerja
0.260 Org Tukang Kayu
0.026 Org Kepala kelompok

No Bahan/HOK Volume Dibulatkan


I. Bahan
1. Paku 5 cm – 10 cm 9.00 9.00
2 Minyak Bekisting 3.00 3.00
II. ALAT
1. - 0.00 0.00
III. HOK
1. Pekerja 15.60 16.00
2. Tukang Kayu 7.80 8.00
3. Kepala kelompok 0.78 1.00

Volume Kegiatan : 78.00 M3


SNI 7394:2008.3.2 : 1 M3 Membuat beton mutu f'c = 9,8 Mpa (K 125), slump (12 ± 2) cm, w/c=0,78 1 : 2 : 3
6.900 Zak Semen
0.591 M3 Pasir Beton
0.750 M3 Kerikil (Maksimum 30 mm)
215 Ltr Air
1.650 Org Pekerja
0.275 Org Tukang Batu
0.028 Org Kepala Tukang
0.083 Org Mandor

No Bahan/HOK Volume Dibulatkan


I. Bahan
1. Semen 538.20 538.00
2. Pasir Beton 46.13 46.00
3. Kerikil (Maksimum 30 mm) 58.47 58.00
4. Air 16,770.00 16,770.00
II. ALAT
1. - 0.00 0.00
III. HOK
1. Pekerja 128.70 129.00
2. Tukang Batu 21.45 21.00
3. Kepala Tukang 2.18 2.00
4. Mandor 6.47 6.00
Volume Kegiatan : 360.00 M2
SNI DT 91 -0010-2007 : 1 M2 plesteran Acian
0.081 Zak Portland Cement
0.100 Org Pekerja
0.100 Org Tukang batu
0.010 Org Kepala Kelompok / Mandor

No Bahan/HOK Volume Dibulatkan


I. Bahan
1. Portland Cement 29.27 29.00
II. ALAT
1. - 0.00 0.00
III. HOK
1. Pekerja 36.00 36.00
2. Tukang batu 36.00 36.00
3. Kepala Kelompok / Mandor 3.60 4.00

Volume Kegiatan : 0.00 M3


: 1 M3 TIMBUNAN TASIRTU
0.1500 Org Pekerja
0.0200 Org Kepala kelompok
1.2000 M3 Timbunan Tasirtu

No Bahan/HOK Volume Dibulatkan


I. Bahan
1. Timbunan Tasirtu 0.00 0.00
II. ALAT
1. - 0.00 0.00
III. HOK
1. Pekerja 0.00 0.00
2. Kepala kelompok 0.00 0.00

REKAPITULASI BAHAN DAN UPAH

NO URAIAN SATUAN VOLUME DIBULATKAN


BAHAN
1 Semen PC 40 Kg Zak 567.00 567.00
2 Pasir Bersih M3 46.13 46.00
3 Kerikil (Maksimum 30 mm) M3 58.47 58.00
4 Air Ltr 16,770.00 16,770.00
5 Plywood 9 mm Lbr 12.50 13.00
6 Kayu Stut 2 x 2 Btg 62.77 63.00
7 Kayu Stut 1 x 2 Btg 10.76 11.00
8 Paku ( 10% Panjang Saluran ) 25% 2.25 Kg 9.00 11.00
9 Minyak Bekisting ( 10% Panjang Saluran ) x 4 Kali Pengolesan Ltr 3.00 15.00
10 Tasirtu M3 0.00 0.00
11 Kayu cerucuk Btg 0.00 0.00

UPAH
1 Pekerja HOK 306.30 306.00
2 Tukang HOK 65.25 65.00
3 Kepala Tukang HOK 2.18 2.00
4 Kepala Kelompok / Mandor HOK 15.05 15.00
Compatibility Report for JEMBATAN ALUE PANAH 5 X 6 M.xls
Run on 03/08/2016 16:41

The following features in this workbook are not supported by earlier versions
of Excel. These features may be lost or degraded when you save this workbook
in an earlier file format.

Minor loss of fidelity # of occurrences

Some formulas in this workbook are linked to other workbooks that are 15
closed. When these formulas are recalculated in earlier versions of Excel
without opening the linked workbooks, characters beyond the 255-character
limit cannot be returned.

'SNI jembtan'!C4
'SNI jembtan'!P20

'SNI jembtan'!Q47

'RAB Saluran Nibong'!O13

'RAB Saluran Nibong'!H67

'RAB Saluran Nibong'!H74

'Rekap Saluran Nibong'!F9

'Rekap Saluran Nibong'!C41

'Rekap Saluran Nibong'!G41

'Rekap Saluran Nibong'!J41:J42

'Rekap Saluran Nibong'!C48

'Harga Satuan'!F56

'Harga Satuan'!B75

'Harga Satuan'!E75

Some formulas in this workbook are linked to other workbooks that are 387
closed. When these formulas are recalculated in earlier versions of Excel Defined Names
without opening the linked workbooks, characters beyond the 255-character
limit cannot be returned.
Some cells or styles in this workbook contain formatting that is not supported 41
by the selected file format. These formats will be converted to the closest
format available.

You might also like