REF: KP/SIAE/2020/UP00106 DTD: 06 JAN, 2020

To,
PROJECT MANAGER
UNIT-11,AYODHYA
AMETHI
U.P.PROJECTS.CORP LTD.
AMETHIU.P

Tel No : +91-97954999036, 7752944777 e-mail :

Kind Attn : Mr.Amit Chaudhary – Architect


Ref : Discussions with Mr Pankaj Mishra at Lucknow Office.
Reg : Turnkey Proposal for Electrification and Lighting of Tourism & Devlopment of temples
Project at Amethi– Uttar Pradesh.

Dear Sir

This has reference to the above detailed discussions we had during your visit at office regarding
Electrification and Lighting Solutions for your upcoming project of Tourism &
Devlopment of temples Project at Amethi– Uttar Pradesh.

Here we are pleased to submit our detailed techno commercial proposal as under:

This document comprises of the following:

 Detailed technical and commercial offer for Electrification and Lighting.

The scope of works shall specifically quotation the complete end-to-end solutions broadly including

 Arrangement and facility for the Metering of Generated Power as per guidelines
and norms
 Electrical Inspectors Approvals
 Supply and Installation of Induction Based High Mast Lighting.
 Supply and Installation of Induction Based Decorative Street Lighting.
 Supply and Installation of various LED and Focus Lighting as required for
Beautification of Temple.
 Scopes of work defined and quoted are designed for zero maintenance for the
complete life span.

we shall be glad to assist you in any further confirmations / clarifications that you may desire in the
subject matter and we shall look forward to be of service to you in the best way we can.

For KESARI POWERTECH.

Pankaj Mishra
(M: +91 9935977600)

REF: KP/SIAE/2020/UP00106 DTD: 06 JAN, 2020


PRICE SCHEDULE:

ITEM DESCRIPTION PRICE AMOUNT IN LIST OF MAKES


SR NO AND SPECIFICATIONS QTY INR/EACH INR

         
Supply Installation
Testing and
Commissioning of
High Mast Induction
Lighting – SITC of
decorative street
light-pole & post
fixture complete with BAJAJ
1 induction Lamp 2 Nos 8,57,000 8,57,000
Panel with timer and MCCB
a. and MCBs 1  
b. Octagonal Pole 4  
c. Earthing 4  
d. LA 1  
e. Gear Box 1  
f. SS wire Rope 1set  
g. Octagonal Pole 4  
h. Motorized Mechanism 1  
i. Aviation Light - 1 no. 1  

j. 200 Watt Flood Light - 28  


Civil Foundation for High
h. Mast and Panel 1job  
i. Catalogue - Attached  
         

Supply Installation
Testing and
Commissioning of
Decorative Street Crompton
2 Light 200Watt. 8 Nos 18500 150000.00 Greives
a. Pole and Post 1  
Fixture Complete with
b. Induction lamp 100 Watt. 1  
         
         
TRANSPORTATION COST & FABRICATION ERECTION & INSTALLATION CONDITION APPLY
REF: KP/SIAE/2020/UP00106 DTD: 06 JAN, 2020

COMMERCIAL TERMS AND CONDITIONS:

1. PRICE : The prices quoted are inclusive of Excise, CST freight FOR Site.

2. FREIGHT : Included in the quoted rates for our scope of supplied materials.

3. TRANSIT INSURANCE : Included in the quoted rates for our scope of


supplied materials

4. GST : Will be charged extra @12 %

5. SALES TAX : Included for all the Supplies.

6. OCTROI : Shall be charged extra at applicable rates


on the supply contracts.

7. PAYMENT : We request the following Schedule of Payment :

 10% of the Contract Value as non-refundable advance along with


the award and acceptance of Letter of Award.
 10 % on final submission and approval of design and drawings.
 70 % on readiness of materials for dispatch after due inspections
and clearance for dispatch.
 10% against Commissioning, Completion and Hand-over of site to
owner against submission of Performance Bank Guarantee for a
period of 1 year.

8. EXECUTION OF CONTRACT : The said Contract as per this quote shall be


completed in 4 months
from 0 date.
0 Date shall be defined as the date of “Letter of Award / Intent ”
alongwith Advance.
The detailed milestone and project execution plan shall be submitted
for information and acceptance.
We assume that Notice to proceed shall be given by Owner upon
achieving Financial Closure. The NTP will be reckoned as date on which
owner instructs in Writing.
REF: KP/SIAE/2020/UP00106 DTD: 06 JAN, 2020

9. LIQUIDATED DAMAGES : We will discuss and conclude the same mutually.

10. JURISDICTION : Any disputes arising during the execution of Contract


shall be subject to Rudrapur Juridiction Uttrakhand.

11. VALIDITY OF QUOTE : If no order has been issued in accordance with this quote
within a period of Four (04) weeks as of the quote date, then the quote shall be
Automatically considered as expired.