FOUNDATION
Preliminaries Excavation cubic meters 83 18000 1,494,000
Setting out Item 1 800000 800,000
Anti termite SM 216 2000 432,000
Sub total 1 2,726,000
SUPER STRUCTURE
Walling Cement Bags 90 30000 2,700,000
sand Magulu Kumi 1 1300000 1,300,000
Hoop iron rolls 103 50000 5,150,000
Concrete blocks No.s 2500 2000 5,000,000
Ring beam and
Cement Bags 30 30000 900,000
columns
Sand forward 2 250000 500,000
Aggregates forward 1 550000 550,000
R7 Roll 30 16500 495,000
Y12 Roll 29 35000 1,015,000
12"X1" pc 45 7500 337,500
2"X2" pc 6 3000 18,000
Nails Kg 30 6500 195,000
Sub total 5 18,160,500
labour 7,264,200