You are on page 1of 32

Supply, Fabrication and Installation of 60 feet single pole antenna

PROJECT: JMT CONSTRUCTION


mast with guy wire and outdoor enclosure / dog house
LOCATION: Bucas Grande Island, Brgy., Navarro (Pob.), Socorro - 9.616194°, 125.955746° & Engineering & Services
OWNER: Microbiz One Inc 4502 General Contractor
SUBJECT: BILL OF QUANTITIES ARCH Design Build
DATE: 11/4/2024 B.O.Q Mono pole Anthena
BILL OF MATERIALS
ITEM NO. DESCRIPTION QUANTITY UNIT UNIT COST AMOUNT
A MOBILIZATION 1.00 lot 18000.00 18,000.00
B CLEARING OF AREA 1.00 lot 3500.00 3,500.00
C TRANSPO & DELEVERY CHARGES 1.00 lot 25000.00 25,000.00
D TEMPORARY FACILITY 1.00 lot 4500.00 4,500.00

Sub-total 51,000.00
E
E.1 EXCAVATION
1 5.00 cu.m. 950 4,750.00
E.2 BACKFILLING / FILLING& COMPACTING 5.00 cu.m. 150 750.00
1 5.00 cu.m. 300 1,500.00
Sub-total 7,000.00

F FORMWORKS & SCAFFOLDINGS 5,600.00

G CONCRETE WORKS (Radio anthena)


G.1 CONCRETE FOOTINGS
1 Portland Cement 10.00 bags. 265.00 2,650.00
2 Screened sand 1.00 cu.m. 1250.00 1,250.00
3 ¾” Gravel 3.00 cu.m. 1450.00 4,350.00
4 10mm Ø Reinforced Steel bar 15.00 pcs. 190.00 2,850.00
5 #16 G.I. Tie Wire 5.00 kgs. 95.00 475.00
G.2 CONCRETE COLUMNS
1 Portland Cement 5.00 bags. 265.00 1,325.00
2 Screened sand 0.50 cu.m. 1250.00 625.00
3 ¾” Gravel 1.00 cu.m. 1450.00 1,450.00
4 10mm Ø Reinforced Steel bar 6.00 pcs. 190.00 1,140.00
5 8mm Ø Reinforced Steel bar 20.00 pcs. 120.00 2,400.00
6 #16 G.I. Tie Wire 3.00 kgs. 90.00 270.00
Sub-total 18,785.00

G.3 STEEL WORKS FABRICATION


1 3" GI S40 PIPE 3"X 20ft 1.00 le 3450.00 3,450.00
2 2" GI S40 PIPE 2"X 20ft 2.00 le 1960.00 3,920.00
3 GuYed WIRE #12 80.00 Mtr 90.00 7,200.00
4 5MM Steel Plate (Cut in Shape) 2.00 sqft 890.00 1,780.00
5 Anchor Bolt 4.00 set 299.00 1,196.00
6 U-Bolt 4.00 set 80.00 320.00
7 Coupling Plunge connector (GI) 12.00 set 650.00 7,800.00
8 Bolt & Knots 24.00 set 24.00 576.00
9 12mm def bars (Ladder) 5.00 le 240.00 1,200.00
16mm def bars (anchor) 2.00 le 350.00 700.00
8 Turn Bucle 24.00 set 280.00 6,720.00
CONSUMABLE
9 Welding Rod 5.00 kl 95.00 475.00
10 Cutting disc 8.00 pcs 120.00 960.00
11 Grinding disc 3.00 set 120.00 360.00
12 Primer Paint 1.00 gal 650.00 650.00
13 Top coat paint 1.00 gal 850.00 850.00
14 Assorted Brush 3.00 set 56.00 168.00
Sub-total 38,325.00
` CONCRETE WORKS (Dog House & Solar Frame)
G.1 CONCRETE Solid
1 Portland Cement 15.00 bags. 265.00 3,975.00
2 Screened sand 1.00 cu.m. 1250.00 1,250.00
3 ¾” Gravel 2.00 cu.m. 1450.00 2,900.00
4 10mm Ø Reinforced Steel bar 8.00 pcs. 190.00 1,520.00
5 2 x 2 x 1/4 angle bar 4.00 pcs. 1150.00 4,600.00
6 Consumable 5.00 set 450.00 2,250.00
Sub-total 16,495.00

L POWER TOOLS 1.00 lot 3500.00 3,500.00


M CLEARING 1.00 lot 2000.00 2,000.00
Sub-total 5,500.00

MATERAL COST 142,705.00


LABOR COST 71,352.50

Summary

DIRECT COST
MATERAL COST 142,705.00
LABOR COST 71,352.50
ESTIMATED DIRECT COST 214,057.50

OCM 7% 14,984.03
CONTRACTORS PROFIT /SUPERVISION FEE 25,686.90
VAT (12 % OF EDC, OCM & PROFIT & PROFIT, OCM & PROFIT) 30,567.41
ESTIMATED INDIRECT COST 71,238.34

GRAND TOTAL 285,295.84

NOTE:
ESITMATED PROJECT DURATION 7-TO 15 WORKING DAYS

SUGESTED MODES OF PAYMENT:

50% DOWNPAYMENT AND 40% PROGRESS BILLING 10% RETENTION

Submitted by : JASON TIBON JMT CONSTRUCTION & ENGINEERING SERVICES


Name of Bidder (company name)
Prepared by : ENGINEER EUGINE LIBOT
Company Representative (Signature over printed Name)
Address : Zone 3 Mohon Tagoloan Misamis Oriental
Project: PROPOSED 1-Storey COMMERCIAL BUILDING
Owner:
Location:

BILL OF MATERIALS
ITEM NO. DESCRIPTION QUANTITY UNIT UNIT COST
A MOBILIZATION
B CLEARING OF AREA
C CLEARING OF DEMOLISHED DEBRIS
D ENCLOSURE OF AREA
Sub-total
E EARTHWORKS
E.1 EXCAVATION
1 Footings
E.2 BACKFILLING / FILLING& COMPACTING
1 Gravel Fill (G1) 7.66 cu.m. 1250
Sub-total
F FORMWORKS & SCAFFOLDINGS
G CONCRETE WORKS
G.1 CONCRETE FOOTINGS
1 Portland Cement 25.00 bags. 285.00
2 Screened sand 2.00 cu.m. 1250.00
3 ¾” Gravel 3.00 cu.m. 1200.00
4 12mm Ø Reinforced Steel bar 31.00 pcs. 330.00
5 #16 G.I. Tie Wire 10.00 kgs. 80.00
G.2 CONCRETE COLUMNS
1 Portland Cement 15.00 bags. 285.00
2 Screened sand 1.00 cu.m. 1250.00
3 ¾” Gravel 2.00 cu.m. 1200.00
4 12mm Ø Reinforced Steel bar 40.00 pcs. 330.00
5 10mm Ø Reinforced Steel bar 0.00 pcs. 190.00
6 #16 G.I. Tie Wire 15.00 kgs. 80.00
G.3 WALL FOOTING
1 Portland Cement 28.00 bags 285.00
2 Screened sand 2.00 cu.m. 1250.00
3 ¾” Gravel 4.00 cu.m. 1200.00
4 10mm Ø Reinforced Steel bar 44.00 pcs. 330.00
5 #16 G.I. Tie Wire 10.00 kgs. 80.00
G.4 CONCRETE BEAMS
1 Portland Cement 23.00 bags 285.00
2 Screened sand 2.00 cu.m. 1250.00
3 ¾” Gravel 3.00 cu.m. 1200.00
4 12mm Ø Reinforced Steel bar 44.00 pcs. 330.00
5 10mm Ø Reinforced Steel bar 33.00 pcs. 130.00
6 #16 G.I. Tie Wire 15.00 kgs. 80.00
G.6 SLAB ON GRADE
1 Portland Cement 63.00 bags 285.00
2 Screened sand 4.00 cu.m. 1250.00
3 ¾” Gravel 7.00 cu.m. 1200.00
4 10mm Ø Reinforced Steel bar 62.00 pcs. 190.00
5 #16 G.I. Tie Wire 15.00 kgs. 80.00
G.7 CHB WALL& PLASTERING
1 CHB 4" 1696.00 nos 15.00
2 Cement 230.00 bags 285.00
3 Screened Sand 6.00 cu.m 1250.00
4 Fine Sand 7.00 cu.m 1400.00
5 Tie wire G.I. #16 10.00 kls 80.00
6 10mmØ x 6m RSB 93.00 pcs 190.00
Sub-total
H ROOF & ROOF FRAMING
1 2"x4" Rafter 184 bd.ft 40.00
2 2"x2" Braces & Purlins 11 bd.ft 40.00
3 1"x10" Fascia Board 49 bd.ft 40.00
4 Asstd. Nails (Kgs.) 8 kgs. 60.00
5 Long Span Deck (pre painted) 25ft length 13 sheets 2,476.40
6 Pre-formed spanish ridge roll 11.10 mts 250.00
7 Umbrella Nails 2.00 kls. 80.00
8 Vulca seal 1.00 tube 75.00
Sub-total
I CEILING WORKS
1 Insulation foam (meter lengthx1m width) 63.0 mts 70.00
Sub-total
J PAINTING WORKS
1 Concrete Neutralizer 5 gals 415.00
2 Boysen Flat Latex White 1 pail 3,200.00
3 Boysen Semi-gloss Latex topcoat 1 pail 3,700.00
5 Masonry putty 1 pail 1,200.00
7 Painting accessories 5 sets 800.00
8 Sand paper (assorted) 10 pcs 150.00
Sub-total
K TILE WORKS
1 Room floor tiles porcelain tiles (60x60) 39.00 pcs 190.00
2 Toilet floor ceramic tiles (30x30) 51.00 pcs 100.00
3 Kitchen counter ceramic tiles (20x20) 22.00 pcs 70.00
4 ABC Tile Adhesive or equivalent 20.00 bags 270.00
Sub-total
L PLUMBING
1 1/2"Ø PVC Pipe (blue) 4.00 pcsx3m 90.00
2 1/2" coupling (blue) 3.00 pcs 20.00
3 1/2" Elbow (blue) 6.00 pcs 20.00
4 1/2" Tee (blue) 2.00 pcs 25.00
5 Gate Valve 1/2" (Falcon) 1.00 pc 400.00
6 4" pipe (orange) 5.00 pcsx3m 550.00
7 4" elbow 45° (orange) 2.00 pcs 160.00
8 4" elbow 90° (orange) 1.00 pcs 160.00
9 4" Wye (orange) 1.00 pcs 160.00
10 4" Cleanout cap 1.00 pcs 80.00
11 4" Tee (orange) 1.00 pcs 170.00
12 2" pipe (orange) 4.00 pcsx3m 225.00
13 2" elbow 90° (orange) 5.00 pcs 45.00
14 2" Wye (orange) 1.00 pcs 160.00
15 PVC Solvent 2.00 cans 70.00
Septic Vault 0.00
16 Cement 52.00 bags 270.00
17 Sand 5.00 cu.m 1,250.00
18 Gravel 2.50 cu.m 1,200.00
19 Fine Sand 1.00 cu.m 1,400.00
20 CHB 4" 428.00 pcs. 15.00
21 12mmØ x 6m RSB 268.00 nos. 190.00
22 4" pipe (orange) 3.00 pcs 550.00
23 4" Tee (orange) 7.00 pcs 180.00
24 Kitchen Sink/faucet/fittings 1.00 sets 2,500.00
25 Water closet & accessories 1.00 set 6,000.00
26 Shower & accessories 1.00 set 2,500.00
27 Lavatory/Fittings/faucet 1.00 set 2,500.00
28 Floor drain 1.00 set 500.00
29 Tissue holder 1.00 set 500.00
30 Soap holder 1.00 set 500.00
Sub-total
M DOORS AND WINDOWS
1 D1 - 2.4x2.3m Fabricated Plywood Door 1.00 set 1,500.00
2 D2 - 0.8x2.1m Fabricated Plywood Door 5.00 sets 5,000.00
3 D3 - 0.7x2.1m Fabricated Plywood Door 2.00 sets 1,800.00
4 Door jambs 8.00 sets 1,500.00
5 W1 - 1.8x1.5m Fabricated Plywood window 1.00 set 500.00
6 W2 - 1.5x1.2m Fabricated Plywood window 2.00 sets 500.00
7 W3 - 2.9x1.3m Fabricated 2" Cyclone window 1.00 set 1,000.00
8 W4 - 1.0x1.5m Fabricated Plywood window 1.00 set 500.00
9 Door Knobs 8.00 sets 800.00
10 Door hinges 21.00 sets 150.00
Sub-total
O ELECTRICAL
1 Panel Board 3 branches 11.00 pcs 350.00
2 Circuit breaker 60amp 0.00 pcs 400.00
3 Circuit breaker 15amp 2.00 pcs 350.00
4 2.0mm2 TW Cu. Wire 40.00 boxes 500.00
5 3.5mm2 TW Cu. Wire 20.00 boxes 500.00
6 1/2"Ø PVC electrical pipes 6.00 pcsx3m 150.00
7 1/2" elbow 3.00 pcs 15.00
8 1/2" PVC clamp 12.00 pcs 3.00
9 Junction box 3.00 pcs 50.00
10 utility box 9.00 pcs 40.00
11 duplex outlets 4.00 pcs 85.00
12 1-gang switch 6.00 pcs 60.00
13 3-gang switch 1.00 pcs 85.00
14 Electrical tape 5.00 pcs 35.00
15 pvc solvent 2.00 cans 80.00
Sub-total
P POWER TOOLS
Q CLEARING
R Material Cost
S Contengencies
T Labor Cost
U Supervison Fee
V TOTAL PROJECT COST

Prepred by:

Engr. Michael John A. Apgao


PRC # 094128
BILL OF MATERIALS
AMOUNT

9,570.00
9,570.00
2,500.00

7,125.00
2,500.00
3,600.00
10,230.00
800.00

4,275.00
1,250.00
2,400.00
13,200.00
0.00
1,200.00

7,980.00
2,500.00
4,800.00
14,520.00
800.00

6,555.00
2,500.00
3,600.00
14,520.00
4,290.00
1,200.00

17,955.00
5,000.00
8,400.00
11,780.00
1,200.00

25,440.00
65,550.00
7,500.00
9,800.00
800.00
17,670.00
280,940.00

7,369.07
437.33
1,941.76
480.00
32,193.20
2,775.00
160.00
75.00
45,431.36

4,410.00
4,410.00

1,937.75
3,735.42
4,319.08
1,400.78
4,000.00
1,500.00
16,893.04

7,410.00
5,100.00
1,540.00
5,400.00
19,450.00

360.00
60.00
120.00
50.00
400.00
2,750.00
320.00
160.00
160.00
80.00
170.00
900.00
225.00
160.00
140.00

14,040.00
6,250.00
3,000.00
1,400.00
6,420.00
50,920.00
1,650.00
1,260.00
2,500.00
6,000.00
2,500.00
2,500.00
500.00
500.00
500.00
105,995.00

1500.00
25000.00
3600.00
12000.00
500.00
1000.00
1000.00
500.00
6400.00
3150.00
54,650.00

3850.00
0.00
700.00
20000.00
10000.00
900.00
45.00
36.00
150.00
360.00
340.00
360.00
85.00
175.00
160.00
37,161.00

577,000.40

Php577,000.40
CONTINGENCY INPUT 10%

Item Description L/H (m) W (m) T (m)

Footings
1 Footing F1 1.0 1.0 0.25

2 Wall Footing 52.0 0.35 0.15


Su
Concrete Class A ColFooting WF Unit
Cement 25 28 bags
Gravel 3 4 cu.m
Sand 2 2 cu.m

Columns
1 Columns C1 3.75 0.2 0.2
2 Columns C2 3.15 0.2 0.2

Su
Concrete Class A Unit
Cement 15.00 bags
Gravel 2.00 cu.m
Sand 1.00 cu.m

Beams
1 Beam B1 12.81 0.2 0.3
2 Beam B2 24.54 0.2 0.3

Su
Concrete Class A Unit
Cement 23.00 bags
Gravel 3.00 cu.m
Sand 2.00 cu.m

Slab
1 Slab on grade 7 9 0.1

Su
Concrete Class A Unit
Cement 63.00 bags
Gravel 7.00 cu.m
Sand 4.00 cu.m
1.1

Rebar length Rebar length


Total Vol. + 10%
Vol. (m3) Qty LONG/ Top&bot TRANS/ Top&bot
Contingency
(m) (m)

0.250 10 2.75 8.4 8.4

2.730 1 3.00 172 67


Subtotal 5.75

Main Bars

Reqd length +
Size
10% contingency

0.15 7 1.16 187.11 8 - 12Ø


0.126 3 0.42 45.54 4 - 12Ø

Subtotal 1.57

No of top bars No of bot. bars

0.769 1 0.845 2 4
1.472 1 1.620 2 4

Subtotal 2.465

Trans (total) Long (total)

6.300 1 6.930 166.85 168.35

Subtotal 6.930
Total Required +
Equivalent no. of
Rebar Size(Ø) 10% contingency
6-meter bars
(m)

12Ø 184.8 31

10Ø 262.2 44

ain Bars Tie Bars


Equiv. nos of 6-
Equiv. nos of 6- Bar length each No. of
Size meter length (w/
meter length tie loop loops/length
10% contingency)
32 0.58 25 10Ø 19
8 0.58 22 10Ø 8

Stirrups
Total length of bars
Eq. nos of 6-
(m) + 10% Rebar Size Size No. of beams
meter length
contingency
84.546 12Ø 15 10Ø 3
170.0622 12Ø 29 10Ø 4

Total rebars length


Total equiv.nos of
(m) + 10% Size
6-meter length
contingency
368.7 10Ø 62
Stirrups

Total No. of stirrup length of Total reqd stirrup Equiv. nos of 6-


loops bar/loop length + 10% (m) meter length

81 0.78 69.498 12
145 0.78 124.41 21
CONTINGENCY INPUT 10%
1.1
MATERIALS SUMMARY FOR STEEL
Qnty Reqd of 6-
Item Total Length meter + 10%
contingency Board Feet
2"x4" Rafter 84.3 16 184.2266667
2"x2" Braces & Purlins 5.0 1 10.93333333
1"x10" Fascia Board 22.2 5 48.544
Asstd. Nails (Kgs.) 8.0 2

CONTINGENCY INPUT 10%


MATERIALS SUMMARY FOR STEEL
Qnty Reqd of 6-
Item Total Length meter + 10%
contingency
2"x4"x1/16"x6m C-Purlins 260.0 48
2"x2"x4mm Angle (Truss) 165.0 31
1"x1"x3mm" Angle (Truss web) 124.8 23
1"x1"x3mm Angle (Angle cleat) 7.7 2
1"x1"x2mm Angle (fascia frame) 80.0 15
10mmØ round bar sag rods 84.8 16
Epoxy Paint, rust proofing (liters) 2
Turco rust converter (liters) 5
Welding rod (kls) 50
Item Reqd length (m) length (ft) Unit price/length
Long Span Deck (pre painted) 13 7.55 24.764 100.00

Pre-formed spanish ridge roll 11.1 250.00

Insulation foam (meter lengthx1m width) 63 70.00


Umbrella Nails 2 80.00

Vulca seal 1 500.00

Item Reqd length (m) length (ft) Unit price/length


Long Span Deck (pre painted) 25 7.55 24.764 100.00
Pre-formed Spanish Gutter/flashing 60 250.00
Pre-formed spanish ridge roll 10.2 250.00
3/4" x 10" pre-cut cement board fascia 24
Insulation foam (meter lengthx1m width) 170 70.00
Tek screw 3 500.00
Rivets 3 500.00
Vulca seal 3 500.00
unit price/pc Subtotal
2,476.40 247,640.00

2,775.00

4,410.00
160.00
-
500.00
Subtotal 254,985.00

unit price/pc Subtotal


2,476.40 247,640.00
15,000.00
2,550.00

11,900.00
1,500.00
1,500.00
1,500.00
Subtotal 280,090.00
CONTINGENCY
INPUT 5%
1.05

Effective Window Area


CHB Wall Length (m) Door Area (sq.m)
Height (m) (sq.m)

Outer walls 2.9 42 17.09 12.81


Division walls 2 9
T&B walls 2.7 7.1

Effective wall
Cement
Cement mortar area + 5% CHB size Screened Sand
"Type-A"
(sq.m)

Outer walls 96.49 4" 76.42 4.20


Division walls 18.90 4" 14.97 0.82
T&B walls 20.13 4" 15.94 0.88

Effective wall Plaster


Wall Area x 2
Plastering wall area + 5% Thickness Cement
face(sq.m)
(sq.m) (mm)

Outer walls 96.49 192.99 25 86.85


Division walls 18.90 37.80 25 17.01
T&B walls 20.13 40.26 25 18.12

MATERIALS SUMMARY FOR MASONRY


Item Qnty Reqd Unit
CHB 4" 1696.0 nos
Cement 230.0 bags
Screened Sand 6.0 cu.m
Fine Sand 7.0 cu.m
Tie wire G.I. #16 10.0 kls
10mmØ x 6m RSB 93.0 pcs
Rebars
Effective wall area Total Reqd length
Required No. Of
(sq.m) + 5% Hor Ver Size (m) + 5%
CHB
contingency contingency
96.49 1207 203.0 203.0 10Ø 426.3
18.90 237 30.0 30.0 10Ø 63.0
20.13 252 32.0 32.0 10Ø 67.1

Fine Sand

4.82
0.95
1.01
CONTINGENCY
INPUT 10% 1.1
Excavation Volumes
Volume
L (m) W (m) D (m) Qty
excavated (m3)

Footing F1 1.0 1.0 1.25 1.25 10

Wall Footing 52.0 0.35 0.55 10.01 1


Total excavation
Filling Materials
Area (sq.m) + Total Volume
Depth of fill (m)
10% contingency of fill (cu.m)

Gravel fill G1 153 0.05 7.66


Soil fill 153 0.15 23.0
Total Volume
Subtotal Area
(m3)

12.5 10.00

10.01 18.20
22.51
CONTINGENCY INPUT 10% 1.1
CEILING MATERIALS

Required Quantity
Qty Unit
+ 10% contingency

Heat Insulator 63 Sq.m 24

Required Quantity
Qty Unit
+ contingency
Cement board 3.5mmx4'x8' 222 Sq.m 0
Metal furring system 222 Sq.m 0
CONTINGENCY INPUT 10 % 1.1
TILEWORKS
Area +10%
Location Area (sq.m) contingency
(sq.m)
Interior walls 97 107
T&B interior 9 10
Exterior walls

Total Paint area 117

Items Unit Required qty


Concrete Neutralizer gals 5
Boysen Flat Latex White pail 1
Boysen Semi-gloss Latex topcoat pail 1
Masonry putty pail 1
Painting accessories set 5
Sand paper pcs (ft) 10
3.891066666667
3.891066666667
3.891066666667
CONTINGENCY INPUT 10% 1.1
TILEWORKS

Tile area
Total Area
(sq.m) + 10% Tile Size
(sqm)
contingency

Room floor tiles porcelain tiles 12.6 13.86 60x60

Toilet floor ceramic tiles 4.2 4.62 30x30


Kitchen counter ceramic tiles 0.8 0.88 20x20

ABC Tile Adhesive or equivalent 20 bags


No. of Tiles Price Subtotal

39 170 Php 6,630.00

51 70 Php 3,570.00
22 50 Php 1,100.00

260 Php 5,200.00


Php 16,500.00
PLUMBING MATERIALS SUMMARY
Item Reqd Unit
1/2"Ø PVC Pipe (blue) 4 pcsx3m
1/2" coupling (blue) 3 pcs
1/2" Elbow (blue) 6 pcs
1/2" Tee (blue) 2 pcs
Gate Valve 1/2" (Falcon) 1 pc
4" pipe (orange) 5 pcsx3m
4" elbow 45° (orange) 2 pcs
4" elbow 90° (orange) 1 pcs
4" Wye (orange) 1 pcs
4" Cleanout cap 1 pcs
4" Tee (orange) 1 pcs
2" pipe (orange) 4 pcsx3m
2" elbow 90° (orange) 5 pcs
2" Wye (orange) 1 pcs
PVC Solvent 2 cans
Septic Vault
Cement 52.0 bags
Sand 5.0 cu.m
Gravel 2.5 cu.m
CHB 4" Chamber walls 428.0 pcs.
Fine Sand 1.0 cu.m
12mmØ x 6m RSB 268.0 nos.
4" pipe (orange) 3 pcs
4" Tee (orange) 7 pcs
Kitchen Sink/faucet/fittings 1 sets
Water closet & accessories 1 set
Shower & accessories 1 set
Lavatory/Fittings/faucet 1 set
Floor drain 1 set
Tissue holder 1 set
Soap holder 1 set
Septic Vault
L (m) W (m) T (m) Req'd Unit
Flooring foundation concrete 4.4 2 0.1 0.88 cu.m
Flooring/foundation rebars 108.90 m
Concrete Footing 11.52 0.35 0.15 0.60 cu.m
Footing Rebars 44.85 m
Top cover concrete 4.4 2 0.1 0.88 cu.m
Top cover rebars, 12Ø 99.90 m
CHB 4" Chamber walls 17.1 2 428.00 pcs
Wall rebars, 12Ø 58.65 m
Cement (mortar) 28.70 bags
Sand (mortar) 2.89 cu.m
Cement (cover/foundation) 19.51 bags
Sand (cover/foundation) 1.18 cu.m
Gravel (cover/foundation) 2.36 cu.m
Length Height Area Cement Fine sand
Internal wall plaster (16mm) 10.8 1.8 19.44 3 1
Item No. Description Qty Unit

1 D1 - 2.4x2.3m Fabricated Plywood Door 1 sets


2 D2 - 0.8x2.1m Fabricated Plywood Door 5 sets
3 D3 - 0.7x2.1m Fabricated Plywood Door 2 sets
4 Door jambs 8 sets
5 W1 - 1.8x1.5m Fabricated Plywood window 1 sets
6 W2 - 1.5x1.2m Fabricated Plywood window 2 sets
7 W3 - 2.9x1.3m Fabricated 2" Cyclone window 1 set
8 W4 - 1.0x1.5m Fabricated Plywood window 1 sets
9 Door Knobs 8 sets
10 Door hinges 21 sets
11 Dead bolt for main doors 11 sets

Item No. Description Qty Unit


1 D1 - 0.8x2.1m solid door panel 10 sets
2 D2 - 0.7x2.1m solid door panel 3 sets
3 D3 - 0.6x2.1m PVC door 10 sets
4 D4 - 0.6x2.1m solid door panel 1 set
5 Door jambs 14 sets
6 W1 - 1.2x1.25m sliding type window 6 sets
7 W1 - 1.0x1.0m sliding type window 6 set
8 W4 - 0.4x0.4m sliding type window 10 sets
9 Cylindrical type (chrome finish) lockset 24 sets
10 Door hinges (heavy duty) 36 sets
11 Dead bolt for main doors 11 sets
Item No. Description
1 2" stainless steel pipe standard (6m length)
2 1" stainless steel pipe standard (6m length)
3 Kitchen counter cabinets
Qty Unit
4 m
14 m
10 set
Items Qty. Unit Items
Fuse Box 245 11 pcs Panel Board 3 branches
Circuit breaker 60amp
Fuse 20 2 pcs Circuit breaker 15amp
2.0mm TW Cu. Wire
2
40 m 2.0mm2 TW Cu. Wire
3.5mm2 TW Cu. Wire 20 m 3.5mm2 TW Cu. Wire
1/2"Ø PVC electrical pipes 6 pcsx3m 1/2"Ø PVC electrical pipes
1/2" elbow 3 pcs 1/2" elbow
1/2" PVC clamp 12 pcs 1/2" PVC clamp
Junction box 3 pcs Junction box
utility box 9 pcs utility box
2-gang outlets 4 pcs 2-gang outlets
1-gang switch 6 pcs 1-gang switch
3-gang switch 1 pcs 2-gang switch
Electrical tape 5 pcs Electrical tape
pvc solvent 2 cans pvc solvent
Qty. Unit
11 pcs
11 pcs
22 pcs
7 boxes
7 boxes
65 pcsx3m
70 pcs
12 pcs
12 pcs
90 pcs
54 pcs
12 pcs
21 pcs
15 pcs
3 cans

You might also like