QUANTITIES FOR CONSTRUCTION OF PROPOSED RESIDENTIAL

HOUSE ON
PLOT No.288 BLOCK No.321 WAKISO DISTRICT FOR MR.
BBOSA

23/3/2023
SUMMARY
ITEM DESCRIPTION MATERIAL
COST
1 SUB TOTAL FOUNDATION WORK 17,620,000
2 SUB TOTAL SUPER STRUCTURE 6,437,000
3 SUB TOTAL ROOF STRUCTURE 33,637,200
GRAND TOTAL FOR SHELL HOUSE 57,694,200

ITEM DESCRIPTION UNIT QTY RATE TOTAL


1 FOUNDATION WORK
Plinth walling in commonred burnt clay
160
1.1 Bricks 230mm (mix 1:5) Sm
Bricks No. 7,000 500 3,500,000
Cement bags 50 36,000 1,800,000
LakeSand Trips 5 260,000 1,300,000
PlasterSand Trips 3.00 260,000 780,000
Hoop Iron rolls 6 40,000 240,000
Hard core filling Trips 15 200,000 3,000,000
Marrum Filling (provision) Trips 35 100,000 3,500,000
Labour item 3,500,000
sub total 2.4 17,620,000

2 SUPER STRUCTURE GROUND FLOOR

2.1 WALLING (MIX 1:5) SM


Damp Proof course Rolls 10 20,000 200,000
Concrete Blocks No. 5,184 2,000 10,368,000
Cement bags 45 36,000 1,620,000
LakeSand Trips 3 260,000 780,000
PlasterSand Trips 2 260,000 520,000
Hoop Iron rolls 6 40,000 240,000
Labour Item 4,000,000
sub Total 3.1 17,728,000
2.2 BEAMS SIZE 200x200 Cm
T12 bars bars 64 38,000 2,432,000
R08 bars bars 50 12,000 600,000
blinding wire Rolls 1 125,000 125,000
Aggregates size 20mm Trips 2 280,000 560,000
Timber 12'' x 1'' Pcs 120 12,000 1,440,000
Nails 3'' Kgs 10 6,000 60,000
4'' Kgs 10 6,000 60,000
Eucalypus Poles Pcs 40 4,000 160,000
Labour Item 1,000,000
sub total 3.3 6,437,000
ROOF
ITEM DESCRIPTION UNIT QTY RATE TOTAL
MATERIAL
Sawn softwood; in trusses, as in
COST
Cypress timber

1.00 100 x 75mm wall plate No. 40 23,000 920,000


1.01 150 x 50mm Tie beams No. 69 23,000 1,587,000
1.02 151 x 50mm Fascia framing along No. 28 23,000 644,000
1.03 100 x 50mm Rafters,Struts and tensioners No. 260 18,000 4,680,000
1.04 100 x 50mm Purlins No. 140 18,000 2,520,000
1.05 100 x 50mm Ridge boards No. 40 18,000 720,000
1.06 100 x 50mm Valley boards No. 12 18,000 216,000
1.07 225 x 22mm Fascia and barge board No. 33 24,000 792,000
1.08 building lines rolls 2 20,000 40,000

Roof covering in versatile roofing sheets

28 Gauge 3M long, pre-painted versatile


88 51,400 4,523,200
1.10 roofing sheets. No.
1.11 Ditto but ridges No. 34 38,000 1,292,000
1.12 Ditto but valleys No. 12 42,000 504,000
1.13 Ridge caps No. 6 15,000 90,000
1.14 Roofing nails kg 25 12,000 300,000
1.15 Hoop iron roll 8 50,000 400,000
1.16 Expanded metal lathe 2.4x0.6M No 33 4,000 132,000
1.17 100 x 50mm for Eaves joists No 30 7,500 225,000
1.18 75 x 50mm eaves brandering No. 28 6,500 182,000
1.19 Cement for eaves all round No. 12 30,000 360,000
1.20 Rubber washers 500pcs. packet No 5 20,000 100,000
1.21 Undercoat 4lt.tin No. 4 54,000 216,000
1.22 Painting Brushes No. 4 5,000 20,000
1.23 Thinner tin 2 30,000 60,000
1.24 Sand paper roll 1 34,000 34,000
1.25 Wire nails 6" kg. 100 5,000 500,000
1.26 Wire nails 5" kg. 90 5,000 450,000
1.27 Ditto but 4" kg. 85 5,000 425,000
1.28 Ditto but 3" kg. 50 5,000 250,000
1.29 Ditto but 2" kg. 50 5,000 250,000
1.30 Ditto but 1 1/2" kg. 25 5,000 125,000
1.31 labour Item 5,000,000

Ceiling

1.32 Expanded metal lathe 2.4x0.6M No 40 4,000 160,000


1.33 100 x 50mm Ceiling joists. No 82 7,500 615,000
1.35 Cement for pricking course No. 25 30,000 750,000
1.36 Wire nails 6" kg. 50 5,000 250,000
1.37 Wire nails 5" kg. 50 5,000 250,000
1.38 Ditto but 4" kg. 50 5,000 250,000
1.39 Ditto but 3" kg. 50 5,000 250,000
1.40 Ditto but 2" kg. 50 5,000 250,000
1.41 Ditto but 1 1/2" kg. 25 5,000 125,000
1.42 labour Item 2,500,000

1.42 TRANSPORT FOR MATERIALS ITEM 680,000

TOTAL ROOF WORK 33,637,200