Professional Documents
Culture Documents
RESIDENTIAL DEVELOPMENT
Comprising;
I) Main house
II)Servants
III)Pit Latrine
IV) Gate house
V) Boundary wall
VI) Landscaping
VII) Main summary
APRIL 2020
MATERIAL SCHEDULE FOR PROPOSED RESIDENTIAL DEVELOPMENT
Item Description Unit Qty Rate UGX Amount UGX
BILL NO.1
MAIN HOUSE (GROUND AND ATTIC FLOOR)
Earthworks
A Allow for setting out, excavation of trenches and pits for
foundations, disposal of excavated material and keeping provisional sum 1 2,615,000 2,615,000
unwanted material out of the excavations
I Allow for timber formwork to support the pad foundations provisional sum 1 270,000 270,000
Hardcore
Q Hardcore ton 79 28,000 2,212,000
Columns
C Cement Bag 18 27,000 486,000
I Allow for timber formwork to support the columns provisional sum 1 546,000 546,000
O Allow for timber formwork to support the floor slab provisional sum 1 570,000 570,000
Staircases
P Cement Bag 10 27,000 270,000
U Allow for timber formwork to support the staircases provisional sum 1 88,000 88,000
Beams
V Cement Bag 45 27,000 1,215,000
D Allow for timber formwork to support the beams provisional sum 1 710,400 710,400
O Pre-painted steel window with burglar proof overall size 1200 x No. 4 432,000 1,728,000
2400mm W-02
P Pre-painted steel window with burglar proof overall size 1200 x No. 1 396,000 396,000
2200mm W-03
Q Pre-painted steel window with burglar proof overall size 900 x No. 2 175,500 351,000
1300mm W-04
R Pre-painted steel window with burglar proof overall size 900 x No. 3 135,000 405,000
1000mm W-05
S Pre-painted steel window with burglar proof overall size 700 x No. 5 105,000 525,000
1000mm W-06
T Pre-painted steel window with burglar proof overall size 600 x No. 11 180,000 1,980,000
2000mm W-07
U Pre-painted steel window with burglar proof overall size 500 x No. 2 135,000 270,000
1800mm W-08
A Pre-painted curved steel window with burglar proof overall size No. 1 471,500 471,500
2000 x 2000mm W-09
B Pre-painted steel window with burglar proof overall size 4325 x No. 1 750,000 750,000
3375mm W-10
C Pre-painted curved steel window with burglar proof overall size No. 6 170,000 1,020,000
600 x 600mm W-11
G Pre-painted glazed steel sliding door overall size 2700 x 2500mm No. 1 2,362,500 2,362,500
with burglur proof D-02
H Pre-painted glazed steel door overall size 1700 x 2500mm with No. 2 1,428,000 2,856,000
burglur proof D-03
I Pre-painted glazed steel door overall size 1200 x 2500mm with No. 2 1,008,000 2,016,000
burglur proof D-04
J Pre-painted glazed steel door overall size 1700 x 2500mm with No. 1 1,487,500 1,487,500
burglur proof D-05
K Pre-painted glazed wooden door overall size 900 x 2400mm D- No. 1 800,000 800,000
06
L Pre-painted glazed wooden door overall size 900 x 2400mm D- No. 7 800,000 5,600,000
07
M Pre-painted glazed wooden door overall size 900 x 2400mm D- No. 8 800,000 6,400,000
08
N Pre-painted glazed steel split door overall size 2950 x 2000mm No. 1 1,177,750 1,177,750
with burglur proof D-09
O Pre-painted glazed steel split door overall size 2075 x 1700mm No. 1 844,000 844,000
with burglur proof D-10
Ceiling Finishes
P 50 x 100mm timber joists No. (10feet) 233 7,500 1,747,500
Floor finishes
P 400 x 400 x 10mm ceramic nonslip floor tiles Box(square meter) 330 32,000 10,560,000
Collection
Earthworks
A Allow for setting out, excavation of trench for foundation,
disposal of excavated material and keeping unwanted material provisional sum 1 768,000 768,000
out of the trench
Hardcore
I Hardcore ton 12 28,000 336,000
Ring beam
Q Cement Bag 5 27,000 135,000
A Allow for timber formwork to support the ring beam provisional sum 1 150,000 150,000
L Pre-painted steel lourvered window overall size 2000 x 400mm No. 2 160,000 320,000
M Pre-painted steel curved window with burglar proof overall size No. 4 157,500 630,000
1500mm diameter W-02
N Pre-painted steel window with burglar proof overall size 700 x No. 1 273,000 273,000
1500mm W-03
Doors
Q Pre-painted glazed steel doors overall size 900 x 2400mm D-01 No. 3 756,000 2,268,000
Ceiling Finishes
R 50 x 100mm timber joists No. (10feet) 24 7,500 180,000
Wall Finishes
D Cement Bag 68 27,000 1,836,000
Floor finishes
L 300 x 300 x 10mm ceramic nonslip floor tiles Box(square meter) 47 32,000 1,504,000
Collection
Earthworks
A Allow for setting out, excavation of pit, disposal of excavated
provisional sum 1 400,000 400,000
material and keeping unwanted material out of the pit
Pit lining
B Clay bricks No. 1,518 200 303,600
Lintols (1:2:4)
R Cement Bag 1 27,000 27,000
Doors
E Pre-painted steel doors overall size 900 x 2400mm D-01 No. 3 300,000 900,000
Finishes
F Cement Bag 26 27,000 702,000
J 300 x 300 x 10mm ceramic nonslip floor tiles Box(square meter) 18 28,000 504,000
Collection
Earthworks
A Allow for setting out, excavation of trenches and pits for
foundations, disposal of excavated material and keeping provisional sum 1 427,000 427,000
unwanted material out of the excavations
I Allow for timber formwork to support the pad foundations provisional sum 1 174,000 174,000
Hardcore
Q Hardcore ton 1.5 28,000 42,000
Columns
E Cement Bag 13 27,000 351,000
K Allow for timber formwork to support the columns provisional sum 1 432,000 432,000
Roof slab
L Cement Bag 3 27,000 81,000
Q Allow for timber formwork to support the floor slab provisional sum 1 96,000 96,000
Beams
R Cement Bag 9 27,000 243,000
X Allow for timber formwork to support the beams provisional sum 1 408,000 408,000
B Pre-painted steel window with burglar proof overall size 300 x No. 1 81,000 81,000
1800mm W-02
C Pre-painted curved steel window with burglar proof overall size No. 2 95,500 191,000
900 x 900mm W-03
Doors
F Pre-painted glazed steel doors overall size 900 x 2400mm D-01 No. 1 756,000 756,000
Ceiling Finishes
G Undercoat litre 2 4,500 9,000
Floor finishes
P 400 x 400 x 10mm ceramic nonslip floor tiles Box(square meter) 4 32,000 128,000
Collection
Earthworks
A Allow for setting out, excavation of trenches for foundations,
disposal of excavated material and keeping unwanted material provisional sum 1 2,300,400 2,300,400
out of the excavations
Finishes
I Cement Bag 75 27,000 2,025,000
Gates
O Pre-painted steel gate overall size 4500 x 2700mm double leaf No. 1 1,350,000 1,350,000
side hung
P Pre-painted steel gate overall size 2300 x 2400mm double leaf No. 2 728,000 1,456,000
side hung
Earthworks
A Allow for setting out, clearing site, making up levels, disposal of
provisional sum 1 2,300,400 2,300,400
excavated material.
E 300x 125 x 250mm Half battered kerbs No. 640 1,500 960,000
MAIN SUMMARY
Page No.
7 Allow a provisional sum of Uganda shillings twenty three Provisional sum 23,000,000
million (UGX 23,000,000/=) for mechanical and electrical
installations