You are on page 1of 2

CHANGE ORDER SAMPLE

DRAWING/S.I. /C.B. Original Contract Change Order Total Amount


NO. DESCRIPTION REASON
REFERENCE Quantity Unit Unit Price Amount Quantity Unit Unit Price Amount Variance
1 MF 1 Concrete 12.48 m3 1,000.00 12,480.00 17.00 m3 1,000.00 17,000.00 4,520.00
2 MF 1 Rebar Re-layout of fire exit stairs 730.37 kg 6.43 4,696.30 1317.30 kg 6.43 8,470.21 3,773.90
3 MF 1 Formworks and adjustment of grids and S-ASB1-202, MDCBP-ASBic- 15.68 m2 350.00 5,488.00 17.12 m2 350.00 5,992.00 504.00
ARIA-13-006 & CB No. ST-002
4 MF 1 Soil Poison column location. 31.28 m2 170.00 5,317.60 38.37 m2 170.00 6,522.90 1,205.30
5 MF 1 Lean Concrete 0.78 m3 1,000.00 780.00 1.50 m3 1,000.00 1,500.00 720.00
6 MF 2 Concrete 36.36 m3 1,000.00 36,360.00 51.00 m3 1,000.00 51,000.00 14,640.00
7 MF 2 Rebar Re-layout of fire exit stairs 4172.66 kg 6.43 26,830.20 7302.07 kg 6.43 46,952.32 20,122.12
S-ASB1-203, MDCBP-ASBic-
8 MF 2 Formworks and adjustment of grids and 23.36 m2 350.00 8,176.00 26.16 m2 350.00 9,156.00 980.00
column location. ARIA-13-006 & CB No. ST-002
9 MF 21 Soil Poison 68.81 m2 170.00 11,697.70 89.91 m2 170.00 15,284.70 3,587.00
10 MF 2 Lean Concrete 2.27 m3 1,000.00 2,272.50 3.50 m3 1,000.00 3,500.00 1,227.50
11 MF 3 Concrete 125.65 m3 1,000.00 125,650.00 138.00 m3 1,000.00 138,000.00 12,350.00
12 MF 3 Rebar Re-layout of fire exit stairs 18606.15 kg 6.43 119,637.54 26600.87 kg 6.43 171,043.59 51,406.04
S-ASB1-204, MDCBP-ASBic-
13 MF 3 Formworks and adjustment of grids and ARIA-13-009 & CB No. ST-003 43.18 m2 350.00 15,112.74 44.18 m2 350.00 15,463.30 350.56
14 MF 3 Soil Poison column location. 200.24 m2 170.00 34,041.10 216.68 m2 170.00 36,835.75 2,794.65
15 MF 3 Lean Concrete 7.85 m3 1,000.00 7,853.13 9.00 m3 1,000.00 9,000.00 1,146.88
16 MF 4 Concrete 18.58 m3 1,000.00 18,576.00 21.00 m3 1,000.00 21,000.00 2,424.00
17 MF 4 Rebar Re-layout of fire exit stairs 1351.63 kg 6.43 8,691.00 1508.57 kg 6.43 9,700.07 1,009.08
18 MF 4 Formworks and adjustment of grids and S-ASB1-203, MDCBP-ASBic- 19.40 m2 350.00 6,790.00 19.90 m2 350.00 6,965.00 175.00
ARIA-13-009 & CB No. ST-003
19 MF 4 Soil Poison column location. 42.62 m2 170.00 7,245.40 46.15 m2 170.00 7,845.50 600.10
20 MF 4 Lean Concrete 1.16 m3 1,000.00 1,161.00 1.50 m3 1,000.00 1,500.00 339.00
21 MF 5 Concrete 43.50 m3 1,000.00 43,504.00 50.00 m3 1,000.00 50,000.00 6,496.00
22 MF 5 Rebar Re-layout of fire exit stairs 3011.73 kg 6.43 19,365.43 5429.91 kg 6.43 34,914.29 15,548.86
23 MF 5 Formworks and adjustment of grids and S-ASB1-205, MDCBP-ASBic- 26.19 m2 350.00 9,166.74 30.75 m2 350.00 10,763.87 1,597.13
ARIA-13-009 & CB No. ST-003
24 MF 5 Soil Poison column location. 80.57 m2 170.00 13,697.02 93.25 m2 170.00 15,853.16 2,156.15
25 MF 5 Lean Concrete 2.72 m3 1,000.00 2,719.00 3.50 m3 1,000.00 3,500.00 781.00
26 MF 6 Concrete 9.92 m3 1,000.00 9,920.00 15.00 m3 1,000.00 15,000.00 5,080.00
27 MF 6 Rebar Re-layout of fire exit stairs 814.05 kg 6.43 5,234.34 1114.07 kg 6.43 7,163.47 1,929.13
S-ASB1-205, MDCBP-ASBic-
28 MF 6 Formworks and adjustment of grids and ARIA-13-009 & CB No. ST-003 16.40 m2 350.00 5,740.00 21.00 m2 350.00 7,350.00 1,610.00
29 MF 6 Soil Poison column location. 28.80 m2 170.00 4,896.00 39.75 m2 170.00 6,757.50 1,861.50
30 MF 6 Lean Concrete 0.62 m3 1,000.00 620.00 1.00 m3 1,000.00 1,000.00 380.00

Bottom of Foundation is 1.5


Excavation Isolated Footings & meters below Adobe Stone
31 Mat Footings Strata 907.86 m3 455.04 413,112.61 1513.45 m3 455.04 688,680.29 275,567.67
32 Additional 2pcs C1
-Concrete Re-layout of fire exit stairs 11.5 m3 1,000.00 11,500.00 11,500.00
and adjustment of grids and CB No. ST-002
-Rebar column location. 5281.14 kg 6.43 33,957.73 33,957.73
-Formworks 96.84 m2 350.00 33,894.00 33,894.00
33 Additional 2pcs C8
-Concrete Re-layout of fire exit stairs 10 m3 1,000.00 10,000.00 10,000.00
and adjustment of grids and CB No. ST-003
-Rebar column location. 3826.52 kg 6.43 24,604.52 24,604.52
-Formworks 88.8 m2 350.00 31,080.00 31,080.00
Shearwall 3 (Sumpit/Retaining
34 Wall)
-Concrete 1.02 m3 1,000.00 1,017.75 1,017.75
-Rebar MDCBP-ASBIC-ARIA-SI-14-021 90 kg 6.43 578.70 578.70
-Formworks 14.26 m2 350.00 4,991.00 4,991.00
-Cutting of Existing Rebars 4,000.00 4,000.00
-Structural Epoxy 5,000.00 5,000.00
-Concrete Epoxy 5,000.00 5,000.00
35 Shearwall 3 Re-layout of fire exit stairs Dimension governed is in
-Concrete and adjustment of grids and 126 m3 1,000.00 126,000.00 135.00 m3 1,000.00 135,000.00 9,000.00
column location. Architectural
-Formworks 854.49 m2 350.00 299,071.50 869.96 m2 350.00 304,486.88 5,415.38

TOTAL 1,411,902.85 2,028,824.50 616,921.65


Vat 12% 169,428.34 243,458.94 74,030.60

GRAND TOTAL 1,581,331.20 2,272,283.44 690,952.25

You might also like