You are on page 1of 2

CHANGE ORDER SAMPLE

DRAWING/S.I. /C.B. Original Contract Change Order Total Amount


NO. DESCRIPTION REASON Remarks
REFERENCE Quantity Unit Unit Price Amount Quantity Unit Unit Price Amount Variance
1 MF 1 Concrete 12.48 m3 1,000.00 12,480.00 17.00 m3 1,000.00 17,000.00 4,520.00 Additive
2 MF 1 Rebar Re-layout of fire exit stairs 730.37 kg 6.43 4,696.30 1317.30 kg 6.43 8,470.21 3,773.90 Additive
S-ASB1-202, MDCBP-ASBic-
3 MF 1 Formworks and adjustment of grids and 15.68 m2 350.00 5,488.00 17.12 m2 350.00 5,992.00 504.00 Additive
ARIA-13-006 & CB No. ST-002
4 MF 1 Soil Poison column location. 31.28 m2 170.00 5,317.60 38.37 m2 170.00 6,522.90 1,205.30 Additive
5 MF 1 Lean Concrete 0.78 m3 1,000.00 780.00 1.50 m3 1,000.00 1,500.00 720.00 Additive
6 MF 2 Concrete 36.36 m3 1,000.00 36,360.00 51.00 m3 1,000.00 51,000.00 14,640.00 Additive
7 MF 2 Rebar Re-layout of fire exit stairs 4172.66 kg 6.43 26,830.20 7302.07 kg 6.43 46,952.32 20,122.12 Additive
S-ASB1-203, MDCBP-ASBic-
8 MF 2 Formworks and adjustment of grids and 23.36 m2 350.00 8,176.00 26.16 m2 350.00 9,156.00 980.00 Additive
ARIA-13-006 & CB No. ST-002
9 MF 21 Soil Poison column location. 68.81 m2 170.00 11,697.70 89.91 m2 170.00 15,284.70 3,587.00 Additive
10 MF 2 Lean Concrete 2.27 m3 1,000.00 2,272.50 3.50 m3 1,000.00 3,500.00 1,227.50 Additive
11 MF 3 Concrete 125.65 m3 1,000.00 125,650.00 138.00 m3 1,000.00 138,000.00 12,350.00 Additive
12 MF 3 Rebar Re-layout of fire exit stairs 18606.15 kg 6.43 119,637.54 26600.87 kg 6.43 171,043.59 51,406.04 Additive
S-ASB1-204, MDCBP-ASBic-
13 MF 3 Formworks and adjustment of grids and 43.18 m2 350.00 15,112.74 44.18 m2 350.00 15,463.30 350.56 Additive
ARIA-13-009 & CB No. ST-003
14 MF 3 Soil Poison column location. 200.24 m2 170.00 34,041.10 216.68 m2 170.00 36,835.75 2,794.65 Additive
15 MF 3 Lean Concrete 7.85 m3 1,000.00 7,853.13 9.00 m3 1,000.00 9,000.00 1,146.88 Additive
16 MF 4 Concrete 18.58 m3 1,000.00 18,576.00 21.00 m3 1,000.00 21,000.00 2,424.00 Additive
17 MF 4 Rebar Re-layout of fire exit stairs 1351.63 kg 6.43 8,691.00 1508.57 kg 6.43 9,700.07 1,009.08 Additive
S-ASB1-203, MDCBP-ASBic-
18 MF 4 Formworks and adjustment of grids and 19.40 m2 350.00 6,790.00 19.90 m2 350.00 6,965.00 175.00 Additive
ARIA-13-009 & CB No. ST-003
column location.
19 MF 4 Soil Poison 42.62 m2 170.00 7,245.40 46.15 m2 170.00 7,845.50 600.10 Additive
20 MF 4 Lean Concrete 1.16 m3 1,000.00 1,161.00 1.50 m3 1,000.00 1,500.00 339.00 Additive
21 MF 5 Concrete 43.50 m3 1,000.00 43,504.00 50.00 m3 1,000.00 50,000.00 6,496.00 Additive
22 MF 5 Rebar Re-layout of fire exit stairs 3011.73 kg 6.43 19,365.43 5429.91 kg 6.43 34,914.29 15,548.86 Additive
S-ASB1-205, MDCBP-ASBic-
23 MF 5 Formworks and adjustment of grids and 26.19 m2 350.00 9,166.74 30.75 m2 350.00 10,763.87 1,597.13 Additive
ARIA-13-009 & CB No. ST-003
column location.
24 MF 5 Soil Poison 80.57 m2 170.00 13,697.02 93.25 m2 170.00 15,853.16 2,156.15 Additive
25 MF 5 Lean Concrete 2.72 m3 1,000.00 2,719.00 3.50 m3 1,000.00 3,500.00 781.00 Additive
26 MF 6 Concrete 9.92 m3 1,000.00 9,920.00 15.00 m3 1,000.00 15,000.00 5,080.00 Additive
27 MF 6 Rebar Re-layout of fire exit stairs 814.05 kg 6.43 5,234.34 1114.07 kg 6.43 7,163.47 1,929.13 Additive
S-ASB1-205, MDCBP-ASBic-
28 MF 6 Formworks and adjustment of grids and 16.40 m2 350.00 5,740.00 21.00 m2 350.00 7,350.00 1,610.00 Additive
ARIA-13-009 & CB No. ST-003
column location.
29 MF 6 Soil Poison 28.80 m2 170.00 4,896.00 39.75 m2 170.00 6,757.50 1,861.50 Additive
Bottom of Foundation is 1.5
30 MF 6 Lean Concrete
Excavation Isolated Footings & meters below Adobe Stone 0.62 m3 1,000.00 620.00 1.00 m3 1,000.00 1,000.00 380.00 Additive
31 Mat Footings Strata 907.86 m3 455.04 413,112.61 1513.45 m3 455.04 688,680.29 275,567.67 Additive
32 Additional 2pcs C1
-Concrete Re-layout of fire exit stairs 11.5 m3 1,000.00 11,500.00 11,500.00 Additive
and adjustment of grids and CB No. ST-002
-Rebar column location. 5281.14 kg 6.43 33,957.73 33,957.73 Additive
-Formworks 96.84 m2 350.00 33,894.00 33,894.00 Additive
33 Additional 2pcs C8
-Concrete Re-layout of fire exit stairs 10 m3 1,000.00 10,000.00 10,000.00 Additive
and adjustment of grids and CB No. ST-003
-Rebar column location. 3826.52 kg 6.43 24,604.52 24,604.52 Additive
-Formworks 88.8 m2 350.00 31,080.00 31,080.00 Additive
Shearwall 3 (Sumpit/Retaining
34 Wall)
-Concrete 1.02 m3 1,000.00 1,017.75 1,017.75 Additive
-Rebar 90 kg 6.43 578.70 578.70 Additive
MDCBP-ASBIC-ARIA-SI-14-021
-Formworks 14.26 m2 350.00 4,991.00 4,991.00 Additive
-Cutting of Existing Rebars 4,000.00 4,000.00 Additive
-Structural Epoxy 5,000.00 5,000.00 Additive
-Concrete Epoxy 5,000.00 5,000.00 Additive
35 Shearwall 3 Re-layout of fire exit stairs
Dimension governed is in
-Concrete and adjustment of grids and 126 m3 1,000.00 126,000.00 135.00 m3 1,000.00 135,000.00 9,000.00 Additive
Architectural
column location.
-Formworks 854.49 m2 350.00 299,071.50 869.96 m2 350.00 304,486.88 5,415.38 Additive

TOTAL 1,411,902.85 2,028,824.50 616,921.65


Vat 12% 169,428.34 243,458.94 74,030.60

GRAND TOTAL 1,581,331.20 2,272,283.44 690,952.25