SUMMARY
Item Description Unit Total amount
1
MELKA ODA HOSPITAL
B. SUPERSTRUCTURE
2
MELKA ODA HOSPITAL
2. CONCRETE WORK -
Cast 50mm thick lean concrete quality C-7
2.10
minimum PPC , 150 kg of cement/m3, -
a) Under Footing pad
m2 264.00 320.00 84,480.00
b) Under Masonry foundation m2 209.00 320.00 66,880.00
c) Under 10cm thick floor slab m2 770.00 320.00 246,400.00
10cm thick reinforced concrete ground floor
slab of concrete quality class C-20 with
2.30 minimum OPC cement content of 320kg/m3
well spread and leveled around Ø 8mm
deformed steel bar (mesh). m2 770.00 800.00 616,000.00
Reinforced concrete class C-25 with
minimum OPC cement content of 360kg/m3
2.40
filled into formwork and vibrated around rod
reinforcement. - -
a) to footing pad m3 108.90 5,100.00 555,390.00
3
MELKA ODA HOSPITAL
4
MELKA ODA HOSPITAL
5
MELKA ODA HOSPITAL
6
MELKA ODA HOSPITAL
7
MELKA ODA HOSPITAL
8
MELKA ODA HOSPITAL
9
MELKA ODA HOSPITAL
10
MELKA ODA HOSPITAL
11
MELKA ODA HOSPITAL
12
MELKA ODA HOSPITAL
13
MELKA ODA HOSPITAL
14
MELKA ODA HOSPITAL
15
MELKA ODA HOSPITAL
16
MELKA ODA HOSPITAL
17
MELKA ODA HOSPITAL
18
MELKA ODA HOSPITAL
19
MELKA ODA HOSPITAL
20
Item
A. SUBSTRUCTURE
B. SUPERSTRUCTURE
21
MELKA ODA HOSPITAL
-
Provide Selected granular material fill brought
1.50 m3
from out side the site and fill around footing 2,178.00 539.26 1,174,508.28
- -
Cart away surplus excavated material from the
1.60 m3
site to an appropriate point as per the engineer's 1,815.00 413.00 749,595.00
- -
250mm thick basaltic stone hardcore well
1.70 m2
rolled, consolidated and blinded with crushed 703.38 450.00 316,521.00
-
Total Carried to Summary - 2,612,313.87
2. CONCRETE WORK -
50mm lean concrete minimum ppc cement
2.10
quality C-7, 150 kg of cement/m3, -
a) Under Footing pad m2 275.00 320.00 88,000.00
b) Under Masonry foundation m2 218.90 320.00 70,048.00
c) Under 10cm thick floor slab m2 773.72 320.00 247,589.76
- -
22
MELKA ODA HOSPITAL
23
MELKA ODA HOSPITAL
25
MELKA ODA HOSPITAL
27
MELKA ODA HOSPITAL
29
MELKA ODA HOSPITAL
30
MELKA ODA HOSPITAL
32
MELKA ODA HOSPITAL
33
MELKA ODA HOSPITAL
34
MELKA ODA HOSPITAL
35
MELKA ODA HOSPITAL
36
MELKA ODA HOSPITAL
37
MELKA ODA HOSPITAL
38
MELKA ODA HOSPITAL
39
MELKA ODA HOSPITAL
40
MELKA ODA HOSPITAL
ELEVATORS
Item Description Unit Qty Rate Amount
Type - Mitsubishi -Japan or equivalent Electrical
1.1
Hospital Beds Lift
Capacity - 16 Persons/1600kg.
No. of Floors- 2
Travel 4000mm
Machine Room
W 4500mm
D 2500mm
H 2700mm
Position -Top
VVVF - Included
Power Supply - Main 380 V
- Light 220 V
Car Internal Size
W 1500mm
D 24000mm
H 2150mm
Car Wall Finish - pattern printed steel sheet
Car Door
Type- Automatic, Four Panel, Centre
parting Door
W 1100mm
H 2000mm 41
Car Door Finish - Pattern printed steel sheet
Landing Door
Item Description Unit Qty Rate Amount
Ceiling Model and Illumination -Std .With Indirect
Suspended Fluorescent.
42
Item Description Unit Qty Rate Amount
Photo Cell- Single
Emergency Rescue Device- Included
MOTION AND OPERATION CONTROL
- Programmable full collective micro processor
motion control system, automatic error detecting and
monitoring facilities and regulated acceleration and
deceleration allowing to enhance smooth starting and
stopping of the car with perfect automatic levelling.
- Key switch in car operating panel (c.o.p) for
attendant control
43
Item Description Unit Qty Rate Amount
- All the wiring and protection of the installation
shall be as per the accepted European standard code
for electric passenger lifts EN 81.
GUIDE RAILS AND GUIDE SHOES
- Guide rails - cold drawn, Iso code - T90-A
(16x75x90x5000) and T 50/A(5x50x50x5000) for Car
and C.W.
- Sliding shoes for the car to be supplied with oiler to
provide noise and vibration free riding
- Sliding shoes for counterweight. No 2.00 7,500,000.00 15,000,000.00
44
Item
A. SUBSTRUCTURE
B. SUPERSTRUCTURE
9 Glazing Birr
45
MELKA ODA HOSPITAL
1.1 Clear of the site to an average depth of 20cm m2 319.00 14.54 4,638.26
- - -
Excavate to bulk in ordinary soil to a depth of
1.2 m3 253.00 224.20 56,722.60
80cm starting from the reduced level.
- - -
1.3 Ditto,but - - -
47
MELKA ODA HOSPITAL
48
MELKA ODA HOSPITAL
49
MELKA ODA HOSPITAL
50
MELKA ODA HOSPITAL
51
MELKA ODA HOSPITAL
52
MELKA ODA HOSPITAL
53
MELKA ODA HOSPITAL
55
Item
A. SUBSTRUCTURE
B. SUPERSTRUCTURE
56
MELKA ODA HOSPITAL
- - -
Excavate to bulk in ordinary soil to a depth of
1.2 m3
80cm from reduced level. 481.10 224.20 107,862.62
- - -
1.3 Ditto,but
- - -
a) Soft rock m3
11.00 295.00 3,245.00
b) Bolder rock m3
16.50 413.00 6,814.50
c) Hard rock m3
5.50 767.00 4,218.50
a) Excavation to Footing to a depth of 150cm
1.4 m3
from reduced level. 398.20 354.00 140,962.80
b) Ditto but to a depth greater than 150cm but
m3
less than 300cm from reduced level. 379.50 413.00 156,733.50
- - -
Provide Selected granular material fill brought
1.5 m3
from out side the site and fill around footing 1,052.70 539.26 567,679.00
- - -
Cart away surplus excavated material from the
1.6 site to an appropriate point as per the m3
engineer's instruction (not more than 5KM). 1,102.72 413.00 455,423.36
- - -
250mm thick basaltic stone hardcore well
1.7 rolled, consolidated and blinded with crushed m2
stone . 229.90 450.00 103,455.00
- -
Total Carried to Summary 1,554,295.32
2. CONCRETE WORK
50mm lean concrete quality C-7, 150 kg of
2.1
cement/m3,
a) Under Footing pad m2 170.50 320.00 54,560.00
b) Under Masonry foundation m2 134.20 320.00 57
42,944.00
b) Under 10cm thick floor slab m2 229.90 320.00 73,568.00
MELKA ODA HOSPITAL
3. MASONRY WORK
Construct 50cm wide (thick) Trychitic or
equivalent stone masonry foundation wall
3.1 m3
bedded in cement mortar 1:3 to a minimum
depth of 100cm 133.1 2699.84 359,348.70
- 0.00 -
Ditto but well dressed stone masonary wall
3.2 Above NGL externally pointed in 1:3 cement m3
mortar. Price includes pointing. 53.9 3187.18 171,789.00
58
MELKA ODA HOSPITAL
1. CONCRETE WORK
2. BLOCK WORK
3.ROOFING
60
MELKA ODA HOSPITAL
5. STEEL STRUCTURE
61
MELKA ODA HOSPITAL
62
MELKA ODA HOSPITAL
63
MELKA ODA HOSPITAL
64
MELKA ODA HOSPITAL
65
MELKA ODA HOSPITAL
66
MELKA ODA HOSPITAL
67
MELKA ODA HOSPITAL
68
MELKA ODA HOSPITAL
69
MELKA ODA HOSPITAL
70
MELKA ODA HOSPITAL
71
MELKA ODA HOSPITAL
B. SUPERSTRUCTURE
5 Steel structure
72
MELKA ODA HOSPITAL
- -
1.20 Excavate to bulk in ordinary soil to a depth of
80cm from reduced level. m3 48.00 224.20 10,761.60
- -
1.30 Ditto,but
- -
a) Soft rock
m3 5.00 295.00 1,475.00
b) Bolder rock
m3 4.00 413.00 1,652.00
c) Hard rock
m3 3.00 767.00 2,301.00
1.40 a) Excavation to Footing to a depth of 150cm from
reduced level. m3 49.00 354.00 17,346.00
b) Ditto but to a depth greater than 150cm but less
than 300cm from reduced level. m3 78.00 413.00 32,214.00
- -
1.50 Provide Selected granular material fill brought from
out side the site and fill around footing and under m3 49.00 539.26 26,423.74
- -
1.70 250mm thick basaltic stone hardcore well rolled,
consolidated and blinded with crushed stone . m2 42.00 450.00 18,900.00
Total Carried to Summary - 144,712.26
2. CONCRETE WORK -
2.10 50mm lean concrete quality C-7, 150 kg of
cement/m3, -
a) Under Footing pad m2 9.00 320.00 2,880.00
b) Under Masonry foundation m2 18.00 320.00 5,760.00
c) Under 10cm floor slab m2 42.00 320.00 13,440.00
2.20 10cm thick reinforced concrete ground floor slab
class C-20 with minimum cement content of
320kg/m3 well spread and leveled oround Ø 8mm
deformed steel bar. m2 42.00 510.00 21,420.00
2.30 Reinforced concrete class C-25 with minimum 73
cement content of 360kg/m3 filled into formwork
MELKA ODA HOSPITAL
75
MELKA ODA HOSPITAL
76
MELKA ODA HOSPITAL
78
MELKA ODA HOSPITAL
stand % complete with all the necessary accessories. No 1.00 14,160.00 14,160.00
9.15
Supply & fix 50 mm diameter floor drain made of - -
enamelled cast-iron with smell trap & all
accessories. No 1.00 1,770.00 1,770.00
9.17 Supply and fix Diameter 110 UPVC. - -
Down Pipe. secured to wall with - -
metal straps at ever 10cm interval. LM 32.00 1,003.00 32,096.00
- -
9.18 Supply &B275 mount fire extingushers of class - -
79
MELKA ODA HOSPITAL
80
MELKA ODA HOSPITAL
81
Item
A. SUBSTRUCTURE
1 Excavation and Earth work Birr 27,324.68
B. SUPERSTRUCTURE
5 Ssteel structure
82
MELKA ODA HOSPITAL
1.1
14.54
Clear off the site to an average depth of 30cm m2 38.0 552.52
-
0.00
1.2 Excavate to bulk in ordinary soil to a depth of
224.20
80cm from reduced level. m3 8.0 1793.60
-
0.00
1.3 Ditto,but
-
0.00
a) Soft rock
295.00
m3 5.0 1475.00
b) Bolder rock
413.00
m3 4.0 1652.00
c) Hard rock
767.00
m3 2.0 1534.00
1.4 a) Excavation to Footing to a depth of 150cm from
354.00
reduced level. m3 5.0 1770.00
b) Ditto but to a depth greater than 150cm but less
413.00
than 300cm from reduced level. m3 4.0 1652.00
-
0.00
1.5 Provide Selected granular material fill brought from
539.26
out side the site and fill around footing and under m3 6.0 3235.56
-
0.00
1.6 Cart away surplus excavated material from the site
to an appropriate point as per the engineer's 413.00
instruction (not more than 5KM). m3 20.0 8260.00
- 0.00
1.7 250mm thick basaltic stone hardcore well rolled,
450.00
consolidated and blinded with crushed stone . m2 12.0 5400.00
-
Total Carried to Summary - 27,324.68
2. CONCRETE WORK -
2.1 50mm lean concrete quality C-7, 150 kg of
cement/m3, -
a) Under Footing pad m2 5.0 320.00 1,600.00
b) Under Masonry foundation m2 7.0 320.00
832,240.00
c) Under 10cm floor slab m2 12.0 320.00 3,840.00
- -
2.3 Reinforced concrete class C-25 with minimum
OPCcement content of 360kg/m3 filled into
formwork and vibrated around rod reinforcement.
- -
a) to footing pad m3 2.0 5,100.00 10,200.00
b) to footing column m3 1.0 5,100.00 5,100.00
c) to grade beam m3 2.0 5,100.00 10,200.00
5,100.00 -
2.4 Provide, cut and fix in position machin cut
Australia pinus wood or metal panel formwork
which ever appropriate. - -
a) to footing pad m2 12.0 675.00 8,100.00
b) to footing column m2 3.0 675.00 2,025.00
c) to grade beam m2 7.0 675.00 4,725.00
- -
2.5 Reinforced steel bar according to structural
drawings.price include cutting bending & placing in
position. - -
a) Dia.08 deformed bar kg 130.0 110.00 14,300.00
b) Dia.10 deformed bar kg 110.00 -
c) Dia.12 deformed bar kg 70.0 110.00 7,700.00
d) Dia.14 deformed bar kg 120.0 110.00 13,200.00
e) Dia.16 deformed bar kg 110.00 -
f) Dia.20 deformed bar kg 110.00 -
-
2.6 12/2 cm chipwood expansion joint b/n G.beam and
slab painted with two coats of asphalt ml 16.0 194.94 3,119.04
Total Carried to Summary - 92,469.04
-
3. MASONRY WORK -
3.1 Construct 50cm wide (thick) Trychitic or equivalent
stone masonry foundation wall bedded in cement
mortar 1:3 to a minimum depth of 100cm
m3 6.0 2,699.84 16199.04
- 0.00
3.2 Ditto but well dressed stone masonary wall Above
NGL externally pointed in 1:3 cement mortar.
Price includes pointing. m3 3.0 3,187.18 9561.54
-
Total Carried to Summary - 25,760.58
-
84
B. SUPERSTRUCTURE -
-
1. CONCRETE WORK -
5,100.00
1.1 Reinforced concrete class C-25 reinforced concrete
with a minimum cement content of 360kg/m3 to be
poured into formwork around reinforcement steel
bar. (formwork and reinforcement measured
separately) 5,100.00
a) In elevation columns m3 1.0 5,100.00 5,100.00
b) In intermediate beam m3 - -
c) in top tie beam m3 1.0 5,100.00 5,100.00
d) Floor slab m2 5,100.00 -
e) in parapet m3 - -
f) in Lintel m3 - -
675.00 -
1.2 Provide, cut and fix in position machin cut
Australia pinus wood or metal panel formwork
which ever appropriate. 675.00 -
a) In elevation columns m2 10.0 675.00 6,750.00
b) In intermidiat beam m2 675.00 -
c) in top tie beam m2 11.0 675.00 7,425.00
d) Floor slab m2 675.00 -
e) in parapet m2 - -
F) in Lintel m2 110.00 -
1.3 steel reinforcement according to structural
drawings. Price includes cutting, bending, placing
in position and tying wire and required spacers. 110.00 -
a) Dia.06 plain bar kg 110.00 -
a) Dia.08 deformed bar kg 25.0 110.00 2,750.00
b) Dia.10 deformed bar kg 110.00 -
c) Dia.12 deformed bar kg 120.0 110.00 13,200.00
d) Dia.14 deformed bar kg 110.00 -
e) Dia.16 deformed bar kg - -
f) Dia.20 deformed bar kg - -
-
Total Carried to Summary - 40,325.00
-
2. BLOCK WORK -
85
-
3.ROOFING
86
D1= 90x270cm No. 1.0 15,770.70 15,770.70
WINDOW - -
W1= 98*200cm No. 2.0 12,720.40 25,440.80
Total Carried to Summary - 41,211.50
6. FINISHING -
Finishing work shall includes all surface pre
cleaning, preparation of finish, polishing and
cleaning at the end of finishing work.
-
6.1 Apply two coats of plastering to external HCB &
concrete surface to recive quartiz paint. m2 55.0 295.00 16,225.00
- -
6.2 Apply three coats of plastering to water exposed
area to receive plastic paint. m2 60.0 330.00 19,800.00
- -
6.3 Apply two coats of plastering to receive gypsum to
non water exposed area. m2 80.0 796.37 63,709.60
- -
6.4 Supply and fix SUSPENDING (Armistrong m2
ceilings ) as per the engineers approval. Price shall
include purlin & battens with c/c spacing of 600
mm both ways, middle and corner list and all other
necessary accessories. 12.0 3,481.00 41,772.00
- -
- -
6.6 Supply & lay best & Approved type 60x60x8mm
thick non slippery ceramic tile (RAK or Equvalent)
flooring bedded on and including 42mm thick
mortar 1:3 ratio & joints grouted with cement.
m2 12.0 1,416.00 16,992.00
- -
6.7 Ditto but 10 cm thick Ceramic skirting bedded on
and including cement mortar backing. ml 15.0 348.10 5,221.50
- -
6.8 Supply and lay best & Approved type Marble
window cill bedded on cement mortar.Size 27/3cm
m 2.0 2,950.00 5,900.00
- -
6.90 30/30/3mm angle iron corner protection bedded
into wall H=150cm m 1,003.00 -
- -
87
6.10 Construct 10 cm thick C-20 RC 120cm wide
pavement (including 4Ø 8 deformed bar mesh
expnasion joint at every 120cm, The
work includes 80 cm bulk excavation, 55 cm thick
selected material fill, 20 cm basaltic hard core and
cart away). m2 20.0 1,086.07 21,721.40
6.11 Supply and lay storm water half concrete pipe of
diameter 30cm with a minimum slope of 2% or
natural ground slope which ever is greater on and
including a firm bed of red ash 100mm thick below.
The joints shall be grouted in cement sand mortar
of (1:3). Price shall include 15cm thick concret curb
stone and all the necessary earth work
ml 23.0 1,183.54 27,221.42
6.12
Construction of 10x40 cm curb stone along the
drive way, walk way, around island and others as in
the drawing in concrete C-15 280kg of cement/m3
and joints shall be in cement mortarPrice shall
include formwork, reinforcement, expansion joint,
5cm thick lean concrete in C-5 and all the necessary
excavation work. (Re-bar shall be of 4 diameter
8mm deformed main bar and stirrups of diameter
6mm c/c25cm.) ml 23.0 1,183.54 27,221.42
Total to summary ………Birr - 245,784.34
7. PAINTING
Prepare and apply by brush three coats of plastic
emulsion paint to: -
7.1
Apply quartize Paint to external plastered surface. m2 55.0 377.60 20768
- 0
7.2 Apply syntetic paint to internal plastered surface to
the hight of 150cm m2 46.0 141.00 6486
- 0
7.3 Ditto but plastic paint above 150cm m2 92.0 141.00 12972
- 0
7.4 Ditto but to slab and stair case sofit m2 - 0
-
Total Carried to Summary - 40,226.00
8. GLAZING -
Supply and fix glass to metal doors windows &
wooden doors as shown on the schedul with proper
imported putty bedding.
-
8.1 4mm thick clear glass m2 4.00 2,006.00 8024
- 0
88
8.2 4mm thick frosted glass for woodene doors m2 2,596.00 0
- 0
8.3 6mm thick louver glass 3,540.00 0
Total Carried to Summary - 8,024.00
9 Electrical Installations -
Supply and install surface mounted sub distribution
9.1 board -
(SDB GH 1) IP 44 made of approved quality
standard steel metal -
with lockeable door and separate earthing , nuetral,
phase -
bus bars 40A/25 KA rating and consisting of -
2pc MCB of 10 A (1 - ph) -
1 pcs MCB of 16 A (1 - ph) -
1 pcs MCB of 16 A (3 - ph)
1 pcs MCB of 20 A (3 - ph) -
complete with accessories and ample for reserve
space No 1 45,000.00 45000
9.2 Light Points - 0
Light points feed through PVC insulated cooper
9.2.1 conductor of - 0
3*2.5 m2 inside PVC conduite of 16 mm diametre
for rec - 0
essed installatio, including junction boxes with
covers & - 0
insulating type screw cap connectors for complete
installation No 6 2,596.00 15576
Extra over light points flush/surface mounted
9.2.2 legrand diplomatic - 0
cover with mechanism - 0
o
a) Single pole switch N 2 767.00 1534
b) Two circute switch No 1 1,003.00 1003
o
c) Two way switches N 2 1,416.00 2832
Socket Out Lets( Siements Shuko type) legrand
9.3 mosaic plate - 0
with frame and boxes - 0
Flush mounted socket out let of 10/16 A ( 1- ph )
9.3.1 with earthing - 0
contact terminal and feed through PVC conduite of
16 mm diametre for recessed - 0
89
o
socket of 16 A and accessories. N 3 1,770.00 5310
Tele phone system - 0
Price shall include related works and accessories - 0
a) RJ 11 out let type legrand mosaic cover with
rocker and - 0
and mechanism complete with clip on support
frame and - 0
o
labling accessories. N 1 2,360.00 2360
90
MELKA ODA HOSPITAL
BLOCK DRY LATERINE Unit
Item
Description Amount (Birr)
A. SUBSTRUCTURE
B. SUPERSTRUCTURE
5 Ssteel structure -
9 Glazing Birr -
91
MELKA ODA HOSPITAL
1.1 Clear off the site to an average depth of 30cm m2 50.00 14.54 727.00
Pit excavation in ordinary soil to level for a depth of
1.2 m3 90.00 224.20 20,178.00
150cm from reduced level.
1.3 Ditto but over 1.50mts but less than 4 meters m3 90.00 600.00 54,000.00
Provide Selected granular material fill brought from
1.4 m3 90.00 539.26 48,533.40
out side the site and fill under hard core area and
Cart away surplus excavated material from the site to
1.5 m3 190.00 413.00 78,470.00
an appropriate point as per the engineer's instruction
250mm thick basaltic stone hardcore well rolled,
1.6 m2 24.00 450.00 10,800.00
consolidated and blinded with crushed stone .
TOTAL CARRIED TO SUMMARY - 212,708.40
2. CONCRETE WORK -
50mm lean concrete quality C-7, 150 kg of
2.1
cement/m3,
a) Under 10cm thick floor slab m2 24.00 320.00 7,680.00
92
Description Unit Qty Rate Amount
No
c/ diameter 6mm plain bars. Kg 35.00 110.00 3,850.00
TOTAL CARRIED TO SUMMARY - 109,510.00
3. Masonry work. -
Construct stone masonry foundation wall bedded in
cement mortar 1:3 to the dimension as specified on
3.1 the respective design. Price includes all other m3 47.00 2,699.84 126,892.48
associated works and materials including pointing in
1:3 cement sand mortar to the Masonry ANGL.
TOTAL CARRIED TO SUMMARY - 126,892.48
B. SUPER STRUCTURE -
I. CONCRETE WORKS -
Reinforced concrete class C-25 reinforced concrete
with a minimum cement content of 360kg/m3 to be
1.1 poured into formwork around reinforcement steel -
bar. (formwork and reinforcement measured
separately)
a) In elevation columns m3 1.00 5,100.00 5,100.00
b) In top beams m3 2.00 5,100.00 10,200.00
c) In lintels m3 5,100.00 -
Provide, cut and fix in position machin cut Australia
1.2 pinus wood or metal panel formwork which ever - -
appropriate.
a) To elevation columns m2 15.00 675.00 10,125.00
b) To top beams m2 18.00 675.00 12,150.00
c) To lintel m2 675.00 -
93
Description Unit Qty Rate Amount
No
Supply and fix G-28 flat metal sheet gutter as per the
3.2 detail drawing. Price shall include all other necessary ml 31.00 1,557.60 48,285.60
acessories.Devt. length =50cm
Supply and fix 110mm UVPC down pipe. Price shall
3.3 include elbow metal bracket and all other necessary ml 28.00 483.80 13,546.40
acessories.
Provide Flashing of G-30 Development length of
3.4 ml 17.00 1,475.00 25,075.00
20 cm
TOTAL CARRIED TO SUMMARY - 131,511.00
4. CARPENTRY & JOINERY -
4.1 Eucalyptus truss from -
a) Diameter 10-12cm top and bottom chord members ml 115.00 100.00 11,500.00
diameter 8-10cm vertical and diagonal chord
b) ml 81.00 85.00 6,885.00
members
4.2 5x7cm Zigba roof purlin c/c 90cm. ml 104.00 250.00 26,000.00
2.5x25cm zigba fascia board, including three coats
4.5 ml 50.00 300.00 15,000.00
of varnish paint
Supply and fix 8 mm thick chip wood ceilings as per
the engineers approval. Price shall include 40 x 50
4.6 mm Zigba wood battens with c/c spacing of 600 mm m2 24.00 300.00 7,200.00
both ways, middle and corner list, and all other
necessary accessories.
-
TOTAL CARRIED TO SUMMARY 66,585.00
5. METAL WORKS
38x38xLTZ door and window
5.1 DOOR Type D,size
a) Type MD6 size (98x260cm) . Pcs 8.00 16,536.52 132,292.16
Expanded metal mesh fixed on LTZ frame shown on
5.2 m2 4.00 4,720.00 18,880.00
drawing
TOTAL CARRIED TO SUMMARY - 151,172.16
6. FINISHING WORKS. -
Three coat plastering in cement sand mortar of 1:3
6.1 m2 140.00 295.00 41,300.00
proportion
6.2 Two coats of plastering and one coat of rendering m2 101.00 330.00 33,330.00
50 mm thick smooth finished cement sand screed
m2 24.00 1,003.00 24,072.00
(1:3) bed floor finish .
- -
94
Description Unit Qty Rate Amount
No
Construct 10 cm thick C-20 RC 120cm wide
pavement (including 4Ø 8 deformed bar mesh
expnasion joint at every 120cm, The
6.11 m2 36.00 1,281.56 46,136.16
work includes 80 cm bulk excavation, 55 cm thick
selected material fill, 20 cm basaltic hard core and
cart away).
95
Description Unit Qty Rate Amount
No
- -
Supply and lay storm water half concrete pipe of
diameter 30cm with a minimum slope of 2% or
natural ground slope which ever is greater on and
including a firm bed of red ash 100mm thick below. ml 64.00 1,003.00 64,192.00
The joints shall be grouted in cement sand mortar of
(1:3). Price shall include 15cm thick concret curb
stone and all the necessary earth work
- -
9. SANITARY INSTALLATION
9.1 SANITARY FIXTURES
All fixtures and pipes which are specified below
shall subject to the Consultants or Owner's approval
based on samples, brochures and catalogues
presented by the contractor. Unit Price shall include
all the necessary fixing brackets or hooks and all
assistnace civil works such as chiselling of walls,
floors, beams etc…
ALL FIXTURES ARE TO BE APPROVED
Supply and fix RAK or equivalent hand wash basins
made of white vitreious china ceramics, with milano
or equivalent stainless steel cold and hot water mixer
tap complete with pedastel stand, chrome plated
9.1.1
chain holder, 60cm long flex-italy or equivalent
flexible hoses, P-smell trap with connection pipe and
with all other necessary accessories that complete the
set.
96
Description Unit Qty Rate Amount
No
Size :- 500 x 400 mm No 2.00 14,160.00 28,320.00
Supply and fix RAK or equivalent toilet paper holder
with chrome plated brass wall flanged roll with
9.1.2 No 8.00 1,770.00 14,160.00
chrome plated fastening screws and other
accessories.
Supply and fix crystal glass mirrors for toilets and
wash basins with copper back protection, size:
9.1.3 500/400 mm including chrome plated brass mirror No 2.00 3,540.00 7,080.00
clips with chrome plated screws and etc... for hand
wash basins.
Supply and fix RAK or equivalent soap holder in
white vitreous china of size 150 x 150 mm complete
9.1.4 No 2.00 2,124.00 4,248.00
with the necessary fixing and other accessories for
hand wash basins.
Supply and fix 400mm x 600mm concrete san plat.
9.1.5 Price shall include all necessry assistances and No 8.00 2,000.00 16,000.00
accessories to install on the slab.
9.2 WATER SUPPLY PIPE LINE AND VALVES - -
97
Description Unit Qty Rate Amount
No
Dia. 20 mm ml 12.00 1,003.00 12,036.00
Supply and fix PPR ball Valves of approved
standard,on water supply distribution lines where
shown on the drawing The valves shall be
9.2.2 - -
compatable with PPR pipes and complete with
adaptors,unions, elastic water proofing , hand wheels
of normal quality and all other necessary accessories.
Diameter 20mm No 1.00 2,950.00 2,950.00
Supply and fix 15mm dia, PN 20 chrome plated
brass quarter turn angle valves with chrome plated
copper connecting pipe, union nut and chrome plated
9.2.3 brass wall flanges, and accessories complete in all - -
respects. The Angle valve should be capable
resisting of PN-20 before hand washbasins, water
closets, shut up hoses, sinks and water heaters.
Dia. 20 mm No 2.00 3,540.00 7,080.00
WASTE, VENT AND RAIN WATER PIPES AND
9.3 - -
ACCESSORIES
98
Description Unit Qty Rate Amount
No
Dia. 50 mm ml 8.00 885.00 7,080.00
Dia. 110 mm (For Vent pipe) ml 11.00 1,416.00 15,576.00
Supply and fix floor drains made of uPVC circular
box of approved quality for grey water with 4- side
openings, complete with P-smell trap with 6cm
9.3.2 - -
water seal, treaded drain/clean bottom outlet,
approved standard stainless steel cover and all other
necessary fittings and accessories.
Size:- Dia. 100 x 100 mm No 2.00 1,770.00 3,540.00
Supply and install vent caps made of rigid uPVC to
be connected to the roof terminal of vent pipe. Unit
9.3.3 - -
price shall include flushing works to prevent roof
leakage and wire mesh fly screen : -
a) Size: - Dia.110mm No 2.00 7,670.00 15,340.00
9.4 ROOF RUNOFF DRAINAGE SYSTEM - -
Supply and fix uPVC(PN 4) Down pipes with mass
concrete support at ground level and complete with
basket strainer at inlet, galvanized clips at every
elbows,joints and at every 1m interval complete with
9.4.1 all accessories.The pipes, accessories, fittings & - -
method of welding shall comply with the
requirement of BS 4514or equivalent Institution.
Unit price shall include all the necessary assistances
to the installation works.
a) Size: - Dia.75mm ml 7.00 1,298.00 9,086.00
99
Description Unit Qty Rate Amount
No
connectors and all necessary accessories
consisting of :(all Breakers are to be type
Legrand or ABB)
1 pcs MCB of 10A 1ph
and complete with phase bar system of 20A
and 25% reserve space. PCs 1.00 25,000.00 25,000.00
2.00 Light points -
100
C O S T S U M M A R Y
Block PUMP HOUSE
A Sub-Structure
B Super-Structure
101
T S U M M A R Y
102
BLOCK- PUMP HOUSE
103
ITEM DESCRIPTION UNIT QTY RATE Amount
2.5 10/2 cm chip wood or Styrofoam expansion joint between G.beam and
slab. ml 9.20 194.94 1,793.45
104
ITEM DESCRIPTION UNIT QTY RATE Amount
3.2 Ditto but above natural ground level externally pointed in 1:3 Cement
mortar (price includes pointing). m3 1.84 3,187.18 5,864.41
3.3 Construct stone masonary steps in 15cm riser & 30cm thread. m3 3,187.18 -
105
ITEM DESCRIPTION UNIT QTY RATE Amount
c) Purlin (Australian) size 5/7cm ml 12.60 295.00 3,717.00
4.2 25*2.5cm Australian wooden fascia board price includes three coats of
767.00
weather resistance paint/ Varnish. ml 16.80 12,885.60
4.3 Supply & fix flush paneled 40mm thick wooden door as per drawings.
Doors shuld be constructed of solid wood internal framed in between
the the strip play wood filled in honeycomp patternes. spced c/c 8cm
both direction. The frames arrangement shuld have two vertical and
eqully spaced for horizontal members. Both side of such units shuld be
vaneered with 4mm thick Kerero or woyera play wood and edges
trimmed framed in to Kerero or woyera. The jamb shuld be 4cm thick
Australian wood framed. The width of the jamb shuld be equal to the
plastered wall thickeness. Price includes three coats of varnish paint ,
door stopper, 4mm clear glass for door with fun light, 80x10mm
skirting at both side bottom edges, three 140x70mm hinges, genuine or
best approved cylinderical lock, and other neccessaries accessories.
(Door sample & its accessories, hinges locks, handles should be
approved by the client). -
Doors -
a) Type D1 size-80/210cm Nº 1.00 13,238.40 13,238.40
4.4 Supply and fix 10x2.5cm Australian or equvalant wooden strip for wall
protectin where indicated by the engineer. (price includes three coats of
weather resistance paint/Varnish). ml -
106
ITEM DESCRIPTION UNIT QTY RATE Amount
6.2 Apply two coats of plastering with cement mortar ratio 1:3 & 3rd coat
gypsum finishing to all internal walls & concrete structural surfaces
where there is no moist. m2 -
6.3 Apply two coats of plastering to recieve Quartize paint to all external
surfaces. m2 31.36 330.40 10,361.34
6.4 Apply cement screed flooring with cement mortar ratio 1:3. m2 5.29 190.00 1,005.10
6.8 Best & Approved type 9mm thick NON-SLIPPERY PORCELAIN
Tile flooring (60x60cm) bedded on and including 41mm thick mortar
1:3 ratio & joints grouted (material shall be approved in advance by the
client) m2 -
6.9 Best & Approved type 9mm thick NON-SLIPPERY RACK Tile
flooring (40x40cm) bedded on and including 41mm thick mortar 1:3
ratio & joints grouted (material shall be approved in advance by the
client) m2 -
6.10 Best & Approved type Porcelain tile skirting 10/0.8cm bedded on and
including cement mortar ratio 1:1 backing (black in color and pre
fabricated) m -
6.11 Lay best & approved type 3x27cm reinforced terrazzo window cill with
marble chips embeded and bedded on cement mortar. (Keep the slop
1.% to wards external ) m -
6.12 Ditto but 30cm wide threads. ml -
6.13 Ditto but 16cm high riser. ml -
6.14 30/30/3mm angle iron corner protection bedded into wall H=150cm m -
6.15 10 cm thick C-20 RC 1.2 m wide pavement (including 4Ø 8 deformed
bar mesh ,expnasion joint at every 1.2 m length, 80cm bulk excavation,
50 cm thick selected fill, 20 cm basaltic hard core and cart away). m2 19.20 900.00 17,280.00
6.16 Supply and lay storm water concrete pipes of diameter 30cm with a
minimum slope of 2% or natural ground slope which ever is greater on
and including 100mm thick firm bed of red ash , The joints shall be
grouted in cement sand mortar of (1:3). Price shall include all the
necessary earth work ml -
6.17 Supply and lay storm water concrete pipes of half diameter 30cm with a
minimum slope of 2% or natural ground slope which ever is greater on
and including 100mm thick firm bed of red ash , The joints shall be
grouted in cement sand mortar of (1:3). Price shall include all the
necessary earth work ml 22.00 660.00 14,520.00
6.18 Construction of 10x40 cm curb stone with good workman ship (ditch
suport) around the building as in the drawing in concrete C-15 280kg of
cement/m3 Price shall include form work, reinforcement, expansion
joint, 5cm thick lean concrete and all the necessary excavation work.
(Re-bar shall be of 4 diameter 8mm deformed main bar and stirrups of
diameter 6mm c/c25cm.) ml 22.00 275.00 6,050.00
107
ITEM DESCRIPTION UNIT QTY RATE Amount
8. GLAZING -
Supply and fix quality clear or forested glass with metal beads and putty -
8.1 4mm thick clear glass m2 -
8.2 4mm thick frosted glass m2 -
108
MELKA ODA HOSPITAL
SUMMARY OF BOQ
A- SUBSTRUCTURE
DEMOLISHING WORKS
1.00 Birr 24,048.75
EXCAVATION AND EARTH WORK
2.00 Birr 336,586.14
CONCRETE WORK
3.00 Birr 626,668.90
MASONARY WORK
4.00 Birr 162,092.92
B- SUPERSTRUCTURE
Item
Description Unit Qty Unit rate Amount
No.
1. DEMOLISHING WORK
Demolish & dispose off debries out off muncipal limits, safely
without any damage other things. This includes cost of all
Floor
110
Item
Description Unit Qty Unit rate Amount
No.
1.8 25cm thick basaltic or equivalent stone approved by the
consultant hard-core well rolled consolidated and blinded
with crushed stones. m2 168.19 450.00 75,685.50
111
Item
Description Unit Qty Unit rate Amount
No.
d) Gutter m3 5.28 5,100.00 26,928.00
1.2 Provide, cut and fix in position timber or steel or a
combination of two formwork or equivalent. 0.00
a) In elevation columns. m 2
46.46 675.00 31,360.50
b) In top tie Beams m2 123.55 675.00 83,396.25
c) In 150mm thick Roof & W. Tanker slab m2 7.56 675.00 5,103.00
D) In Gutter m2 102.96 675.00 69,498.00
1.3 Steel reinforcements according to the drawing, price shall
including cutting, bending placing in position using tying
wires and spacers. 0.00
a) dia. 8 mm deformed bar. kg 84.74 110.00 9,321.40
B) dia. 12 mm deformed bar. kg 409.33 110.00 45,026.30
c) dia. 14 mm deformed bar. kg 784.34 110.00 86,277.40
112
Item
Description Unit Qty Unit rate Amount
No.
4. CARPENTRY & JOINERY
4.1 CARPENTRY
4.1.1 Supply and fix 10mm thick PVC ceiling batten placed 600
mm c/c in both sides. Price shall include ceiling batten and all
accessories for the completion of the work. m2 183.48 680.00 124,766.40
4.1.2 Supply and fix 40mm thick best quality internal flush type
wooden doors in hard wood frame both sides covered with
4mm thick weira ply wood. Price shall include safety locks,
swing door hinges, and other necessary accessories and three
coats of varnish paint. All timber shall be well seasoned and
free from harmful defects. 0.00
DOORS 0.00
a) size 150x330cm=2PC m2 5.90 8,500.00 50,150.00
a) size 120x330cm=1PC m2 4.80 8,500.00 40,800.00
b) size 90x330cm =3PC m2 10.70 8,500.00 90,950.00
c) size 80x330cm =1PC m2 3.20 8,500.00 27,200.00
0.00
113
Item
Description Unit Qty Unit rate Amount
No.
7. FINISHING
7.1 WALL AND FLOOR FINISH
7.1 5mm thick Epoxy Floor Installations in accordance to BS6319
PTS 3 & 7 & ASTMC579 & D4060. Prepare the
screeded surface (measured separately), supply and install
5mm thick epoxy floor finish all in strict accordance with
manufacturer's instructions with minimum comprehensive
strength of 85N/mm2 as per ASTM C579 and Flexural
Strength of 28N/mm2 and Tensile Strength of 16N/mm2 both
as per BS 6319, that meets chemical and abrasion resistance
all to manufacturer's Instructions and to approval of Architect. m2 175.56 2,900.00 509,124.00
7.2 Ditto for allowance for monolithic skirting 150mm high ml 68.64 2,900.00 199,056.00
7.3 Supply and lay to floor 8mm thick 30*30 imported ceramic
floor tile with cement paste and joints shall be grouted with
white cement. m3 7.92 830.00 6,573.60
7.4 300x200x6mm RAK or equivalent Ceramic wall tile bedded
with cement mortar of (1:3) to all toilets, bath rooms and
kitchen walls. Price include cement mortar bed and white
cement grouting. m2 264.00 855.00 225,720.00
7.5 48mm thick cement sand screed under plastic tile flooring and
finished smooth to receive 2mm thick PVC tile. m2 175.56 280.00 49,156.80
7.60 Supply and lay 2cm thick marble window cills bedded in
cement-sand screed 1:3. price includes cement screed and all
nacessary works ml 14.39 700.00 10,073.00
7.70 Ditto but 3 cm thick marble threshold bedded on cement
mortar (1:3) ratio . Price shall include cement screed , mirror
polishing and all necessary works. ml 2.64 680.00 1,795.20
114
Item
Description Unit Qty Unit rate Amount
No.
3 pc 10A, MCB, 1 Phase
and with 20% reserve space No 1.00 35,000.00 35,000.00
9.1.4 Flush mounted sub distribution board LLP-1 with lockable
door, phase-bar rating of 25A/1ph and with all its accessories
consisting of :-
4 pc 16A, MCB, 1 Phase
1 pc 10A, MCB, 1 Phase
and with 20% reserve space No 1.00 35,000.00 35,000.00
9.2 LIGHT POINTS
9.2.1 Light point fed through PVC insulated copper conductors of
2x2.5 sq.mm in thermoplastic conduit of minimum diameter
13.5 mm in/or under surface including junction box with cover
and screw type insulating connectors and flush mounted
switches. No 28.00 1,520.00 42,560.00
9.3 SWITHCES
9.3.1 Flush mounting single switch No 2.00 380.00 760.00
9.3.2 Flush mounting double switch No 8.00 610.00 4,880.00
9.3.3 Flush mounting two way switch No 8.00 360.00 2,880.00
9.3.4 Flush mounting intermediate switch No 4.00 360.00 1,440.00
9.5 TYPE OF LIGHT FITTINGS OR EQUIVALENT
Supply and install florecent light. Connected and tested
including lamps and accessories complete.
(a) Light Fittings - Complete florecent 36wt No 27.00 2,260.00 61,020.00
(a) Light Fittings - Complete florecent 18wt No 1.00 2,100.00 2,100.00
9.6 SOCKET OUTLETS POINTS
9.6.1 Flush mounted Legrand Schuko socket outlets points of
16A/1ph fed through PVC conductors of 3x2.5 sq.mm in
thermoplastic conduit of minimum 16mm in/under surface
including junction box with cover and screw type insulating
connectors. No 8.00 410.00 3,280.00
9.6.2 Flush mounting sockets outlet points of 16A 1phase for Water
heaters fed through PVC conductors of 3x2.5 sq.mm in
thermoplastic conduit of minimum f 20mm No 3.00 410.00 1,230.00
9.6.3 Flush mounting sockets outlet points of 20A 1phase for Stove
fed through PVC conductors of 3x4 sq.mm in thermoplastic
conduit of minimum f 20mm No 9.00 1,800.00 16,200.00
9.6.4 Flush mounting sockets outlet of 16A 1phase with earth
contact No 11.00 410.00 4,510.00
9.6.5 Flush mounting sockets outlet of 20A 1phase earth contact No 9.00 410.00 3,690.00
9.7 TELEPHONE SYSTEM
9.7.1 Telephone points fed through Cat-6 STP-100 Base TX cables
in thermoplastic conduit of minimum diameter 19mm for flush
installation. R-J 11 sockets measured elsewhere. No 2.00 4,210.00 8,420.00
9.7.2 Flush mounted RJ-11 sockets of type legrand or approved
equivalent. No 2.00 680.00 1,360.00
9.7.3 Tv Terminal Box No 2.00 9,015.00 18,030.00
9.80 FEEDER CABLES 0.00
9.8.1 Supply power from MDB to SDB-1F ,2F and 3F through PVC
insulated and PVC sheathed copper cable of 5x4mm2 in
thermoplastic conduit of minimum dia.20mm. ml 200.00 100.00 20,000.00
115
Item
Description Unit Qty Unit rate Amount
No.
9.9 POWER AND TELE INTAKE 0.00
9.9.1 Supply power from EEPCO to MLLP through PVC insulated
and PVC sheathed copper cable of 4x10mm2 in
thermoplastic conduit of minimum dia.20mm. ml 50.00 910.00 45,500.00
9.9.2 EEPCO and Tele intake manholes of size 700x700mm and
depth 500mm No 1.00 5,000.00 5,000.00
9.9.3 EEPCO Connection Fee LS 1.00 5,000.00 5,000.00
116
Item
Description Unit Qty Unit rate Amount
No.
50 liters No 1.00 27,000.00 27,000.00
Floor drain of approved quality complete with all accessories
10.2.8 including a removable strainer cap fitted to smell trap, etc.
Diameter 50 mm No. 1.00 1,050.00 1,050.00
Supply & fix toilet paper holder of approved quality
10.2.9 complete with fixing screws. No. 1.00 1,030.00 1,030.00
11.2.10 Supply anf fix normal glass mirrors with light fittings.
Size 600 x 1000 mm No. 1.00 2,500.00 2,500.00
Supply and fix towel hangers of approved quality complete
11.2.11 with fixing accessories No. 1.00 1,290.00 1,290.00
Supply & fix soap holders of approved quality complete with
10.2.12 fixing accessories No. 1.00 1,035.00 1,035.00
WASTE WATER PIPES
Supply & install soil waste in horizontal branches and vertical
stacks made of rigid plastic pipes PVC of approved standard
including all ncessary fitting, such as bends Y.T cleanouts,
increasing & reducing pieces with tight joints as shown on the
10.2.13
drawing. All horizontal branches shall be laid in a slope of
2%. The unit price shall include all necessary masonry
assistance such as chiseling of walls slabs, beams floor etc.
and closing them with concrete or cement mortar.
Diameter 50 mm m.l. 50.00 100.00 5,000.00
Diameter 110 mm m.l. 20.00 130.00 2,600.00
B- EXTERNAL INSTALLATION
10 SITE SANITARY WORKS
Supply and install HDPE NP 16 pipes and Fittings, for water
pipe line from city main to roof water tank and to internal
inout points complete with the necessary fittings and
accessories. The unit price shall include shall include trench
works to a depth of appr. 500mm for laying the pipe, spread of
10.3.1 granular material 100mm under.
Diameter 20mm m.l 15.00 180.00 2,700.00
Supply & fix Gate Valves on PP-R and GS Pipe lines
10.3.2 complete with PP- union, hand wheel.
Diameter 20mm No. 2.00 200.00 400.00
Supply & fix GRP 5,000lit. capacity roof water tank in fiber
glass to be mounted on roof slab complete with float valve and
10.3.3 all pipe connections. No. 2.00 35,000.00 70,000.00
Supply & lay PVC pipes for Sanitary drainage lines with the
sizes & slopes shown in the drawing on a compacted bed of
sand 10cms thick below the invert, and 10cms above crown of
pipe. The unit price shall include excavation of the trench,
10.3.4 supply & spread of granular material & backfilling.
Diameter 110 mm m.l. 15.00 130.00 1,950.00
Diameter 160 mm m.l. 15.00 235.00 3,525.00
Supply & install vent caps of rigid PVC to be connected to the
10.3.5 roof terminal of vent pipe.
Diameter 50 mm No. 4.00 100.00 400.00
Supply and install diameter 80mm, rigid PVC down pipe,
secured to wall with pipe fixing brackets at 150cm interval
10.3.6 complete with roof drainage strainer cap. m.l. 20.00 90.00 1,800.00
117
Item
Description Unit Qty Unit rate Amount
No.
Supply & construct sanitary manholes from 12cm thick
Concrete pipes on sanitary lines on 200mm thick mass
concrete base and removable RC slab cover Dia.80mm thick
10.3.7 as detailed in the drawing.
Dia. 600mm No. 10.00 8,000.00 80,000.00
118
MELKA ODA HOSPITAL
C O S T S U M M A R Y Civil Site Work
A Sub-Structure
119
MELKA ODA HOSPITAL
120
Site Civil Work
Supply, fill & compact the space or voids between the
1.7 M2
cobblestones with fine crushed aggregates to prevent 528 885.00 467,280.00
Total to summary ………Birr
- 1,432,751.76
2.Fence Work
-
-
A) Excavation and Earth Work
-
Trench excavation for masonry foundation in ordary
2.1 m3
soil to a depth not exceeding 100cm starting from 75 649.00 48,675.00
2.2 Cartaway surplus material (2km away from site) m3
75 413.00 30,975.00
B) Masonry Work
- -
50 cm thick masonry Below NGL price shall include
2.3 m3
cement mortar of 1:3 mix ratio 75 2,699.84 202,488.00
Ditto but well dressed stone Above NGL (Price
2.4 includes pointing and 8cm thick C-20 concret m3
Copping and plastering to concret to copping ) 112.5 5,000.00 562,500.00
50 cm thick well dressed masonry pillars (COLUMN)
above gound level (Price includes pointing and 8cm
2.5 m3
thick C-20 concret Copping and plastering to concret
to copping) 20 6,490.00 129,800.00
C) Concrete Work - -
2.. Concrete work - -
2.1 C-7 lean concrete - -
a) Under masonary m2 75.00 320.00 24,000.00
- -
2.2 C-25 RC Concrete in grade beam m3 15.00 5,100.00 76,500.00
C-25 RC Concrete in elevation column m3 4.32 5,100.00 22,032.00
- -
Provide, cut and fix in position machin cut Australia
2.4 pinus wood or metal panel formwork which ever m2
appropriate to the Grade beam 60.00 1,416.00 84,960.00
Reinforced steel bar according to structural drawings.
2.5 price include cutting bending & placing in position
and tying wires. - -
a) Diameter 10 deformed bars kg 2,350.00 110.00 258,500.00
b) diameter 8 deformed bars kg 2,400.00 110.00 264,000.00
Sub Total to summary ………Birr(1) - 1,704,430.0
2. BLOCK WORK -
Concrete block wall class "B" bedded in cement
mortar ratio 1:3 both sides left for plastering (price
shall include pointing,8cm thick C-20 concret
Copping and plastering to concret to copping)
-
121
Site Civil Work
a) 20cm thick m2 270.0 627.97 169,551.90
Sub Total to summary ………Birr (2) - 169,551.9
3. Metal Works -
122
Site Civil Work
3.STEPS AND RAMPS -
Steps and ramps shall be constructed at the gable side
of the blocks parallel to the gable side wall the width
of the ramp.with shall be decided on site.im
accordance with the ground and building level steps m3
should be provided on either side of the ramp parallel
to the gable side the ramp and the steps shall be
constructed where directed and ordered on site
-
1. Excavation and Masnory Works -
1.1 Excavation in 50cm from NGL m3 40 224.20 8,968.00
Stone masonry foundation wall with 50cm thick
1.2 m3
below NGL with cement morter 1:3 40 2,699.84 107,993.60
Ditto but semi-dressed stone masonry including
1.3 m3
pointing with 1:2 cement sand morter 20 6,490.00 129,800.00
1.4 Cartaway surplus excavated material(2km away) m3 40 413.00 16,520.00
1.5 Fill granular approved type selected m3 15 539.26 8,088.90
1.6 25cm thick Hard core for ramps m2 12 450.00 5,400.00
Total to summary ………Birr - 276,770.50
2.CONCRETE WORK -
2.1 7cm thick lean concrete m2 15 413.00 6,195.00
10 cm thickand C-20 renforced concrete slab with
2.2 dia.of 8mm re-bar spaced 20cm both ways (price shall m2
include renforcment and form work , 100 649.00 64,900.00
12.5cm thick reinforced concrete laid stone masonery
2.3 foundation for steps with C-20(price shall include m2
dia.8 mm renforcment and form work ,
40 811.25 32,450.00
Total to summary ………Birr - 103,545.00
steps and ramps Total to summary Birr - 380,315.50
1.Covered walk way -
A. Sub structure -
1. Excavation & earh work -
1.1 Removal of 20cm thick top soil m2 850.00 14.54 12,359.00
1.2 Excavation of black cottons soil up to 35cm m3 290.00 413.00 119,770.00
1.3 Excavation of trench m3 270.00 531.00 143,370.00
1.4 Selected material back fill under floor slab m3 460.00 539.26 248,059.60
1.5 Cart away (2kms away) m3 730.00 413.00 301,490.00
1.6 25cm thick Hard core m2 627.00 450.00 282,150.00
Total to summary …Birr 1,107,198.60
2.. Concrete work -
2.1 C-7 lean concrete -
a) Under masonary m2 330.00 320.00 105,600.00
b) Under floor slab m2 627.00 320.00 200,640.00
123
Site Civil Work
2.2 C-25 RC Concrete in grade beam m3 40.00 5,100.00 204,000.00
10cm thick reinforced concrete m2 627.00 510.00 319,770.00
Best & Approved type 40mm thick checkered terrazzo
2.3 floor tile bedded on and including 42mm thick mortar m2
1:3 ratio & joints grouted 627.00 767.00 480,909.00
Provide, cut and fix in position machin cut Australia
2.4 pinus wood or metal panel formwork which ever m2
appropriate to the Grade beam 330.00 675.00 222,750.00
Reinforced steel bar according to structural drawings.
2.5 price include cutting bending & placing in position
and tying wires. - -
a) Diameter 12 deformed bars kg 2,620.00 110.00 288,200.00
b) diameter 8 deformed bars kg 4,006.00 110.00 440,660.00
Masonry wall below NGL. price shall includes
2.6 pointing and all associated works and materials as m3
well. 268.00 2,699.84 723,557.12
Masonry wall ANGL. price shall includes pointing
2.6 m3
and all associated works and materials as well.
15.00 5,310.00 79,650.00
Total to summar Birr - 3,065,736.12
1. Steel structure -
Supply & fix steel structure fabricated according to
structural detal drawings with two coats of anti-rust
paint three coats of syntetuc paint
1.1 Diam 60mm CHS post 2.5mm thick kg 3,234.00 187.97 607,894.98
1.2 Plates(150mm*150mmx3mm) No 170.00 2,124.00 361,080.00
1.3 Ancher 'J' bolts - -
a. diam 16mm length 30cm No 340.00 1,670.88 568,099.20
1.4 40x60x2.5mm RHSbeam welded to plate kg 2,500.00 187.97 469,925.00
1.5 50x30x2mm RHS for upper & lower trusses kg 850.00 187.97 159,774.50
1.6 Ditto but 30x20x2mm diagonal member kg 1,560.00 187.97 293,233.20
Total to summary Birr - 2,460,006.88
2. ROOFING
Roof cover in G-30 C-I-S including roof ridge, vally
guttter, fixed to RHS truss and zigba wooden purlin
with "J" bolts and nuts. Provide asphalt washers.(roof
2.1
cover measured in horizontal projection).The work
include 40x30x2.5mm angle iron and all other
associated works and materials
m2 820.00 1,593.00 1,306,260.00
- -
Provide 5x7cm sawn zigba wood purlin to the covered
2.2
walk way ml 1,369.00 448.40 613,859.60
Total to summary Birr - 1,920,119.60
covered walk way Total to summary Birr - 8,553,061.20
124
Site Civil Work
2.CLOTH HANGER AREA
Prepare and adjust the ground to make level by
removing and cutting soil to average depth of 50cm.
Price shall incude cart away of excavated waste away
2.1 m2
from the compound. 25cm selected back fill and 15cm
thick hard coring with 10cm mass concret slab
paneled at every 100cms with trowel finish
130.00 177.00 23,010.00
Supply and fix CT-60 cloth hanger to plinth concrete
foundation as per the given drawing. Price shall
2.2 include excavation and cart away of plinth foundation ml
and its concret work. And also one coat of anti rust
and three coats of oil paint to the pillars.
120.00 1,888.00 226,560.00
Supply and fix 2.5cm thick galvanized white wire for
2.3 ml
cloth hanging 80.00 767.00 61,360.00
Total to summary Birr - 310,930.00
3.MISELLANEOUS WORKS
Supply and fix 4mm thick formica of size 40x60 over
3.1 No
which name of each block is labeled 20.00 7,080.00 141,600.00
Supply and fix semi-circular box type display board to
be fixed over the main enterance gate with 80cm
3.2 width both sides laminated with 1mm thick flat metal No
over which name of the the Hospital is written in three
languages 1.00 5,310.00 5,310.00
Cylinderical garbage bascket made of plastic with
3.3 rolling cover to be fixed in the pole of the blocks
approved by the engineer - -
Siz: 40x40x40cm No 15.00 5,900.00 88,500.00
Size: 60x60x100cm No 10.00 7,670.00 76,700.00
Total to summary Birr - 312,110.00
4. Uncovered Walk Way
4.1 Bulck excavation to the depth of 50cm M3 20 413.00 8,260.00
4.2 Cart away to the distance of 2kms awy M3 20 413.00 8,260.00
selected material back fill with selected granular
4.3 material brought from approved quary and well M3
compacted in the layer of not exceeding 20cm 20 826.00 16,520.00
4.4 25cm thick hard core blinded with crushed stone M2 75 450.00 33,750.00
125
Site Civil Work
8cm thick mass concrete in C-20 pavement flooring
4.5 spanned at every one meter using expansion joint out M2
of 10mm thick chipwood aon trolled floor finish
50 519.20 25,960.00
126
MELKA ODA HOSPITAL
C O S T S U M M A R Y
Sanitary Site Work
DESCRIPTION AMOUNT (BIRR)
A Sub-Structure
127
ELKA ODA HOSPITAL
128
MELKA ODA HOSPITAL
129
MELKA ODA HOSPITAL
130
MELKA ODA HOSPITAL
131
MELKA ODA HOSPITAL
3
a) Soft rock m 7 767.00 5,369.00
b) Bed(hard rock) m3 5 944.00 4,720.00
c) Bolder rock m3 6 1,180.00 7,080.00
Back fill around the masonry wall with selected
3.1.4 m3 20 885.00 17,700.00
granular material
Back fill on top R.C slab to a depth of 50cm . Wth
3.1.5 excavated good materials and well compacted in m3 23 539.26 12,402.98
layers not exceeding 25cm Thick.
Cart away surplus excavated material to an
3.1.6 m3 128 413.00 52,864.00
average distance of 500mt
3.2. Concrete Works - -
5cm, Thick lean concrete in C-5 with minimum
3.2.1 m2 42 413.00 17,346.00
cement content of 150kg/m3
Reinforced concrete in C-20 with minimum
cement content of 320kg/m3 of concrete, placed
3.2.2 - -
and vibirated around reinforcement rod. Form
work and reinforcement are measured separately
132
MELKA ODA HOSPITAL
3.4.2 Ditto but to both sides of H.C.B partiion walls. m2 26 684.40 17,794.40
3.5. Pipe Work - -
Provide and install inposition PVC "T" pipe Ø
3.5.1 No 2 767.00 1,534.00
200cm
3.5.2 Provide and instaal elbow Ø 200mm No 2 1,180.00 2,360.00
Total carried to summary - -
Total to summary ………Birr - 632,189.34
4.Soak away pit for 2 units -
4.1. Excavation and Earth work -
Excavate pit for septic thank to a depth not
4.1.1 m3 26 413.00 10,738.00
exceeding 1.5mt
4.1.2 Ditto but to not exceeding a depth of 30cm m3 26 472.00 12,272.00
4.1.3 Ditto but not exceeding a depth of 450cm m3 26 590.00 15,340.00
4.1.4 Ditto but not exceedingg a depth of 550cm m3 18 767.00 13,806.00
4.1.5 Rock excavation - -
3
a) Soft rock m 5 1,180.00 5,900.00
b) Bed(hard rock) m3 3 1,416.00 4,248.00
c) Bolder rock m3 3 1,770.00 5,310.00
2. Block Work - -
60cm thick hard tractytic of equivalent stone
4.2 masonary retaining wall bedded in cement mortar m3 22 4,720.00 103,840.00
1:4 (Cement sand)
4.2.1. Ditto but dry(without cement mortar) m3 12.5 3,540.00 44,250.00
6.3. Fill work - -
Fill pit from the bottom upto a depth of 1.8m with
4.3.1 m3 9 885.00 7,965.00
water absorbent light and clean coarse gravel
a) Ditto but with coarser gravel to a depth of
m3 1.5 1,180.00 1,770.00
30cm
b) Ditto but with fine gravel to a depth of 30cm m3 1.5 1,770.00 2,655.00
c) Ditto but with fine sandto a depth of 30cm m3 1.5 2,124.00 3,186.00
6.4. Concrete Work - -
Reinforced comcreate class C-20 with minimum
cement content of 320kg/m2 filled into from work
and vibrated around red reinforcement steel and m3 6.5 5,100.00 33,150.00
form work measured separately in top slab &
manhole cover.
Reinforcement bars according to structural
4.4.1 drawing price includes cutting,bending,placing in - -
position & tying wires
a) Dia 8mm deformed bars kg 71 141.60 10,053.60
133
MELKA ODA HOSPITAL
3
5.0 Septic Tank 30m Capacity -
Construct rectangular septic thank 30m3 capacity
in accordance with the detall drawing including all -
incidental works.
4.1, Earth works -
Excavate pit for septic thank to a depth not
413.00 22,302.00
5.1.1 exceeding 1.5mt m3 54
5.1.2 Ditto over 1.5mt but not exceeding 3.5 mt m3 71 531.00 37,701.00
5.1.4 Rock excavation -
a) Soft rock m3 7 767.00 5,369.00
b) Bed(hard rock) m3 5 944.00 4,720.00
3
c) Bolder rock m 6 1,180.00 7,080.00
Back fill around the masonry wall with selected
885.00 35,400.00
5.1.5 granular material m3 40
Back fill on top R.C slab to a depth of 50cm . Wth
excavated good materials and well compacted in
539.26 9,167.42
layers not exceeding 25cm Thick.
5.1.6 m3 17
Cart awway surplus excavated material to an
3 413.00 51,625.00
5.1.7 average distance of 500mt m 125
5.2. Concrete Works -
5cm, Thick lean concrete in C-5 with minimum
2 510.00 15,810.00
5.2.1 cement content of 150kg/m3 m 31
Reinforced concrete in C-20 with minimum
cement contentt of 320kg/m3 of concrete placed
-
and vibrated around reinforcement are measired
5.2.2 separataly.
5.2.3 In 20cm. thick top slab m3 5.25 5,100.00 26,775.00
3
5.2.4 In 10cm. think inspection manhole wall m 6.75 973.50 6,571.13
Provide, cut and fix in position sawn zigba form
-
5.2.5 work
a. To 20cm. botttom dlsb m2 5 675.00 3,375.00
2
b. To 15cm. top slab m 21 675.00 14,175.00
c. To 10cm. wall m2 12 675.00 8,100.00
d. To R.C removable cover m2 1.5 675.00 1,012.50
5.2.6 Mid steel reinforcement according to drawing -
a. dia. 8mm. Deformed bar. kg 221 110.00 24,310.00
134
MELKA ODA HOSPITAL
2 684.40 17,794.40
5.4.2 Ditto but to both sides of H.C.B partiion walls. m 26
Apply one coat of water proofing membrane,
which is approved by the client prior to
850.00 75,650.00
installation; in case of the existance of ground
5.4.3 water percolation to the septic tank. m3 89
4.5. Pipe Work -
Provide and install inposition PVT "T" pipe Ø
767.00 1,534.00
5.5.1 200cm No 2
5.5.2 Provide and onstal above elbow Ø 200mm No 2 1,180.00 2,360.00
Total to summary ………Birr 600,947.81
135
MELKA ODA HOSPITAL
A Sub-Structure
136
LKA ODA HOSPITAL
137
MELKA ODA HOSPITAL
Complete with separate earthing and neutral bus bars NO 1 1,000,000.00 1,000,000.00
3. Cable Ducts - -
Supply and lay recessed PVC rigid conduit. -
a)19mm ml 50 23.60 1,180.00
b) 21mm ml 50 25.96 1,298.00
c) 25mm ml 50 29.50 1,475.00
d)29mm ml 15 35.40 531.00
e)40mm ml 15 37.76 566.40
f)50mm ml 200 100.30 20,060.00
-
138 -
ITEM Descriptions Unit QTY Unit rate Amount
2.1.4 Circular manhole 600mm dia, with 600mm depth NO 80 23,600.00 1,888,000.00
139
ITEM Descriptions Unit QTY Unit rate Amount
140