You are on page 1of 5

Project :

Location :

Item Description of works Qty Unit Unit Cost

A B C
A. EARTH WORKS
A.1. Excavation 4.62 cu.m. 623.35
A.2. Backfill/Compaction 1.69 cu.m. 114.20
A.3. Embankment 4.15 cu.m.
A.4. Termite control

B. STRUCTURAL WORKS
B.1. Concrete Works 5.72 cu.m. 722.26
B.2. Reinforced Steel Bars 454.53 kgs. 5.31
B.3. Formworks 26.00 sq.m. 199.31

C. MASONRY
C.1 4" thk. CHB 17.00 sq.m. 190.45
C.2 Plastering 34.00 sq.m. 177.17

D. ROOFING WORKS
D.1 Roof Framing Works 1.00 lot 3,796.44
D.2. Roofing and accessories 1.00 lot

E. ARCHITECTURAL
E.1. Floor Finishes 16.00 sq.m. 202.48
400x400 Floor Tiles
E.2. Pebble washout 11.64 sq.m. 272.08
E.3. Stone Cladding 2.40 sq.m. 263.64
E.4. Paver (Driveway) 6.50 sq.ft. 272.08
E.5. Precast 4" dia. 7.00 l.m. 7.23

G. CEILING FINISHES
G.2. Flexboard Ceiling-flat ceiling 27.00 sq.m. 189.82

I. Painting works
l.a Exterior Walls 34.00 sq.m. 101.24
l.e Flexboard Ceiling (2 coats) 27.00 sq.m. 101.24

K. Plumbing wortks 1.00 lot 418.09


J.1. Carport

TOTAL AMOUNT
Prepared by: ____________________________
Subcon

Checked by: _____________________________


ACCOMPLISHMENT
Amount % Wt.
TO DATE PREVIOUS THIS PERIOD
D E Percent % Wt. Amount Percent % Wt. Amount Percent

1,053.46 2.11% 100.00 2.110% 1,053.46 100.00


192.99 0.39%
543.03 1.09%

4,131.33 8.26% 25.00 2.065% 1,032.83 25.00


2,414.54 4.83% 50.00 2.415% 1,207.27 50.00
5,182.14 10.36%

3,237.73 6.48%
6,023.69 12.05%

3,796.44 7.59%
2,847.33 5.69%

3,239.63 6.48%

3,166.99 6.33%
632.74 1.27%
1,768.51 3.54%
50.62 0.10%

5,125.20 10.25%

3,442.11 6.88%
2,733.44 5.47%

418.09 0.84%

Php 50,000.00 100.00% 6.590% 3,293.56


Recommending Approval : __________________________

Project Manager

Approved by : ___________________________

President/A.M.O.
THIS PERIOD
% Wt. Amount

2.110% 1,053.46

2.065% 1,032.83
2.415% 1,207.27

6.590% 3,293.56

You might also like