OFFICE OF THE REGIONAL EXECUTIVE DIRECTOR

Regional Field Office - MiMaRoPa


3rd Flr., ATI Building, Elliptical Road, Diliman, Quezon
City
Telephone No. (02) 332-72-74
Telefax: (02) 927-43-50
Email address: ored4b@yahoo.com

Name of Project: LOT 11: EXTENSION OF IRRIGATION CANAL OF CABIGAAN DIVERSION DAM
Location of Project: Brgy. Cabigaan, Aborlan, Palawan
VALIDATED STATEMENT OF WORK ACCOMPLISHED
as of April 20, 2021
ACCOMPLISHMENT
Item No. DESCRIPTION Quantity Unit Unit Cost Total Cost % Weight As of April 12, 2021 As of April 20, 2021 Total Accomplishment Up To Date
Quantity Accomp. Weight( %) Quantity Accomp. Weight( %) Quantity Accomp. Weight( %)
A. General Requirements
SPL9(1) Construction of Temporary Facilities 36.00 sq.m 2,288.06 82,370.03 2.98% 36.00 100.00% 2.98% 0.00 0.00% 0.00% 36.00 100.00% 2.98%
SPL9(2) Mobilization and Demobilization of Equipment 1.00 l.s. 91,291.20 91,291.20 3.30% 0.50 50.00% 1.65% 0.00 0.00% 0.00% 0.50 50.00% 1.65%
SPL11b Concrete Marker 1.00 pc 13,588.47 13,588.47 0.49% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
Sub-total 187,249.70 6.77% 4.63% 0.00% 4.63%
B. Canal Works
102(a) Common Excavation - Manual 441.33 cu.m 411.14 181,448.81 6.56% 374.00 84.74% 5.56% 18.58 4.21% 0.28% 392.58 88.95% 5.83%
100(2) Structure Backfill 225.00 cu.m 310.09 69,769.35 2.52% 112.50 50.00% 1.26% 14.50 6.44% 0.16% 127.00 56.44% 1.42%
404 Reinforcing Bars 6,101.04 kgs. 79.51 485,075.08 17.53% 4500.00 73.76% 12.93% 937.61 15.37% 2.69% 5437.61 89.13% 15.62%
405(1) Concrete Class "A" (w/ forms) 74.00 cu.m 16,862.78 1,247,845.35 45.10% 35.41 47.85% 21.58% 11.39 15.39% 6.94% 46.80 63.25% 28.52%
405(2) Concrete Class "A" (w/o forms) 58.03 cu.m 10,063.35 583,976.22 21.10% 27.69 47.72% 10.07% 8.91 15.35% 3.24% 36.60 63.07% 13.31%
201 Levelling Course 47.76 cu.m 245.84 11,741.09 0.42% 38.20 79.98% 0.34% 7.30 15.28% 0.06% 45.50 95.27% 0.40%
Sub-total 2,579,855.90 93.23% 51.74% 13.38% 65.12%
TOTAL COST 2,767,105.60 100.00% 56.36% 13.38% 69.74%

I HEREBY CERTIFY that all works items were verified by the undersigned and have been accomplished in accordance with the approved plans, specifications
and programs of work and representing 69.74%

Prepared by: Checked by:

JESSA ANN C. LOMUGDANG ENGR. VICTOR A. BINASAHAN ENGR. ERIC T. AVES


RAED Technical Staff P.E.O II/ C.E Engineer III

Reviewed by: Recommending Approval: Approved:

ENGR. MA. CHRISTINE C. INTING ENGR. ELMER T. FERRY, Ph.D ANTONIO G. GERUNDIO, CESO III, DPA
Chief, RAED / Engineer V RTD for Operations Regional Executive Director