You are on page 1of 4

Project :

Location :

Item Description of works Qty Unit Unit Cost Amount % Wt.


TO DATE
A B C D E Percent
A. EARTH WORKS
A.1. Excavation 4.62 cu.m. 623.35 1,053.46 2.11% 100.00
A.2. Backfill/Compaction 1.69 cu.m. 114.20 192.99 0.39%
A.3. Embankment 4.15 cu.m. 543.03 1.09%
A.4. Termite control

B. STRUCTURAL WORKS
B.1. Concrete Works 5.72 cu.m. 722.26 4,131.33 8.26% 25.00
B.2. Reinforced Steel Bars 454.53 kgs. 5.31 2,414.54 4.83% 50.00
B.3. Formworks 26.00 sq.m. 199.31 5,182.14 10.36%

C. MASONRY
C.1 4" thk. CHB 17.00 sq.m. 190.45 3,237.73 6.48%
C.2 Plastering 34.00 sq.m. 177.17 6,023.69 12.05%

D. ROOFING WORKS
D.1 Roof Framing Works 1.00 lot 3,796.44 3,796.44 7.59%
D.2. Roofing and accessories 1.00 lot 2,847.33 5.69%

E. ARCHITECTURAL
E.1. Floor Finishes 16.00 sq.m. 202.48 3,239.63 6.48%
400x400 Floor Tiles
E.2. Pebble washout 11.64 sq.m. 272.08 3,166.99 6.33%
E.3. Stone Cladding 2.40 sq.m. 263.64 632.74 1.27%
E.4. Paver (Driveway) 6.50 sq.ft. 272.08 1,768.51 3.54%
E.5. Precast 4" dia. 7.00 l.m. 7.23 50.62 0.10%

G. CEILING FINISHES
G.2. Flexboard Ceiling-flat ceiling 27.00 sq.m. 189.82 5,125.20 10.25%
I. Painting works
l.a Exterior Walls 34.00 sq.m. 101.24 3,442.11 6.88%
l.e Flexboard Ceiling (2 coats) 27.00 sq.m. 101.24 2,733.44 5.47%

K. Plumbing wortks 1.00 lot 418.09 418.09 0.84%


J.1. Carport

TOTAL AMOUNT Php 50,000.00 100.00%

Prepared by: ____________________________ Recommending Approval : _____________________


Subcon
Project Manager

Checked by: _____________________________ Approved by : _______________________

President/A.M.O.
ACCOMPLISHMENT
TO DATE PREVIOUS THIS PERIOD
% Wt. Amount Percent % Wt. Amount Percent % Wt. Amount

2.110% 1,053.46 100.00 2.110% 1,053.46

2.065% 1,032.83 25.00 2.065% 1,032.83


2.415% 1,207.27 50.00 2.415% 1,207.27
6.590% 3,293.56 6.590% 3,293.56

__________________________

Project Manager

_________________________

President/A.M.O.

You might also like