Professional Documents
Culture Documents
Page 1 of 46
B.3 Clearing and Grubbing sq.m 153
Labor Days
Engineer 1 man 1 700.00 700.00
Foreman 1 man 1 500.00 500.00
Skilled workers 1 man 2 350.00 700.00
labor 1 man 4 200.00 800.00
Sub-Total 2,700.00
B.4 Structural Excavation cu.m 36.14
Labor Days
Engineer 5 man 1 700.00 3,500.00
Foreman 5 man 1 500.00 2,500.00
Skilled workers 5 man 2 350.00 3,500.00
labor 5 man 6 200.00 6,000.00
Sub-Total 15,500.00
ITEM "B" Total 61,651.00
C. CONCRETING WORKS
C.1 Column Footing cu.m 4.68
Portland Cement bag 43.00 275.00 11,825.00
Crush gravel 1" cu.m 4.75 950.00 4,512.50
Washed Sand cu.m 2.50 850.00 2,125.00
C.2 Tie Beam cu.m 5.7 -
Portland Cement bag 52.00 275.00 14,300.00
Crush gravel 1" cu.m 5.75 950.00 5,462.50
Washed Sand cu.m 3.00 850.00 2,550.00
C.3 Column cu.m 4.94
Portland Cement bag 45.00 275.00 12,375.00
Crush gravel 1" cu.m 5.00 950.00 4,750.00
Washed Sand cu.m 2.50 850.00 2,125.00
C.4 Roof Beam cu.m 6.75
Portland Cement bag 61.00 275.00 16,775.00
Crush gravel 1" cu.m 6.75 950.00 6,412.50
Washed Sand cu.m 3.50 850.00 2,975.00
C.5 Slab on grade cu.m 15.3
Portland Cement bag 138.00 275.00 37,950.00
Crush gravel 1" cu.m 15.50 950.00 14,725.00
Washed Sand cu.m 7.75 850.00 6,587.50
C.6 Ramp on fill cu.m 0.58
Portland Cement bag 6.00 275.00 1,650.00
Crush gravel 1" cu.m 0.75 950.00 712.50
Washed Sand cu.m 0.50 850.00 425.00
Sub-Total 148,237.50
C.7 Labor Days
Engineer 20 man 1 700.00 14,000.00
Foreman 20 man 1 500.00 10,000.00
Skilled workers 20 man 4 350.00 28,000.00
labor 20 man 6 200.00 24,000.00
Sub-Total 76,000.00
C.8 Equipment Days
1 Bagger conc. Mixer 20 set 1 1,000.00 20,000.00
Sub-Total 20,000.00
ITEM "C" Total 244,237.50
Page 2 of 46
D. Rebar Works
D.1 Item works
Footing kg 238.11 50.00 11,905.50
Tie Beam kg 585.25 50.00 29,262.50
Column kg 878.38 50.00 43,919.00
Roof Beam kg 801.5 50.00 40,075.00
Slab on grade kg 402.44 50.00 20,122.00
Ramp on fill kg 24.24 50.00 1,212.00
Tie wire #16 kg 59 70.00 4,130.00
Sub-Total 150,626.00
D.2 Labor Days
Engineer 7 man 1 700.00 4,900.00
Foreman 7 man 1 500.00 3,500.00
Skilled workers 7 man 4 350.00 9,800.00
labor 7 man 6 200.00 8,400.00
Sub-Total 26,600.00
D.3 Equipment Days
Bar Cutter 7 set 1 500.00 3,500.00
Sub-Total 3,500.00
ITEM "D" Total 180,726.00
E FORMWORKS
E.1 Tie Beam sq.m 68.4
Coco Lumber bd.ft 348.9 15.00 5,233.50
Ord. Plywood 1/4thickx4x8 pc 12 375.00 4,500.00
CWN Assorted kg 5 65.00 325.00
E.2 Column sq.m 60.42
Coco Lumber bd.ft 308.4 15.00 4,626.00
Ord. Plywood 1/4thickx4x8 pc 11 375.00 4,125.00
CWN Assorted kg 5 65.00 325.00
E.3 Roof Beams sq.m 71.75
Coco Lumber bd.ft 366.4 15.00 5,496.00
Ord. Plywood 1/4thickx4x8 pc 13 375.00 4,875.00
CWN Assorted kg 6 65.00 390.00
Sub-Total 29,895.50
E.4 Labor Days
Engineer 7 man 1 700.00 4,900.00
Foreman 7 man 1 500.00 3,500.00
Skilled workers 7 man 4 350.00 9,800.00
labor 7 man 3 200.00 4,200.00
Sub-Total 22,400.00
ITEM "E" Total 52,295.50
F MASONRY WORKS
F.1 Masonry Wall sq.m 159.98
CHB 6" thick pc 2000 20.00 40,000.00
Portland Cement bag 80.00 275.00 22,000.00
Washed Sand cu.m 8.00 850.00 6,800.00
10mm x 6m RSB kg 212.00 50.00 10,600.00
Tie wire #16 kg 5 70.00 350.00
Concrete Louver Blocks pc 16 35.00 560.00
Page 3 of 46
F.2 Plastering sq.m 319.96
Portland Cement bag 106.00 275.00 29,150.00
Washed Sand cu.m 11.000 850.00 9,350.00
Sub-Total 118,810.00
F.3 Labor Days
Engineer 20 man 1 700.00 14,000.00
Foreman 20 man 1 500.00 10,000.00
Skilled workers 20 man 4 350.00 28,000.00
labor 20 man 6 200.00 24,000.00
Sub-Total 76,000.00
ITEM "F" Total 194,810.00
G DOOR
D-1 andDoor
W-1 panel
(2.6x1.5)WINDOW
.90x2.10
Shutter WORKS
typeon
G.1 150mm wooden jamb with
window wood jalousie on wood set 4 9,500.00 38,000.00
G.2 complete
frame accessories
& fixed clear glass with set 4 1,200.00 4,800.00
W-2 (1.3x1.5)
Window grills Shutter
hollow type
block design,
G.3 transom
window on 50x150mm
wood jalousie wooden
on wood set 4 7,500.00 30,000.00
10mm
jamb &square
completebaraccessories.
(2.6x1.5)
G.4 frame & fixed clear glass with set 4 7,500.00 30,000.00
Window
transom grills hollow block
on 50x150mm design,
wooden
G.5 set 4 5,000.00 20,000.00
10mm square bar (1.3x1.5)
jamb & complete accessories. Sub-Total 122,800.00
G.4 Labor Days
Engineer 3 man 1 700.00 2,100.00
Foreman 3 man 1 500.00 1,500.00
Skilled workers 3 man 4 350.00 4,200.00
labor 3 man 6 200.00 3,600.00
Sub-Total 11,400.00
ITEM "G" Total 134,200.00
H TRUSSES WORKS
H.1 Materials
Angle bar 60x60x6mm kg 207.36 1,700.00 352,512.00
C 150x65x20x1.2mm kg 1425.79 730.00 1,040,826.70
Angle bar 60x60x6mm kg 2349.00 1,700.00 3,993,300.00
Angle bar 20x20x2mm kg 133.68 245.00 32,751.60
Angle bar 50x50x2mm kg 49.06 500.00 24,530.00
Flat bar 1"x1/4 kg 35.4 350.00 12,390.00
Plain round bar 16mmx6m pc 16 475.00 7,600.00
Plain round bar 10mmx6m pc 18 180.00 3,240.00
Turn Buckle 16mm pc 16 120.00 1,920.00
Steel plate 1.2mx2.4mx10mm pc 2 10,500.00 21,000.00
Anchor bolt w/ nut and washer
pc 32 55.00 1,760.00
16mmx50mmx300mm
Anchor bolt w/ nut and washer
pc 24 15.00 360.00
10mmx50mmx200mm
G.I Pipe 1-1/2 pc 5 1,200.00 6,000.00
welding rod kg 85 75.00 6,375.00
Primer Zinc chromate gal 4 925.00 3,700.00
Paint Brush 4" pc 8 75.00 600.00
Sub-Total 5,508,865.30
H.2 Labor Days
Engineer 7 man 1 700.00 4,900.00
Foreman 7 man 1 500.00 3,500.00
Skilled workers 7 man 4 350.00 9,800.00
labor 7 man 6 200.00 8,400.00
Sub-Total 26,600.00
Page 4 of 46
H.3 Equipment Days
Acetelen 7 set 1 -
Welding machine 7 set 1 -
Sander 7 set 1 -
Sub-Total -
ITEM "H" Total 5,535,465.30
I ROOFING WORKS
I.1 Materials
Long span Rib type pre-painted
1.220mmx .048mmthick (Blue sq.m 219.03 450.00 98,563.50
Ridge Roll Pre-painted .
Color) pc 9 550.00 4,950.00
610x2.4mx.48mmthick
Flashing Pre-painted .
pc 10 465.00 4,650.00
610x2.4mx.48mmthick
Teckscrew 2-1/2 pc 1753 1.50 2,629.50
Roof Sealant l 2 240.00 480.00
Sub-Total 111,273.00
I.2 Labor Days
Engineer 5 man 1 700.00 3,500.00
Foreman 5 man 1 500.00 2,500.00
Skilled workers 5 man 5 350.00 8,750.00
labor 5 man 6 200.00 6,000.00
Sub-Total 20,750.00
I.3 Equipment Days
Electric Drill 2 set 1 -
Sub-Total -
ITEM "I" Total 132,023.00
J CARPENTRY WORKS
J.1 Interior Ceiling sq.m 126
Rough lumber sun dried bd.ft 551 30.00 16,530.00
Plywood 1/4 x 4 x8 pc 44 375.00 16,500.00
Finishing Nails kg 3 70.00 210.00
Common Wire Nails kg 10 65.00 650.00
Wood preservative brown L 2 900.00 1,800.00
J.2 Exterior Ceiling sq.m 55.14
Rough lumber sun dried bd.ft 241 30.00 7,230.00
Plywood 1/4 x 4 x8 pc 19 375.00 7,125.00
Finishing Nails kg 2 70.00 140.00
Common Wire Nails kg 5 65.00 325.00
Wood preservative brown L 1 900.00 900.00
Fascia Board fiber cement 8"x12' pc 17 325.00 5,525.00
Ceiling Vent 1"x12"x3m w/Screen pc 12 250.00 3,000.00
J.3 Blackboards sq.m 11.52
S4S Lumber kiln dried tanguile bd.ft 74 32.00 2,368.00
Lawanit 1/4thick pc 4 210.00 840.00
Plywood 1/4 x 4 x8 pc 4 375.00 1,500.00
Finishing Nails kg 1 70.00 70.00
Common Wire Nails kg 2 65.00 130.00
Concrete Nail kg 1 90.00 90.00
Sub-Total 64,933.00
Page 5 of 46
J.4 Labor Days
Engineer 7 man 1 700.00 4,900.00
Foreman 7 man 1 500.00 3,500.00
Skilled workers 7 man 6 350.00 14,700.00
labor 7 man 4 200.00 5,600.00
Sub-Total 28,700.00
ITEM "J" Total 93,633.00
K ELECTRICAL WORKS
K.1 Roughing-Ins.
Electrical Conduit uPVC 15mm pc 20 45.00 900.00
RSC 20mm pc 1 110.00 110.00
Entrance cap 20mm pc 1 50.00 50.00
Junction Box 2"x4" pc 6 2,450.00 14,700.00
Utility Box 2"x4" G.I. pc 4 35.00 140.00
Grounding rod 2.4mx16mm pc 1 750.00 750.00
K.2 Wires and Fixtures 432
3.5mm THW wire stranded roll 10 3,280.00 32,800.00
5.5mm THW wire Stranded m 5 2,750.00 13,750.00
Duplex C.O w/Plate pc 2 100.00 200.00
2 Gang switch w/plate pc 2 100.00 200.00
Single Switch w/ Plate pc 8 60.00 480.00
FL 2x40w industrial type set 2 1,400.00 2,800.00
FL 1x40w industrial type set 1 900.00 900.00
Panel box, Flush Type, 4 Branches set 1 650.00 650.00
Circuit Breaker 40A set 1 270.00 270.00
Circuit Breaker 20A set 2 270.00 540.00
Ceiling Fan set 2 1,650.00 3,300.00
Sub-Total 72,540.00
K.3 Labor Days
Engineer 3 man 1 700.00 2,100.00
Foreman 3 man 1 500.00 1,500.00
Skilled workers 3 man 1 350.00 1,050.00
labor 3 man 2 200.00 1,200.00
Sub-Total 5,850.00
ITEM "K" Total 78,390.00
L PAINTING WORKS
L.1 Concrete Surface sq.m 345.15
Neutralizer gal 5 240.00 1,200.00
Latex flat gal 14 365.00 5,110.00
Masonry Putty gal 14 450.00 6,300.00
Latex semi gloss gal 14 458.00 6,412.00
Acri-Color qrt 5 47.00 235.00
L.2 Wood Suraface sq.m 200.22
Enamel flatwall gal 11 610.00 6,710.00
Glazing Putty gal 11 680.00 7,480.00
Enamel Semi gloss gal 11 610.00 6,710.00
Paint Thinner gal 6 240.00 1,440.00
Page 6 of 46
L.3 Brushes
Brush 4" pc 10 75.00 750.00
Brush 2" pc 10 75.00 750.00
Roller brush 7" w/ tray set 10 95.00 950.00
Roller brush 4" w/ tray set 10 95.00 950.00
Sand paper #120 pc 50 12.50 625.00
Sub-Total 45,622.00
L.4 Labor Days
Engineer 5 man 1 700.00 3,500.00
Foreman 5 man 1 500.00 2,500.00
Skilled workers 5 man 6 350.00 10,500.00
labor 5 man 4 200.00 4,000.00
Sub-Total 20,500.00
ITEM "L" Total 66,122.00
M HANDRAILS WORKS
M.1 Materials
38mm G.I Pipe pc 2 1,200.00 2,400.00
Welding Rod kg 2 65.00 130.00
Sub-Total 2,530.00
M.2 Labor Days
Engineer 2 man 1 700.00 1,400.00
Foreman 2 man 1 500.00 1,000.00
Skilled workers 2 man 1 350.00 700.00
labor 2 man 1 200.00 400.00
Sub-Total 3,500.00
M.3 Equipment Days
Welding machine 1 set 1 1,000.00 1,000.00
Electric Drill 1 set 1 1,000.00 1,000.00
Sub-Total 2,000.00
ITEM "M" Total 8,030.00
N OTHER FIXTURES
N.1 Steel Billboard 4x8 LS 2 15,000.00 30,000.00
N.2 Arm Chairs (wood) pc 90 850.00 76,500.00
N.3 Teacher Table and Chair set 2 1,500.00 3,000.00
N.4 Mural Painting CL 2 20,000.00 40,000.00
N.5 Plate Marker Brass type 30mmx40mm pc 1 8,000.00 8,000.00
Sub-Total 157,500.00
ITEM "N" Total 157,500.00
Total Direct Cost 6,982,453.30
Page 7 of 46
SUMMARY BILL OF QUANTITIES
NOTE:
*The road condition toward school is passable.
PREPARED BY;
Manager/Proprietor
Date: __________________________
Page 8 of 46
Insert contractor letter head
Page 9 of 46
B.3 Clearing and Grubbing sq.m 153
Labor Days
Engineer 2 man 1 550.00 1,100.00
Foreman 2 man 1 450.00 900.00
Skilled workers 2 man 4 350.00 2,800.00
labor 2 man 6 300.00 3,600.00
Sub-Total 8,400.00
B.4 Structural Excavation cu.m 50.78
Labor Days
Engineer 7 man 1 550.00 3,850.00
Foreman 7 man 1 450.00 3,150.00
Skilled workers 7 man 4 350.00 9,800.00
labor 7 man 6 300.00 12,600.00
Sub-Total 29,400.00
ITEM "B" Total 145,510.50
C. CONCRETING WORKS
C.1 Column Footing cu.m 6.48
Portland Cement bag 59 250.00 14,750.00
Crush gravel 1" cu.m 6.5 850.00 5,525.00
Washed Sand cu.m 3.25 650.00 2,112.50
C.2 Tie Beam cu.m 8.2 -
Portland Cement bag 74 250.00 18,500.00
Crush gravel 1" cu.m 8.25 850.00 7,012.50
Washed Sand cu.m 4.25 650.00 2,762.50
C.3 Column cu.m 6.84
Portland Cement bag 62 250.00 15,500.00
Crush gravel 1" cu.m 7 850.00 5,950.00
Washed Sand cu.m 3.5 650.00 2,275.00
C.4 Roof Beam cu.m 9.25
Portland Cement bag 84 250.00 21,000.00
Crush gravel 1" cu.m 9.25 850.00 7,862.50
Washed Sand cu.m 4.25 650.00 2,762.50
C.5 Slab on grade cu.m 22.95
Portland Cement bag 207 250.00 51,750.00
Crush gravel 1" cu.m 23 850.00 19,550.00
Washed Sand cu.m 11.5 650.00 7,475.00
C.6 Ramp on fill cu.m 0.58
Portland Cement bag 6 250.00 1,500.00
Crush gravel 1" cu.m 0.75 850.00 637.50
Washed Sand cu.m 0.5 650.00 325.00
Sub-Total 187,250.00
C.7 Labor Days
Engineer 24 man 1 550.00 13,200.00
Foreman 24 man 1 450.00 10,800.00
Skilled workers 24 man 4 350.00 33,600.00
labor 24 man 6 300.00 43,200.00
Sub-Total 100,800.00
Page 10 of 46
C.8 Equipment Days
1 Bagger conc. Mixer 20 set 1 500.00 10,000.00
Sub-Total 10,000.00
ITEM "C" Total 298,050.00
D. Rebar Works
D.1 Item works
Footing kg 329.7 40.00 13,188.00
Tie Beam kg 841.5 40.00 33,660.00
Column kg 1023.35 40.00 40,934.00
Roof Beam kg 1079.53 40.00 43,181.20
Slab on grade kg 603.66 40.00 24,146.40
Ramp on fill kg 24.24 40.00 969.60
CHB Wall kg 332 40.00 13,280.00
Tie wire #16 kg 86 40.00 3,440.00
Sub-Total 172,799.20
D.2 Labor Days
Engineer 9 man 1 550.00 4,950.00
Foreman 9 man 1 450.00 4,050.00
Skilled workers 9 man 4 350.00 12,600.00
labor 9 man 6 300.00 16,200.00
Sub-Total 37,800.00
D.3 Equipment Days
Bar Cutter 7 set 1 150.00 1,050.00
Sub-Total 1,050.00
ITEM "D" Total 211,649.20
E FORMWORKS
E.1 Tie Beam sq.m 77.9
Coco Lumber bd.ft 397.5 15.00 5,962.50
Ord. Plywood 1/4thickx4x8 pc 14 340.00 4,760.00
CWN Assorted kg 6 80.00 480.00
E.2 Column sq.m 83.66
Coco Lumber bd.ft 426.9 15.00 6,403.50
Ord. Plywood 1/4thickx4x8 pc 15 340.00 5,100.00
CWN Assorted kg 6 80.00 480.00
E.3 Roof Beams sq.m 98
Coco Lumber bd.ft 499.8 15.00 7,497.00
Ord. Plywood 1/4thickx4x8 pc 17 340.00 5,780.00
CWN Assorted kg 7 80.00 560.00
Sub-Total 37,023.00
E.4 Labor Days
Engineer 9 man 1 550.00 4,950.00
Foreman 9 man 1 450.00 4,050.00
Skilled workers 9 man 4 350.00 12,600.00
labor 9 man 6 300.00 16,200.00
Sub-Total 37,800.00
ITEM "E" Total 74,823.00
Page 11 of 46
F MASONRY WORKS
F.1 Masonry Wall sq.m 250.47
CHB 6" thick pc 3131 15.00 46,965.00
Portland Cement bag 126 250.00 31,500.00
Washed Sand cu.m 11 650.00 7,150.00
Concrete Louver Blocks pc 16 30.00 480.00
F.2 Plastering sq.m 500.94
Portland Cement bag 166 250.00 41,500.00
Washed Sand cu.m 17 650.00 11,050.00
Sub-Total 138,645.00
F.3 Labor Days
Engineer 24 man 1 550.00 13,200.00
Foreman 24 man 1 450.00 10,800.00
Skilled workers 24 man 4 350.00 33,600.00
labor 24 man 6 300.00 43,200.00
Sub-Total 100,800.00
ITEM "F" Total 239,445.00
G DOOR
D-1 andDoor
WINDOW WORKS
W-1 panel
(2.6x1.5) .90x2.10
Shutter typeon
G.1 150mm wooden jamb with
window wood jalousie on wood set 6 9,500.00 57,000.00
G.2 complete
frame accessories
& fixed clear glass with set 6 12,000.00 72,000.00
W-2 (1.3x1.5)
Window grills Shutter
hollow type
block design,
G.3 transom
window on 50x150mm
wood jalousie wooden
on wood set 6 6,500.00 39,000.00
10mm
jamb square bar (2.6x1.5)
G.4 frame&&complete
fixed clearaccessories.
glass with set 6 7,500.00 45,000.00
Window grills hollow
transom on 50x150mm block design,
wooden
G.5 set 6 4,500.00 27,000.00
10mm square bar (1.3x1.5)
jamb & complete accessories. Sub-Total 240,000.00
G.4 Labor Days
Engineer 5 man 1 550.00 2,750.00
Foreman 5 man 1 450.00 2,250.00
Skilled workers 5 man 4 350.00 7,000.00
labor 5 man 6 300.00 9,000.00
Sub-Total 21,000.00
ITEM "G" Total 261,000.00
H TRUSSES WORKS
H.1 Materials
Angle bar 60x60x6mm kg #REF! 40.00 #REF!
C 150x65x20x1.2mm kg #REF! 40.00 #REF!
Angle bar 60x60x6mm kg #REF! 40.00 #REF!
Angle bar 50x50x2mm kg #REF! 40.00 #REF!
Angle bar 20x20x2mm kg #REF! 40.00 #REF!
Flat bar 1"x1/4 kg #REF! 40.00 #REF!
Plain round bar 16mmx6m pc #REF! 40.00 #REF!
Plain round bar 10mmx6m pc #REF! 40.00 #REF!
Turn Buckle 16mm pc #REF! 80.00 #REF!
Steel plate 1.2mx2.4mx12mm pc #REF! 10,500.00 #REF!
gusset Plate 1.2mx2.4mx6mm pc #REF! 5,390.00 #REF!
Anchor bolt w/ nut and washer
pc #REF! 45.00 #REF!
16mmx50mmx300mm
Anchor bolt w/ nut and washer
pc #REF! 12.00 #REF!
10mmx50mmx200mm
G.I Pipe 1-1/2 pc 5 991.00 4,955.00
welding rod kg 131 67.00 8,777.00
Primer Zinc chromate gal 5 590.00 2,950.00
Paint Brush 4" pc 8 95.00 760.00
Sub-Total #REF!
Page 12 of 46
H.2 Labor Days
Engineer 9 man 1 550.00 4,950.00
Foreman 9 man 1 450.00 4,050.00
Skilled workers 9 man 4 350.00 12,600.00
labor 9 man 6 300.00 16,200.00
Sub-Total 37,800.00
H.3 Equipment Days
Acetelen 7 set 1 1,500.00 10,500.00
Welding machine 7 set 1 500.00 3,500.00
Sander 7 set 1 150.00 1,050.00
Sub-Total 15,050.00
ITEM "H" Total #REF!
I ROOFING WORKS
I.1 Materials
Long span Rib type pre-painted
1.220mmx .048mmthick (Blue sq.m 323.33 428.00 138,385.24
Ridge
Color) Roll Pre-painted . pc 13 549.00 7,137.00
610x2.4mx.48mmthick
Flashing Pre-painted .
pc 10 464.00 4,640.00
610x2.4mx.48mmthick
Teckscrew 2-1/2 pc 2587 1.50 3,880.50
Roof Sealant l 3 240.00 720.00
Sub-Total 154,762.74
I.2 Labor Days
Engineer 3 man 1 550.00 1,650.00
Foreman 3 man 1 450.00 1,350.00
Skilled workers 3 man 4 350.00 4,200.00
labor 3 man 6 300.00 5,400.00
Sub-Total 12,600.00
I.3 Equipment Days
Electric Drill 2 set 1 150.00 300.00
Sub-Total 300.00
ITEM "I" Total 167,662.74
J CARPENTRY WORKS
J.1 Interior Ceiling sq.m 189
Rough lumber sun dried bd.ft 826 32.00 26,432.00
Plywood 1/4 x 4 x8 pc 65 340.00 22,100.00
Finishing Nails kg 4 80.00 320.00
Common Wire Nails kg 15 80.00 1,200.00
Wood preservative brown L 3 900.00 2,700.00
J.2 Exterior Ceiling sq.m 78.54
Rough lumber sun dried bd.ft 344 32.00 11,008.00
Plywood 1/4 x 4 x8 pc 27 340.00 9,180.00
Finishing Nails kg 2 80.00 160.00
Common Wire Nails kg 7 80.00 560.00
Wood preservative brown L 2 900.00 1,800.00
Fascia Board fiber cement 8"x12' pc 21 325.00 6,825.00
Ceiling Vent 1"x12"x3m w/Screen pc 18 250.00 4,500.00
Page 13 of 46
J.3 Blackboards sq.m 17.28
S4S Lumber bd.ft 110 32.00 3,520.00
Lawanit 1/4thick pc 6 340.00 2,040.00
Plywood 1/4 x 4 x8 pc 6 340.00 2,040.00
Finishing Nails kg 2 80.00 160.00
Common Wire Nails kg 3 80.00 240.00
Concrete Nail kg 1 90.00 90.00
Sub-Total 94,875.00
J.4 Labor Days
Engineer 9 man 1 550.00 4,950.00
Foreman 9 man 1 450.00 4,050.00
Skilled workers 9 man 4 350.00 12,600.00
labor 9 man 6 300.00 16,200.00
Sub-Total 37,800.00
ITEM "J" Total 132,675.00
K ELECTRICAL WORKS
K.1 Roughing-Ins.
Electrical Conduit uPVC 15mm pc 144 50.00 7,200.00
RSC 20mm pc 1 113.00 113.00
Entrance cap 20mm pc 1 50.00 50.00
Junction Box 2"x4" pc 36 15.00 540.00
Utility Box 2"x4" pc 24 30.00 720.00
Grounding rod 2.4mx16mm pc 1 150.00 150.00
K.2 Wires and Fixtures
3.5mm THW wire stranded m 1296 26.00 33,696.00
5.5mm THW wire Stranded m 10 39.00 390.00
Duplex C.O w/Plate pc 3 264.00 792.00
2 Gang switch w/plate pc 3 154.00 462.00
Single Switch w/ Plate pc 12 98.00 1,176.00
FL 2x40w industrial type set 12 2,600.00 31,200.00
FL 1x40w industrial type set 6 1,185.00 7,110.00
Panel box, Flush Type, 4 Branches set 1 1,200.00 1,200.00
Circuit Breaker 40A set 1 442.00 442.00
Circuit Breaker 20A set 3 315.00 945.00
Ceiling Fan set 3 2,500.00 7,500.00
Sub-Total 93,686.00
K.3 Labor Days
Engineer 5 man 1 550.00 2,750.00
Foreman 5 man 1 450.00 2,250.00
Skilled workers 5 man 4 350.00 7,000.00
labor 5 man 6 300.00 9,000.00
Sub-Total 21,000.00
ITEM "K" Total 114,686.00
L PAINTING WORKS
L.1 Concrete Surface sq.m 500.94
Neutralizer gal 7 145.00 1,015.00
Latex flat gal 21 495.00 10,395.00
Masonry Putty gal 21 350.00 7,350.00
Latex semi gloss gal 21 550.00 11,550.00
Acri-Color qrt 6 35.00 210.00
L.2 Wood Suraface sq.m 600.66
Page 14 of 46
Enamel flatwall gal 15 495.00 7,425.00
Glazing Putty gal 12 542.00 6,504.00
Enamel Semi gloss gal 15 530.00 7,950.00
Paint Thinner gal 15 286.00 4,290.00
L.3 Brushes
Brush 4" pc 12 95.00 1,140.00
Brush 2" pc 12 50.00 600.00
Roller brush 7" w/ tray set 12 250.00 3,000.00
Roller brush 4" w/ tray set 12 180.00 2,160.00
Sand paper #120 pc 50 15.00 750.00
Sub-Total 64,339.00
L.4 Labor Days
Engineer 5 man 1 550.00 2,750.00
Foreman 5 man 1 450.00 2,250.00
Skilled workers 5 man 4 350.00 7,000.00
labor 5 man 6 300.00 9,000.00
Sub-Total 21,000.00
ITEM "L" Total 85,339.00
M HANDRAILS WORKS
M.1 Materials
38mm G.I Pipe pc 2 499.00 998.00
Welding Rod kg 2 67.00 134.00
Sub-Total 1,132.00
M.2 Labor Days
Engineer 3 man 1 550.00 1,650.00
Foreman 3 man 1 450.00 1,350.00
Skilled workers 3 man 4 350.00 4,200.00
labor 3 man 6 300.00 5,400.00
Sub-Total 12,600.00
M.3 Equipment Days
Welding machine 1 set 1 500.00 500.00
Electric Drill 1 set 1 150.00 150.00
Sub-Total 650.00
ITEM "M" Total 14,382.00
N OTHER FIXTURES
N.1 Steel Billboard 4x8 LS 2 15,000.00 30,000.00
N.2 Arm Chairs (wood) pc 135 900.00 121,500.00
N.3 Teacher Table and Chair set 3 4,500.00 13,500.00
N.4 Mural Painting CL 3 20,000.00 60,000.00
N.5 Plate Marker Brass type 30mmx40mm pc 1 8,000.00 8,000.00
Sub-Total 233,000.00
ITEM "N" Total 233,000.00
Total Direct Cost #REF!
Page 15 of 46
SUMMARY BILL OF QUANTITIES
NOTE:
*The School location is beside Rio Grande De Mindanao. The means of transportation going in this school is
through pump boat. The hauling ang handling cost is somehow expensive because of the triple hauling.
PREPARED BY;
Date: __________________________
Page 16 of 46
Insert contractor letter head
Page 17 of 46
B.3 Clearing and Grubbing sq.m 153
Labor Days
Engineer 1 man 1 550.00 550.00
Foreman 1 man 1 450.00 450.00
Skilled workers 1 man 4 350.00 1,400.00
labor man 6 300.00 -
Sub-Total 2,400.00
B.4 Structural Excavation cu.m 50.78
Labor Days
Engineer 5 man 1 550.00 2,750.00
Foreman 5 man 1 450.00 2,250.00
Skilled workers 5 man 4 350.00 7,000.00
labor 5 man 6 300.00 9,000.00
Sub-Total 21,000.00
ITEM "B" Total 122,710.50
C. CONCRETING WORKS
C.1 Column Footing cu.m 6.48
Portland Cement bag 58.32 250.00 14,580.00
Crush gravel 1" cu.m 4.47 850.00 3,800.52
Washed Sand cu.m 2.98 650.00 1,937.52
C.2 Tie Beam cu.m 8.2 -
Portland Cement bag 73.80 250.00 18,450.00
Crush gravel 1" cu.m 5.66 850.00 4,809.30
Washed Sand cu.m 3.77 650.00 2,451.80
C.3 Column cu.m 6.84
Portland Cement bag 61.56 250.00 15,390.00
Crush gravel 1" cu.m 4.72 850.00 4,011.66
Washed Sand cu.m 3.15 650.00 2,045.16
C.4 Roof Beam cu.m 9.25
Portland Cement bag 83.25 250.00 20,812.50
Crush gravel 1" cu.m 6.38 850.00 5,425.13
Washed Sand cu.m 4.26 650.00 2,765.75
C.5 Slab on grade cu.m 22.95
Portland Cement bag 206.55 250.00 51,637.50
Crush gravel 1" cu.m 15.84 850.00 13,460.18
Washed Sand cu.m 10.56 650.00 6,862.05
C.6 Ramp on fill cu.m 0.58
Portland Cement bag 5.22 250.00 1,305.00
Crush gravel 1" cu.m 0.40 850.00 340.17
Washed Sand cu.m 0.27 650.00 173.42
Sub-Total 170,257.65
C.7 Labor Days
Engineer 20 man 1 550.00 11,000.00
Foreman 20 man 1 450.00 9,000.00
Skilled workers 20 man 4 350.00 28,000.00
labor 20 man 6 300.00 36,000.00
Sub-Total 84,000.00
Page 18 of 46
C.8 Equipment Days
1 Bagger conc. Mixer 20 set 1 500.00 10,000.00
Sub-Total 10,000.00
ITEM "C" Total 264,257.65
D. Rebar Works
D.1 Item works
Footing kg 329.7 40.00 13,188.00
Tie Beam kg 841.5 40.00 33,660.00
Column kg 1023.35 40.00 40,934.00
Roof Beam kg 1079.53 40.00 43,181.20
Slab on grade kg 603.66 40.00 24,146.40
Ramp on fill kg 24.24 40.00 969.60
CHB Wall kg 332 40.00 13,280.00
Tie wire #16 kg 86 40.00 3,440.00
Sub-Total 172,799.20
D.2 Labor Days
Engineer 7 man 1 550.00 3,850.00
Foreman 7 man 1 450.00 3,150.00
Skilled workers 7 man 4 350.00 9,800.00
labor 7 man 6 300.00 12,600.00
Sub-Total 29,400.00
D.3 Equipment Days
Bar Cutter 7 set 1 150.00 1,050.00
Sub-Total 1,050.00
ITEM "D" Total 203,249.20
E FORMWORKS
E.1 Tie Beam sq.m 77.9
Coco Lumber bd.ft 397.5 15.00 5,962.50
Ord. Plywood 1/4thickx4x8 pc 14 340.00 4,760.00
CWN Assorted kg 6 80.00 480.00
E.2 Column sq.m 83.66
Coco Lumber bd.ft 426.9 15.00 6,403.50
Ord. Plywood 1/4thickx4x8 pc 15 340.00 5,100.00
CWN Assorted kg 6 80.00 480.00
E.3 Roof Beams sq.m 98
Coco Lumber bd.ft 499.8 15.00 7,497.00
Ord. Plywood 1/4thickx4x8 pc 17 340.00 5,780.00
CWN Assorted kg 7 80.00 560.00
Sub-Total 37,023.00
E.4 Labor Days
Engineer 7 man 1 550.00 3,850.00
Foreman 7 man 1 450.00 3,150.00
Skilled workers 7 man 4 350.00 9,800.00
labor 7 man 6 300.00 12,600.00
Sub-Total 29,400.00
ITEM "E" Total 66,423.00
Page 19 of 46
F MASONRY WORKS
F.1 Masonry Wall sq.m 250.47
CHB 6" thick pc 3131 15.00 46,965.00
Portland Cement bag 126 250.00 31,500.00
Washed Sand cu.m 11 650.00 7,150.00
Concrete Louver Blocks pc 16 30.00 480.00
F.2 Plastering sq.m 500.94
Portland Cement bag 166 250.00 41,500.00
Washed Sand cu.m 17 650.00 11,050.00
Sub-Total 138,645.00
F.3 Labor Days
Engineer 20 man 1 550.00 11,000.00
Foreman 20 man 1 450.00 9,000.00
Skilled workers 20 man 4 350.00 28,000.00
labor 20 man 6 300.00 36,000.00
Sub-Total 84,000.00
ITEM "F" Total 222,645.00
G DOOR
D-1 andDoor
WINDOW WORKS
W-1 panel
(2.6x1.5) .90x2.10
Shutter typeon
G.1 150mm wooden jamb with
window wood jalousie on wood set 6 9,500.00 57,000.00
G.2 complete
frame accessories
& fixed clear glass with set 6 12,000.00 72,000.00
W-2 (1.3x1.5)
Window grills Shutter
hollow type
block design,
G.3 transom
window on 50x150mm
wood jalousie wooden
on wood set 6 6,500.00 39,000.00
10mm
jamb square bar (2.6x1.5)
G.4 frame&&complete
fixed clearaccessories.
glass with set 6 7,500.00 45,000.00
Window grills hollow
transom on 50x150mm block design,
wooden
G.5 set 6 4,500.00 27,000.00
10mm square bar (1.3x1.5)
jamb & complete accessories. Sub-Total 240,000.00
G.4 Labor Days
Engineer 3 man 1 550.00 1,650.00
Foreman 3 man 1 450.00 1,350.00
Skilled workers 3 man 4 350.00 4,200.00
labor 3 man 6 300.00 5,400.00
Sub-Total 12,600.00
ITEM "G" Total 252,600.00
H TRUSSES WORKS
H.1 Materials
Angle bar 60x60x5mm kg 6902.172 40.00 276,086.88
C 150x65x20x1.2mm kg 2108.35 40.00 84,334.00
Angle bar 50x50x2mm kg 81.77 40.00 3,270.80
Angle bar 20x20x2mm kg 185.11 40.00 7,404.40
Flat bar 1"x1/4 kg 49.58 40.00 1,983.20
Plain round bar 16mmx6m pc 24 40.00 960.00
Plain round bar 10mmx6m pc 27 40.00 1,080.00
Turn Buckle 16mm pc 24 80.00 1,920.00
Steel plate 1.2mx2.4mx12mm pc 2 10,500.00 21,000.00
gusset Plate 1.2mx2.4mx6mm pc 2 5,390.00 10,780.00
Anchor bolt w/ nut and washer
pc 48 45.00 2,160.00
16mmx50mmx300mm
Anchor bolt w/ nut and washer
pc 32 12.00 384.00
10mmx50mmx200mm
G.I Pipe 1-1/2 pc 5 991.00 4,955.00
welding rod kg 131 67.00 8,777.00
Primer Zinc chromate gal 5 590.00 2,950.00
Paint Brush 4" pc 8 95.00 760.00
Sub-Total 428,805.28
Page 20 of 46
H.2 Labor Days
Engineer 7 man 1 550.00 3,850.00
Foreman 7 man 1 450.00 3,150.00
Skilled workers 7 man 4 350.00 9,800.00
labor 7 man 6 300.00 12,600.00
Sub-Total 29,400.00
H.3 Equipment Days
Acetelen 7 set 1 1,500.00 10,500.00
Welding machine 7 set 1 500.00 3,500.00
Sander 7 set 1 150.00 1,050.00
Sub-Total 15,050.00
ITEM "H" Total 473,255.28
I ROOFING WORKS
I.1 Materials
Long span Rib type pre-painted
1.220mmx .048mmthick (Blue sq.m 323.33 428.00 138,385.24
Ridge
Color) Roll Pre-painted . pc 13 549.00 7,137.00
610x2.4mx.48mmthick
Flashing Pre-painted .
pc 10 464.00 4,640.00
610x2.4mx.48mmthick
Teckscrew 2-1/2 pc 2587 1.50 3,880.50
Roof Sealant l 3 240.00 720.00
Sub-Total 154,762.74
I.2 Labor Days
Engineer 2 man 1 550.00 1,100.00
Foreman 2 man 1 450.00 900.00
Skilled workers 2 man 4 350.00 2,800.00
labor 2 man 6 300.00 3,600.00
Sub-Total 8,400.00
I.3 Equipment Days
Electric Drill 2 set 1 150.00 300.00
Sub-Total 300.00
ITEM "I" Total 163,462.74
J CARPENTRY WORKS
J.1 Interior Ceiling sq.m 189
Rough lumber sun dried bd.ft 826 32.00 26,432.00
Plywood 1/4 x 4 x8 pc 65 340.00 22,100.00
Finishing Nails kg 4 80.00 320.00
Common Wire Nails kg 15 80.00 1,200.00
Wood preservative brown L 3 900.00 2,700.00
J.2 Exterior Ceiling sq.m 78.54
Rough lumber sun dried bd.ft 344 32.00 11,008.00
Plywood 1/4 x 4 x8 pc 27 340.00 9,180.00
Finishing Nails kg 2 80.00 160.00
Common Wire Nails kg 7 80.00 560.00
Wood preservative brown L 2 900.00 1,800.00
Fascia Board fiber cement 8"x12' pc 21 325.00 6,825.00
Ceiling Vent 1"x12"x3m w/Screen pc 18 250.00 4,500.00
Page 21 of 46
J.3 Blackboards sq.m 17.28
S4S Lumber bd.ft 110 32.00 3,520.00
Lawanit 1/4thick pc 6 340.00 2,040.00
Plywood 1/4 x 4 x8 pc 6 340.00 2,040.00
Finishing Nails kg 2 80.00 160.00
Common Wire Nails kg 3 80.00 240.00
Concrete Nail kg 1 90.00 90.00
Sub-Total 94,875.00
J.4 Labor Days
Engineer 7 man 1 550.00 3,850.00
Foreman 7 man 1 450.00 3,150.00
Skilled workers 7 man 4 350.00 9,800.00
labor 7 man 6 300.00 12,600.00
Sub-Total 29,400.00
ITEM "J" Total 124,275.00
K ELECTRICAL WORKS
K.1 Roughing-Ins.
Electrical Conduit uPVC 15mm pc 144 50.00 7,200.00
RSC 20mm pc 1 113.00 113.00
Entrance cap 20mm pc 1 50.00 50.00
Junction Box 2"x4" pc 36 15.00 540.00
Utility Box 2"x4" pc 24 30.00 720.00
Grounding rod 2.4mx16mm pc 1 150.00 150.00
K.2 Wires and Fixtures
3.5mm THW wire stranded m 1296 26.00 33,696.00
5.5mm THW wire Stranded m 10 39.00 390.00
Duplex C.O w/Plate pc 3 264.00 792.00
2 Gang switch w/plate pc 3 154.00 462.00
Single Switch w/ Plate pc 12 98.00 1,176.00
FL 2x40w industrial type set 12 2,600.00 31,200.00
FL 1x40w industrial type set 6 1,185.00 7,110.00
Panel box, Flush Type, 4 Branches set 1 1,200.00 1,200.00
Circuit Breaker 40A set 1 442.00 442.00
Circuit Breaker 20A set 3 315.00 945.00
Ceiling Fan set 3 2,500.00 7,500.00
Sub-Total 93,686.00
K.3 Labor Days
Engineer 3 man 1 550.00 1,650.00
Foreman 3 man 1 450.00 1,350.00
Skilled workers 3 man 4 350.00 4,200.00
labor 3 man 6 300.00 5,400.00
Sub-Total 12,600.00
ITEM "K" Total 106,286.00
L PAINTING WORKS
L.1 Concrete Surface sq.m 500.94
Neutralizer gal 7 145.00 1,015.00
Latex flat gal 21 495.00 10,395.00
Masonry Putty gal 21 350.00 7,350.00
Latex semi gloss gal 21 550.00 11,550.00
Acri-Color qrt 6 35.00 210.00
Page 22 of 46
L.2 Wood Suraface sq.m 600.66
Enamel flatwall gal 15 495.00 7,425.00
Glazing Putty gal 12 542.00 6,504.00
Enamel Semi gloss gal 15 530.00 7,950.00
Paint Thinner gal 15 286.00 4,290.00
L.3 Brushes
Brush 4" pc 12 95.00 1,140.00
Brush 2" pc 12 50.00 600.00
Roller brush 7" w/ tray set 12 250.00 3,000.00
Roller brush 4" w/ tray set 12 180.00 2,160.00
Sand paper #120 pc 50 15.00 750.00
Sub-Total 64,339.00
L.4 Labor Days
Engineer 5 man 1 550.00 2,750.00
Foreman 5 man 1 450.00 2,250.00
Skilled workers 5 man 4 350.00 7,000.00
labor 5 man 6 300.00 9,000.00
Sub-Total 21,000.00
ITEM "L" Total 85,339.00
M HANDRAILS WORKS
M.1 Materials
38mm G.I Pipe pc 2 499.00 998.00
Welding Rod kg 2 67.00 134.00
Sub-Total 1,132.00
M.2 Labor Days
Engineer 2 man 1 550.00 1,100.00
Foreman 2 man 1 450.00 900.00
Skilled workers 2 man 4 350.00 2,800.00
labor 2 man 6 300.00 3,600.00
Sub-Total 8,400.00
M.3 Equipment Days
Welding machine 1 set 1 500.00 500.00
Electric Drill 1 set 1 150.00 150.00
Sub-Total 650.00
ITEM "M" Total 10,182.00
N OTHER FIXTURES
N.1 Steel Billboard 4x8 LS 2 15,000.00 30,000.00
N.2 Arm Chairs (wood) pc 135 900.00 121,500.00
N.3 Teacher Table and Chair set 3 4,500.00 13,500.00
N.4 Mural Painting CL 3 20,000.00 60,000.00
N.5 Plate Marker Brass type 30mmx40mm pc 1 8,000.00 8,000.00
Sub-Total 233,000.00
ITEM "N" Total 233,000.00
Total Direct Cost 2,359,435.37
Page 23 of 46
SUMMARY BILL OF QUANTITIES
NOTE:
*The road condition toward school is passable.
PREPARED BY;
Date: __________________________
Page 24 of 46
Name ofProject : EXPANSION OF AMINISTRATION BUILDING PHASE-1
IV EARTHWORKS
A. EXCAVATION 500.00 cu.m
Labor
1 Construction Foreman 20 days 650.00 13,000.00
4 Unskilled Laborers 20 days 350.00 28,000.00
Sub-Total (Laborer) 41,000.00
Equipment
1 Backhoe 15 days 15,000.00 225,000.00
Sub Total (Equipment) Php 225,000.00
Page 25 of 46
B. EMBANKMENT 2,200.00 cu.m
Materials
1 Earthfill (Loose Volume) 2,200.00 cu.m 450.00 990,000.00
Sub-Total (Materials) Php 990,000.00
Labor
1 Construction Foreman 30 days 650.00 19,500.00
4 Unskilled Laborers 30 days 350.00 42,000.00
Sub-Total (Laborer) 61,500.00
Equipment
2 Plate Compactor 30 days 1,200.00 72,000.00
4 Backhoe 10 days 15,000.00 600,000.00
Sub Total (Equipment) Php 672,000.00
Page 26 of 46
Tie beams: 40.00 cu.m
Portland Cement 360 bags 275.00 99,000.00
Sand 22.00 cu.m 615.00 13,530.00
Gravel 40.00 cu.m 675.00 27,000.00
180 20mm Ø DRB x 9.00 m 4,001.40 kgs 49.00 196,068.60
200 10mm Ø DRB x 6.00 m 768.00 kgs 49.00 37,632.00
# G.I Tie Wire 100.00 kgs 70.00 7,000.00
Sub-Total (Materials) 380,230.60
Labor
1 Construction Foreman 15.00 days 650.00 9,750.00
5 Skilled Laborers 15.00 days 450.00 33,750.00
10 Unskilled Laborers 15.00 days 350.00 52,500.00
Sub-Total (Labor) 96,000.00
Equipment
1 Concrete Vibrator w/motor oil 1.00 days 1,192.00 1,192.00
1 Transit Mixer/ pumpcrete 1.00 days 25,000.00 25,000.00
1 Bar Cutter 10.00 days 1,758.00 17,580.00
Sub-Total (Equipment) Php 43,772.00
Page 27 of 46
Slab On Fill 71.00 cu.m
Portland Cement 639 bags 275.00 175,725.00
Sand 39.05 cu.m 615.00 24,015.75
Gravel 71.00 cu.m 675.00 47,925.00
400 10mm Ø DRB x 6.00 m 1,536.00 kgs 49.00 75,264.00
# G.I Tie Wire 40.00 kgs 70.00 2,800.00
Sub-Total (Materials) 325,729.75
Labor
1 Construction Foreman 10.00 days 650.00 6,500.00
2 Skilled Laborers 10.00 days 450.00 9,000.00
5 Unskilled Laborers 10.00 days 350.00 17,500.00
Sub-Total (Labor) 33,000.00
Equipment
1 Concrete Vibrator w/motor oil 3.00 days 1,192.00 3,576.00
1 Bagger Mixer 3.00 days 2,500.00 7,500.00
1 Bar Cutter 1.00 days 1,758.00 1,758.00
Sub-Total (Equipment) Php 12,834.00
Page 28 of 46
Second floor Girder/Beam: 60.00 cu.m
Portland Cement 540 bags 275.00 148,500.00
Sand 33.00 cu.m 615.00 20,295.00
Gravel 60.00 cu.m 675.00 40,500.00
564 20mm Ø DRB x 9.00 m 12,537.72 kgs 49.00 614,348.28
800 10mm Ø DRB x 6.00 m 3,072.00 kgs 49.00 150,528.00
# G.I Tie Wire 100.00 kgs 70.00 7,000.00
Sub-Total (Materials) 981,171.28
Labor
1 Construction Foreman 20.00 days 650.00 13,000.00
5 Skilled Laborers 20.00 days 450.00 45,000.00
10 Unskilled Laborers 20.00 days 350.00 70,000.00
Sub-Total (Labor) 128,000.00
Equipment
1 Concrete Vibrator w/motor oil 3.00 days 1,192.00 3,576.00
1 Transit Mixer/ pumpcrete 3.00 days 25,000.00 75,000.00
1 Bar Cutter 20.00 days 1,758.00 35,160.00
Sub-Total (Equipment) Php 113,736.00
Page 29 of 46
VI MASONRY 930.00 sq.m
6.1 Concrete Wall
Materials
CHB 6" thck (Exterior wall) 7,500 pcs 25.00 187,500.00
CHB 4" thck (interior wall) 3,750 pcs 15.00 56,250.00
Portland Cement 1,488 bag 275.00 409,200.00
Washed Sand 78.49 cu.m 650.00 51,019.80
700.00 12mm x 6m RSB 3,570.00 kgs 49.00 174,930.00
G.I Tie wire 35 kgs 70.00 2,450.00
Sub-total (Materials) Php 881,349.80
Labor
1 Construction Foreman 20 days 650.00 13,000.00
4 Skilled Laborers 20 days 450.00 36,000.00
8 UnskilledLaborers 20 days 350.00 56,000.00
Sub-Total (Laborer) 105,000.00
Door -3
0.9m x 2.1m Aluminum frame Glass 1 sets 10,000.00 10,000.00
with complete accessories
Door -4
0.9m x 2.1m Panel Double Door Type Hinged Door 2 sets 18,000.00 36,000.00
on 50 x 150mm Wood Jambs
Lever-Type Locksets with complete accessories
Door -5
0.8m x 2.1m Panel Door Type Hinged Door 6 sets 8,500.00 51,000.00
on 50 x 150mm Wood Jambs
Lever-Type Locksets with complete accessories
Door -6
0.9m x 2.1m Panel Door Type Hinged Door 1 sets 8,500.00 8,500.00
on 50 x 150mm Wood Jambs
Lever-Type Locksets with complete accessories
Door -7
0.6m x 2.1m Plush Door Type Hinged Door 2 sets 4,000.00 8,000.00
on 50 x 150mm Wood Jambs
Lever-Type Locksets with complete accessories
Page 30 of 46
Labor
4 Skilled Laborers 15 days 428.16 25,689.60
Sub-Total (Laborer) 25,689.60
Window (W-2)
Aluminum (Powder coated)Frame Sliding Window 1.00 sets 16,000.00 16,000.00
with 1/4"thk Clear Glass
Window (W-3)
Aluminum (Powder coated)Frame Sliding Window 8.00 sets 16,000.00 128,000.00
with 1/4"thk Clear Glass
Window (W-4)
Steel Framing Awning type Window with Clear Glass 3.00 sets 6,660.00 19,980.00
fixed Windows
Aluminum (powder coated)Frame Fixed Window 10.00 set 5,000.00 50,000.00
with 1/4"thk Clear Glass
Sub-Total (Materials) Php 733,980.00
Labor
16 Skilled Laborers 20 days 428.16 137,011.20
Sub-Total (Laborer) 137,011.20
Page 31 of 46
VIII CEMENT PLASTER FINISH 1,500.00 sq.m
9.1 Convetional Concrete plastering 1,000.00 sq.m
Materials
Portland Cement 250 bags 275.00 68,750.00
Washed Sand 20.83 cu.m 650.00 13,541.67
Special finises 200.00 sq.m 1,800.00 360,000.00
Sub-total (Materials) Php 442,291.67
Labor
8 Skilled Laborers 60 days 428.16 205,516.80
8 UnskilledLaborers 60 days 330.48 158,630.40
Php 364,147.20
Equipment
1 Assorted Hand tools 1 lot 10,000.00 10,000.00
Sub-total (Equipments) Php 10,000.00
Page 32 of 46
Page 33 of 46
XI GLASSING 90.00 sq.m
Materials
Glass Materials (6MM thk.) 90.00 sq.m 2,000.00 180,000.00
Assorted Aluminum Framing 1 lot 150,000.00 150,000.00
Asorted fitings 1 lot 12,000.00 12,000.00
Other materials 1 lot 15,000.00 15,000.00
Sub-total (Materials) Php 357,000.00
Labor
2 Installer 15 days 1,200.00 36,000.00
4 UnskilledLaborers 15 days 330.48 19,828.80
Php 55,828.80
Equipment
1 Assorted Hand tools 15 days 500.00 7,500.00
Sub-total (Equipments) Php 7,500.00
Page 34 of 46
XIII ELECTRICAL 1.00 LS
Materials
20 Kva Distribution Transformer set 1 sets 120,000.00 120,000.00
PVC Pipe 15mmx 3.0 mts 200 pcs 165.00 33,000.00
RCS Pipe 20mm x 6.0 mts 10 pcs 227.00 2,270.00
C-channel metal Tray (fabricated) 60 LM 500.00 30,000.00
Assorted Fittings 1 lot 20,000.00 20,000.00
Wiring and Device
3.5mm2 THW Wire Stranded 2,000 mtrs 33.00 66,000.00
5.5mm2 THW Wire Stranded 600 mtrs 42.00 25,200.00
Duplex Convenience Outlet with Plate 120 pcs 265.00 31,800.00
ACU outlets 5 pcs 265.00 1,325.00
Fire Alarm Bell Outlet 1 pcs 265.00 265.00
2-Gang Switch with Plate 80 pcs 265.00 21,200.00
1-Gang Switch with Plate 60 pcs 265.00 15,900.00
Electric Tape 20 pcs 21.00 420.00
Lighting Fixtures
40Watts, 230V, 60Hz, Fourescent Lighting Fixtures, Box type 50 sets 1,200.00 60,000.00
18 Watts, 230V, 60Hz AC, Compact Fourescent Lamp 30 sets 435.00 13,050.00
Led Strip 6 sets 2,000.00 12,000.00
Panel Board and Cabinets
Panel Board 12 Branches 3 sets 2,500.00 7,500.00
Circuit Breaker 15 AT 10 sets 350.00 3,500.00
Circuit Breaker 20 AT 10 sets 400.00 4,000.00
Circuit Breaker 30 AT 20 sets 450.00 9,000.00
Circuit Breaker 40 AT 3 sets 600.00 1,800.00
Circuit Breaker 100 AT 2 sets 2,000.00 4,000.00
Page 35 of 46
XVI FIRE PROTECTION FACILITIES 1.00 LS
Materials
Dry Piping materials and intallation 1 lot 900,000.00 900,000.00
Fire alarm
Sprinkle Head
Smock Detector
TOTAL DIRECT COST Php 900,000.00
XVII FORMS AND SCAFOLDINGS 1.00 LS
Materials
Assoted Scafolding 1 lot 1,751,000.00 1,751,000.00
TOTAL DIRECT COST Php 1,751,000.00
Prepared by:
Page 36 of 46
Name ofProject : EXPANSION OF AMINISTRATION BUILDING PHASE-1
Bar Cutter 1
Concrete Vibrator 1
Dump truck 1
Welding Machine 1
TOTAL 5
Prepared by:
Project Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Foreman 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Carpenter 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Steel Man 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Mason 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Electrician 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Laborer 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12
Driver 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
TOTAL 31
Prepared by:
Prepared by:
75%
50%
50%
25%
0%
Name ofProject
: EXPANSION OF AMINISTRATION BUILDING PHASE-1
SUMMARY SHEET
DESCRIPTION UNITS UNITS/PRICES
MATERIALS
#26-32"x 7 ft Corr. G.I Roofing sheets 600.00
Plastic Trapal sheets 650.00
Assorted Coco Lumber bd.ft 20.00
Ply Board pcs 420.00
Assorted Nails kgs 90.00
Portland Cement bags 275.00
Sand cu.m 615.00
Gravel cu.m 675.00
20mm Ø DRB x 9.00 m kgs 49.00
# G.I Tie Wire kgs 70.00
EQUIPMENT
Concrete Vibrator w/motor oil days 1,192.00
Transit Mixer/ pumpcrete days 25,000.00
Bar Cutter days 1,758.00
MANPOWER
Construction Foreman days 650.00
Skilled Laborers days 450.00
Unskilled Laborers days 350.00
Prepared by: