You are on page 1of 10

ENGINEER ESTIMATE (EE)

REKAPITULASI

Kegiatan :

Pekerjaan :

Lokasi :

NO URAIAN PEKERJAAN JUMLAH HARGA

A PERSIAPAN 4,000,000.00
B PEKERJAAN PAGAR 39,978,064.82

C PEKERJAAN FINISHING 1,500,000.00

JUMLAH 45,478,064.82

PPN 10% 4,547,806.48


JUMLAH TOTAL 50,025,871.30
DIBULATKAN 50,000,000.00

Terbilang :

Lima Puluh Juta Rupiah

Pekanbaru, Maret 2012


CV. CIPTA REKAYASA ARSITEKTUR

BENARDO, ST
Direktur
ENGINEER ESTIMATE (EE)

RENCANA ANGGARAN BIAYA

Kegiatan :
Pekerjaan :
Lokasi :

NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA

I II III IV V

A PERSIAPAN 4,000,000.00
1 Pembersihan Lokasi 1.000 Ls 1,500,000.00 1,500,000.00
2 Pek. Pembongkaran Pagar Lama 1.000 Ls 2,500,000.00 2,500,000.00

B PEKERJAAN PAGAR 39,978,064.82


1 Pengukuran dan pasangan bouwplank 24.000 M1 61,630.00 1,479,120.00
2 Penggalian Tanah Pondasi 4.770 M3 27,600.00 131,652.00
3 Pas. Cerocok Pondasi 81.000 Btg 57,500.00 4,657,500.00
4 Pek. Pasir Urug Bawah Pondasi 0.603 M3 213,900.00 128,981.70
5 Pek. Cor Pondasi Setapak 1:2:3 0.648 M3 4,783,862.00 3,099,942.58
6 Pek. Cor sloof 15/20 ad. 1:2:3 0.720 M3 6,054,254.50 4,359,063.24
7 Pek. Urugan Tanah Kembali 3.578 M3 751,218.00 2,687,482.40
8 Pek. Cor Kolom Pagar 60/25 1.080 M3 5,562,212.00 6,007,188.96
9 Pek. Cor Balok 15/15 0.540 M3 5,145,412.00 2,778,522.48
10 Pek. Pas. Dinding Batu Bata 1 : 3 41.580 M2 120,799.58 5,022,846.54
11 Pek. Plesteran Dinding Batu Bata 1 : 3 + Aci 83.160 M2 36,702.32 3,052,164.93
12 Pek. Pas. Kawat Duri 24.000 M1 273,900.00 6,573,600.00

C PEKERJAAN FINISHING 1,500,000.00


1 Pembersihan akhir 1.000 Ls 1,500,000.00 1,500,000.00

J U M LA H T O T A L 45,478,064.82
DAFTAR ANALISA HARGA SATUAN

Kegiatan :
Pekerjaan :
Lokasi :

HARGA JUMLAH
HRG. SATUAN
NO. URAIAN UPAH BAHAN HARGA
( Rp )
( Rp ) ( Rp ) ( Rp )
I II III IV V VI

1 Pembersihan Lapangan dan Peralatan

0.100 Pekerja 60,000.00 6,000.00

0.050 Mandor 90,000.00 4,500.00

Jumlah 10,500.00 10,500.00

Dibulatkan 1,050.00

2 1 m' Pek. Pengukuran kembali (site) & Pemasangan Bowplank


0.100 Tukang kayu 70,000.00 7,000.00

0.010 Kepala tukang kayu 80,000.00 800.00

0.100 Pekerja 60,000.00 6,000.00

0.005 Mandor 90,000.00 450.00

0.007 M3 papan meranti klas III 2,470,000.00 17,290.00

0.012 M3 Kayu Kayu kelas II 2,470,000.00 29,640.00

0.020 Kg Paku 22,500.00 450.00

Jumlah 14,250.00 47,380.00 61,630.00

Dibulatkan 61,630.00

3 1 M3 Galian Tanah Biasa Max Kedalaman 1 m

0.400 Pekerja 60,000.00 24,000.00

0.040 Mandor 90,000.00 3,600.00

Jumlah 27,600.00 27,600.00

Dibulatkan 27,600.00

4 1 M3 Urugan Tanah Kembali

0.1920 Pekerja 60,000.00 11,520.00

0.0190 Mandor 90,000.00 1,710.00

Jumlah 13,230.00 13,230.00

Dibulatkan 13,230.00

5 1 M3 Urugan Pasir

0.300 Pekerja 60,000.00 18,000.00

0.010 Mandor 90,000.00 900.00

1.200 M3 Pasir Urug 162,500.00 195,000.00

Jumlah 18,900.00 195,000.00 213,900.00

Dibulatkan 213,900.00

6 1 m³ Membuat Beton 1 Pc : 2 Ps : 3 Kr
1.6500 Pekerja 60,000.00 99,000.00

0.0800 Mandor 90,000.00 7,200.00

0.2500 Tukang Batu 70,000.00 17,500.00

0.0250 Kepala Tukang batu 80,000.00 2,000.00

232.0000 Zak Semen ( 50 Kg ) 1,334.00 309,488.00

0.5200 M3 Pasir Beton 247,000.00 128,440.00

0.7800 M3 Kerikil Cor 240,500.00 187,590.00

Jumlah 125,700.00 625,518.00 751,218.00


HARGA JUMLAH
HRG. SATUAN
NO. URAIAN UPAH BAHAN HARGA
( Rp )
( Rp ) ( Rp ) ( Rp )
I II III IV V VI
Dibulatkan 751,218.00
HARGA JUMLAH
HRG. SATUAN
NO. URAIAN UPAH BAHAN HARGA
( Rp )
( Rp ) ( Rp ) ( Rp )
I II III IV V VI
7 1 m³ Membuat Pondasi Beton Bertulang ( 180 Kg + bekisting )
Bahan

0.2000 m3 Kayu kelas II 2,860,000.00 572,000.00

1.5000 Kg Paku Biasa 2" - 5" 22,500.00 33,750.00

0.4000 Lt Minyak Bekisting 6,500.00 2,600.00

180.0000 Kg Besi Beton Polos 16,250.00 2,925,000.00

2.2500 Kg Kawat Beton 28,600.00 64,350.00

323.0000 Kg Semen Portland 1,334.00 430,882.00

0.5200 m3 Pasir Beton 247,000.00 128,440.00

0.7800 m3 Koral Beton 240,500.00 187,590.00

Tenaga
3.9000 Perkerja 60,000.00 234,000.00

0.3500 Tukang Batu 70,000.00 24,500.00

1.0400 Tukang Kayu 70,000.00 72,800.00

1.0500 Tukang Besi 70,000.00 73,500.00

0.2450 Kepala Tukang 80,000.00 19,600.00

0.1650 Mandor 90,000.00 14,850.00

Jumlah 4,344,612.00 439,250.00 4,783,862.00

Dibulatkan 4,783,862.00

8 1 m³ Membuat Sloof Beton Bertulang ( 237 Kg + bekisting ) 15/20


Bahan

0.2700 m3 Kayu kelas II 2,860,000.00 772,200.00

2.0000 Kg Paku Biasa 2" - 5" 22,500.00 45,000.00

0.6000 Lt Minyak Bekisting 6,500.00 3,900.00

237.6100 Kg Besi Beton Polos 16,250.00 3,861,162.50

3.0000 Kg Kawat Beton 28,600.00 85,800.00

323.0000 Kg Semen Portland 1,334.00 430,882.00

0.5200 m3 Pasir Beton 247,000.00 128,440.00

0.7800 m3 Koral Beton 240,500.00 187,590.00

Tenaga
4.8500 Perkerja 60,000.00 291,000.00

0.3500 Tukang Batu 70,000.00 24,500.00

1.0400 Tukang Kayu 70,000.00 72,800.00

1.5600 Tukang Besi 70,000.00 109,200.00

0.3310 Kepala Tukang 80,000.00 26,480.00

0.1700 Mandor 90,000.00 15,300.00

Jumlah 5,514,974.50 539,280.00 6,054,254.50

Dibulatkan 6,054,254.50
HARGA JUMLAH
HRG. SATUAN
NO. URAIAN UPAH BAHAN HARGA
( Rp )
( Rp ) ( Rp ) ( Rp )
I II III IV V VI
9 1 m³ Membuat Kolom Beton Bertulang ( 100 Kg + bekisting )
Bahan

0.4000 m3 Kayu kelas II 2,860,000.00 1,144,000.00

4.0000 Kg Paku Biasa 2" - 5" 22,500.00 90,000.00

2.0000 Lt Minyak Bekisting 6,500.00 13,000.00

100.0000 Kg Besi Beton Polos 16,250.00 1,625,000.00

4.5000 Kg Kawat Beton 28,600.00 128,700.00

323.0000 Kg Semen Portland 1,334.00 430,882.00

0.5200 m3 Pasir Beton 247,000.00 128,440.00

0.7800 m3 Koral Beton 240,500.00 187,590.00

3.5000 lbr Plywood 9 mm 156,000.00 546,000.00

20.0000 btg Dolken Ø 8 / 4 m 18,000.00 360,000.00

Tenaga
7.3000 Perkerja 60,000.00 438,000.00

0.3500 Tukang Batu 70,000.00 24,500.00

3.3000 Tukang Kayu 70,000.00 231,000.00

2.1000 Tukang Besi 70,000.00 147,000.00

0.5700 Kepala Tukang 80,000.00 45,600.00

0.2500 Mandor 90,000.00 22,500.00

Jumlah 4,653,612.00 908,600.00 5,562,212.00

Dibulatkan 5,562,212.00

10 1 m³ Membuat Reng Balok Beton Bertulang ( 15 x 15) cm


Bahan

0.2700 m3 Kayu kelas II 2,860,000.00 772,200.00

2.0000 Kg Paku Biasa 2" - 5" 22,500.00 45,000.00

2.0000 Lt Minyak Bekisting 6,500.00 13,000.00

100.0000 Kg Besi Beton Polos 16,250.00 1,625,000.00

4.5000 Kg Kawat Beton 28,600.00 128,700.00

323.0000 Kg Semen Portland 1,334.00 430,882.00

0.5200 m3 Pasir Beton 247,000.00 128,440.00

0.7800 m3 Koral Beton 240,500.00 187,590.00

3.5000 lbr Plywood 9 mm 156,000.00 546,000.00

20.0000 btg Dolken Ø 8 / 4 m 18,000.00 360,000.00

Tenaga
7.3000 Perkerja 60,000.00 438,000.00

0.3500 Tukang Batu 70,000.00 24,500.00

3.3000 Tukang Kayu 70,000.00 231,000.00

2.1000 Tukang Besi 70,000.00 147,000.00

0.5700 Kepala Tukang 80,000.00 45,600.00

0.2500 Mandor 90,000.00 22,500.00

Jumlah 4,236,812.00 908,600.00 5,145,412.00

Dibulatkan 5,145,412.00
HARGA JUMLAH
HRG. SATUAN
NO. URAIAN UPAH BAHAN HARGA
( Rp )
( Rp ) ( Rp ) ( Rp )
I II III IV V VI
11 1 M2 Pasang bata merah tebal 1/2 bata, 1 Pc : 3 Ps

0.320 Pekerja 60,000.00 19,200.00

0.100 Tukang batu 70,000.00 7,000.00

0.010 Kepala Tukang 80,000.00 800.00

0.015 Mandor 90,000.00 1,350.00

100.000 Bh Bata merah 5 x 11 x 22 cm 660.00 66,000.00

14.370 Kg Semen Portland 1,334.00 19,169.58

0.040 M3 Pasir pasang 182,000.00 7,280.00

Jumlah 28,350.00 92,449.58 120,799.58

Dibulatkan 120,799.58

12 1 M2 Plesteran 1 Pc : 3 Ps, tebal 15 mm

0.200 Pekerja 60,000.00 12,000.00

0.150 Tukang batu 70,000.00 10,500.00

0.015 Kepala Tukang 80,000.00 1,200.00

0.010 Mandor 90,000.00 900.00

6.480 Kg Semen Portland 1,334.00 8,644.32

0.019 M3 Pasir pasang 182,000.00 3,458.00

Jumlah 24,600.00 12,102.32 36,702.32

Dibulatkan 36,702.32

13 1 Btg Pasang Kayu Cerocok

0.200 Pekerja 60,000.00 12,000.00

0.200 Tukang Kayu 70,000.00 14,000.00

0.020 Kepala Tukang 80,000.00 1,600.00

0.010 Mandor 90,000.00 900.00

1.000 Btg Kayu cerocok 24,000.00 24,000.00

1.000 Alat bantu 5,000.00 5,000.00

Jumlah 28,500.00 29,000.00 57,500.00

Dibulatkan 57,500.00

14 1 m' Pek. Pas. Kawat Berduri


Bahan
8.000 Kg Kawat berduri 22,500.00 180,000.00

3.900 Kg Besi Siku 15,000.00 58,500.00

Tenaga
0.300 Perkerja 60,000.00 18,000.00

0.200 Tukang 70,000.00 14,000.00

0.020 Kepala Tukang 80,000.00 1,600.00

0.020 Mandor 90,000.00 1,800.00

Jumlah 238,500.00 35,400.00 273,900.00

Dibulatkan 273,900.00
DAFTAR HARGA SATUAN BAHAN DAN UPAH

Kegiatan :
Pekerjaan :
Lokasi :

SATUAN HARGA SATUAN


NO URAIAN KET
(Rp) (Rp)

1 2 3 4 5

I. UPAH
1 Kepala Tukang Hari 80,000.00
2 Tukang Hari 70,000.00
3 Pekerja Hari 60,000.00
4 Mandor Hari 90,000.00

II. BAHAN BANGUNAN


A. BAHAN PASANGAN
1 Tanah Urug M3 65,000.00
2 Pasir Urug M3 162,500.00
3 Pasir Pasang M3 182,000.00
4 Pasir Cor/beton M3 247,000.00
5 Kerikil M3 240,500.00
6 Portland Cemen type I Kg 1,334.00
7 Batu bata Bh 660.00
8 Batu Under Site M2 250,000.00
9 Panel Beton Pracetak Lbr 90,000.00
10 Kolom Beton Pracetak Btg 170,000.00

B. BAHAN KAYU
1 Kayu Kozen (Klas I) M3 3,640,000.00
2 Kayu Klas II M3 2,860,000.00
3 Kayu Klas III M3 2,470,000.00
4 Kayu cerocok Btg 24,000.00
5 Plywood 9mm Lbr 156,000.00
6 Kayu Dolken Btg 18,000.00

C. BAHAN BESI/ BAJA, PAKU


1 Besi beton polos Kg 16,250.00
2 Kawat ikat beton Kg 28,600.00
3 Paku biasa Kg 22,500.00
4 Paku seri/triplek Kg 22,500.00
5 Kawat berduri M2 22,500.00
6 Besi Siku Kg 15,000.00

D. BAHAN FINISHING
1 Minyak Bekisting Ltr 6,500.00
ENGINEER ESTIMATE (EE)

VOLUME PEKERJAAN

Kegiatan :
Pekerjaan :
Lokasi :

NO URAIAN PEKERJAAN P L T Unit M' M2 M3 VOLUME SK ETSA KET.

A PERSIAPAN
1 Pembersihan Lokasi 1.000 Ls
2 Pek. Pembongkaran Pagar Lama 1.000 Ls

B PEKERJAAN PAGAR
1 Pengukuran dan pasangan bouwplank 24.000 24.000 24.000 M1
2 Penggalian Tanah Pondasi - - 4.770 M3
Tapak 0.800 0.800 0.500 9.000 0.640 2.880
Pondasi memenjang 2.800 0.250 0.300 9.000 0.700 1.890
3 Pas. Cerocok Pondasi 9.000 9.000 81.000 Btg
4 Pek. Pasir Urug Bawah Pondasi 0.603 M3
Tapak 0.800 0.800 0.050 9.000 0.288
Pondasi memenjang 2.800 0.250 0.050 9.000 0.315
5 Pek. Cor Pondasi Setapak 1:2:3 0.648 M3
Tapak 0.600 0.600 0.200 9.000 0.648
6 Pek. Cor sloof 15/20 ad. 1:2:3 24.000 0.200 0.150 0.720 0.720 M3
7 Pek. Urugan Tanah Kembali 3.578 M3
8 Pek. Cor Kolom Pagar 60/25 0.200 0.300 2.000 9.000 1.080 1.080 M3
9 Pek. Cor Balok 15/15 24.000 0.150 0.150 0.540 0.540 M3
10 Pek. Pas. Dinding Batu Bata 1 : 3 2.800 1.650 9.000 4.620 41.580 M2
11 Pek. Plesteran Dinding Batu Bata 1 : 3 + Aci 2.800 83.160 M2
NO URAIAN PEKERJAAN P L T Unit M' M2 M3 VOLUME SK ETSA KET.

12 Pek. Pas. Kawat Duri 24.000 24.000 M1

D PEKERJAAN FINISHING
1 Pembersihan akhir 1.000 Ls

You might also like