TABEL PERHITUNGAN VOLUME

PRAKTIKUM : KERJA DRAINASE


PEKERJAAN : PEMBANGUNAN SALURAN DRAINASE
LOKASI : DEPAN LAB.KONSTRUKSI POLITEKNIK NEGERI KUPANG

DIMENSI
NO URAIAN PEKEJAAN SKETSA GAMBAR
P L
1 Pekerjaan Galian Tanah 4.71 0.65

2 Pekerjaan Pasangan Dinding 4.71


Saluran Drainase 1 : 3

3 urugan pasir 4.71 0.4


4 plat lantai saluran 4.71 0.4
E

DIMENSI
SAT VOLUME PEKERJAAN
T
0.06 m' luas penampang galian = 1/2 X (a+b) X t
0.13 luas penampang galian = 1/2 X (0,06+0,13) X 4,71
luas penampang galian = 0,44745 m2

volume =luas penampang X lebar saluran


volume = 0,44745 X 0,65
volume = 0,291 m3

0.291

0.21 m' Luas pasangan bata = p X t


= 4,71 X 0,21
= 0,9891 m2

1.9782

0.06 volume urugan pasir = (1/2 ( a+b)X p) x l


0.05 = (1/2X( 0.06+0.05)X4,71)X0,4
= 0,10362 m3
0.10362
0.6 volume plat lantai =(1/2 ( a+b)X p) x l
0.3 = (1/2X( 0,06 + 0,03)X 4,71 )X 0,4
=0,08478

0.08478
HARGA SAT HARGA SAT
NO. URAIAN KOEF SAT
matrial upah

A B C D E F

I PEKERJAAN PERSIAPAN
ANALISA 001 1 m Pembersihan Lahan
Bahan
-
Tenaga
Perkerja 0.400 Oh Rp60,000.00
Mandor 0.020 Oh Rp80,000.00
ANALISA 002 1 m Pengukuran dan Patok
Bahan
Kayu Usuk 0.012 btg Rp33,600.00
Paku 5"-7" 1.200 kg Rp12,500.00
Tenaga
Perkerja 0.350 Oh Rp60,000.00
Mandor 0.040 Oh Rp80,000.00
II PEKERJAAN TANAH
ANALISA 003 1 m3 Pek. Galian Tanah
Tenaga
Perkerja 0.675 Oh Rp60,000.00
Tukang Gali 0.010 Oh Rp75,000.00
Kepala Tukang 0.020 Oh Rp80,000.00
Mandor 0.068 Oh Rp80,000.00
III PEKERJAAN PASANGAN DAN PLESTERAN
ANALISA 004 1 m2 Pek. Pasangan Bata Merah ( 1:3)
Bahan
Semen 14.370 kg Rp1,150.00
Pasir Pasang 0.040 m3 Rp107,142.00
Bata Merah 70.000 bh Rp2,000.00
Tenaga
Perkerja 0.300 Oh Rp60,000.00
Tukang Batu 0.100 Oh Rp75,000.00
Kepala Tukang 0.010 Oh Rp80,000.00
Mandor 0.015 Oh Rp80,000.00
III PEKERJAAN PLAT LANTAI SALURAN
ANALISA 005 1 m3 Pek. Urugan Pasir dibawah plat lantai
Bahan
Pasir Urug 1.200 m3 Rp64,285.00
Tenaga
Perkerja 0.300 Oh Rp60,000.00
Kepala Tukang 0.013 Oh Rp80,000.00
Mandor 0.010 Oh Rp80,000.00
ANALISA 006 1 m3 Pek. Plat Lantai saluran( 1:2:3)
Bahan
Semen Portland 326.000 m3 Rp1,150.00
Pasir Beton 0.540 m3 Rp128,571.00
Batu Kerikil 0.810 m3 Rp177,937.00
Tenaga
Perkerja 1.953 Oh Rp60,000.00
Kepala Tukang 0.488 Oh Rp80,000.00
Mandor 0.030 Oh Rp80,000.00
JUMLAH JUMLAH TOTAL
matrial upah harga

G=(CXE) H = (C X F ) I = ( G + H )

Rp0.00 Rp25,600.00 Rp25,600.00

Rp24,000.00
Rp1,600.00
Rp15,403.20 Rp24,200.00 Rp39,603.20

Rp403.20
Rp15,000.00

Rp21,000.00
Rp3,200.00

Rp0.00 Rp48,290.00 Rp48,290.00

Rp40,500.00
Rp750.00
Rp1,600.00
Rp5,440.00

Rp160,811.18 Rp27,500.00 Rp188,311.18

Rp16,525.50
Rp4,285.68
Rp140,000.00

Rp18,000.00
Rp7,500.00
Rp800.00
Rp1,200.00

Rp77,142.00 Rp19,840.00 Rp96,982.00

Rp77,142.00
Rp18,000.00
Rp1,040.00
Rp800.00
Rp444,328.34 Rp158,620.00 Rp602,948.34

Rp374,900.00
Rp69,428.34

Rp117,180.00
Rp39,040.00
Rp2,400.00
No Jenis Pekerjaan Volume Satuan Harga Satuan

I PEK. PERSIAPAN
1 Pekerjaan Pembersihan 1.00 ls Rp 25,600
2 Pekerjaan Pengukuran dan Patok 1.00 ls Rp 39,603
2.00

ll PEKERJAAN TANAH
1 Galian Tanah Saluran 0.291 m3 Rp 48,290

lll PEKERJAAN PASANGAN DINDING SALURAN


1 Pasangan batu kali 1:5 1.9782 m3 Rp 188,311

lV PEKERJAAN PENUTUP SALURAN


1 Urugan pasir bawah plat lantai 0.10362 m3 Rp 96,982
2 Plat lantai saluran 1:2:3 0.08478 m3 Rp 602,948
0.1884

REKAPITULASI :
Jumlah Harga

Rp 25,600
Rp 39,603
Rp 65,203

Rp 14,052

Rp 372,517

Rp 10,049
Rp 51,118
Rp 61,167

Rp 512,940