DISMANTLING 0F STRUKTURE, 2 UNIT MIXING TANK CAP 30 TON, PIPING WITH ACCESSORIES
PT. JAYA TREAD INDONESIA PLANT GRESIK
TOT. HARGA
NO. URAIAN PEKERJAAN QTY. UNIT weight T, weight sub.total
(Rp)
A. PERSIAPAN
1 Mob Demob ( Staff, Material, Alat Peralatan ) 1.00 ls Rp 20,000,000.00 Rp 20,000,000.00
2 Alat Bantu kerja 1.00 ls Rp 10,500,000.00 Rp 10,500,000.00
3 Keamanan Proyek Gresik - Cirebon 1.00 ls Rp 8,000,000.00 Rp 8,000,000.00
B PEKERJAAN MEKANIKAL
Pembongkaran / Pengangkatan
1 Tangki Bitumen Cap 30 ton tinggi 5,4m. Diameter 2.4m ( 2 unit ) 2.00 unit Rp 7,500,000.00 Rp 15,000,000.00
2 Motor gearbox MIXER ( 2 unit ) 2.00 unit Rp 2,500,000.00 Rp 5,000,000.00
3 Motor Pompa Asphalt sirkulasi 1.00 unit Rp 2,250,000.00 Rp 2,250,000.00
4 Motor Pompa Asphalt Transfer 1.00 unit Rp 3,500,000.00 Rp 3,500,000.00
5 Instalasi Pipa Asphalt + valve 1.00 unit Rp 2,500,000.00 Rp 2,500,000.00
6 Instalasi Pipa Hot Oil + valve 1.00 unit Rp 2,000,000.00 Rp 2,000,000.00
7 Mini Boiler, instalasi, expantion tank 1.00 LS Rp 4,450,000.00 Rp 4,450,000.00
8 Tangga , Platfom & Accesories 1.00 bh Rp 5,500,000.00 Rp 5,500,000.00
9 Filling shelter 1.00 bh Rp 2,000,000.00 Rp 2,000,000.00
10 Timbangan Capasitas 40 ton ( pengerjaan PT. MUGI ) 1.00 bh Rp 12,500,000.00 Rp 12,500,000.00
11 Insulation Pipa 1.00 bh Rp 2,500,000.00 Rp 2,500,000.00
C PEKERJAAN STRUKTUR
1 Roofing Galvanized 300.60 M" Rp 17,500.00 Rp 5,260,500.00 with new roofing bolt
2 Main frame rafter ( L = 9000 mm ) 10.00 sets 218.00 2,180.00 Rp 8,550.00 Rp 18,639,000.00 WF. 200 x 100 x 4.5 x 7
3 Purlin ( L= 14.000 mm ) 16.00 sets 17.50 280.00 Rp 8,550.00 Rp 2,394,000.00 CNP. 100x 50 x 20 x 1,6
4 Roff " X " Win bracing ( L = 4.600 mm ) 16.00 sets Rp 45,000.00 Rp 720,000.00 R. Bar 12 mm
5 Sagrot 272.00 sets Rp 8,550.00 Rp 2,325,600.00 R. Bar 10 mm
6 Sided " X " Win bracing ( L = 4.600 mm ) 16.00 sets Rp 45,000.00 Rp 720,000.00 R. Bar 12 mm
7 Colum Beam 10.00 sets 218.00 2,180.00 Rp 8,550.00 Rp 18,639,000.00 WF. 200 x 200 x 9 x 14
D Elekrikal
1 - Panel Induk 1.00 unit Rp 1,200,000.00 Rp 1,200,000.00
2 - Instalasi Pompa aspal 33.00 m' Rp 35,000.00 Rp 1,155,000.00
3 - Instalasi Motor Mixer Aspal 66.00 m' Rp 35,000.00 Rp 2,310,000.00
4 - Instalasi Instalasi Boiler 45.00 m' Rp 35,000.00 Rp 1,575,000.00
5 - Instalasi Instalasi Penerangan 1.00 ls Rp 650,000.00 Rp 650,000.00
6 - Instalasi Untuk Container 1.00 ls Rp 500,000.00 Rp 500,000.00
7 - Kabel Grounding Tanki ( Paralel dg Exsisting ) 1.00 ls Rp 400,000.00 Rp 400,000.00
DIBULATKAN Rp 318,000,000.00
REKAPITULASI
DISMANTLING 0F STRUKTURE, 2 UNIT MIXING TANK CAP 30 TON, PIPING WITH ACCESSORIES
PT. JAYA TRADE INDONESIA PLANT GRESIK - SURABAYA
TOTAL HARGA
NO. URAIAN PEKERJAAN
(Rp)
B. PEKERJAAN MECHANICAL
1 PEMBNGKARAN TANGKI 2 UNIT,BOILER,PIPE LINE & ACCESSORIES 57,200,000.00
C. PEKERJAAN STRUKTUR
1 PEMBONGKARAN STRUKTUR RUMAH PRODUKSI DAN GUDANG 48,698,100.00
D PEKERJAAN ELEKTRIKAL
1 PEMBONGKARAN ALL INSTALASI 7,790,000.00
A. PERSIAPAN
1 Mob Demob ( Staff, Material, Alat Peralatan ) 1.00 ls
2 Alat Bantu kerja 1.00 ls
3 Keamanan Proyek Gresik - Cirebon 1.00 ls
SUB TOTAL A.
B PEKERJAAN MEKANIKAL
Pembongkaran / Pengangkatan
1 Tangki Bitumen Cap 30 ton tinggi 5,4m. Diameter 2.4m ( 2 unit ) 2.00 unit
2 Motor gearbox MIXER ( 2 unit ) 2.00 unit
3 Motor Pompa Asphalt sirkulasi 1.00 unit
4 Motor Pompa Asphalt Transfer 1.00 unit
5 Instalasi Pipa Asphalt + valve 1.00 unit
6 Instalasi Pipa Hot Oil + valve 1.00 unit
7 Mini Boiler, instalasi, expantion tank 1.00 LS
8 Tangga , Platfom & Accesories 1.00 bh
9 Filling shelter 1.00 bh
10 Timbangan Capasitas 40 ton ( pengerjaan PT. MUGI ) 1.00 bh
11 Insulation Pipa 1.00 bh
SUB TOTAL B
C PEKERJAAN STRUKTUR
1 Roofing Galvanized 300.60 M"
2 Main frame rafter ( L = 9000 mm ) 10.00 sets 218.00
3 Purlin ( L= 14.000 mm ) 16.00 sets 17.50
4 Roff " X " Win bracing ( L = 4.600 mm ) 16.00 sets
5 Sagrot 272.00 sets
6 Sided " X " Win bracing ( L = 4.600 mm ) 16.00 sets
7 Colum Beam 10.00 sets 218.00
SUB TOTAL C
D Elekrikal
1 - Panel Induk 1.00 unit
2 - Instalasi Pompa aspal 33.00 m'
3 - Instalasi Motor Mixer Aspal 66.00 m'
4 - Instalasi Instalasi Boiler 45.00 m'
5 - Instalasi Instalasi Penerangan 1.00 ls
6 - Instalasi Untuk Container 1.00 ls
7 - Kabel Grounding Tanki ( Paralel dg Exsisting ) 1.00 ls
SUB TOTAL D
SUB TOTAL E
SUB TOTAL F
DIBULATKAN
OST ENGINEERING
G TANK CAP 30 TON, PIPING WITH ACCESSORIES
DONESIA PLANT GRESIK
TOT. HARGA
T, weight sub.total
(Rp)
Rp 20,000,000.00 Rp 20,000,000.00
Rp 10,500,000.00 Rp 10,500,000.00
Rp 8,000,000.00 Rp 8,000,000.00
Rp 38,500,000.00
Rp 7,500,000.00 Rp 15,000,000.00
Rp 2,500,000.00 Rp 5,000,000.00
Rp 2,250,000.00 Rp 2,250,000.00
Rp 3,500,000.00 Rp 3,500,000.00
Rp 2,500,000.00 Rp 2,500,000.00
Rp 2,000,000.00 Rp 2,000,000.00
Rp 4,450,000.00 Rp 4,450,000.00
Rp 5,500,000.00 Rp 5,500,000.00
Rp 2,000,000.00 Rp 2,000,000.00
Rp 12,500,000.00 Rp 12,500,000.00
Rp 2,500,000.00 Rp 2,500,000.00
Rp 57,200,000.00
Rp 48,698,100.00
Rp 1,200,000.00 Rp 1,200,000.00
Rp 35,000.00 Rp 1,155,000.00
Rp 35,000.00 Rp 2,310,000.00
Rp 35,000.00 Rp 1,575,000.00
Rp 650,000.00 Rp 650,000.00
Rp 500,000.00 Rp 500,000.00
Rp 400,000.00 Rp 400,000.00
Rp 7,790,000.00
Rp 8,500,000.00 Rp 17,000,000.00
Rp 15,000,000.00 Rp 15,000,000.00
Rp 5,500,000.00 Rp 5,500,000.00
Rp 6,500,000.00 Rp 13,000,000.00
Rp 15,000,000.00 Rp 30,000,000.00
Rp 80,500,000.00
Rp 9,500,000.00 Rp 9,500,000.00
Rp 11,000,000.00 Rp 33,000,000.00
Rp 24,000,000.00 Rp 24,000,000.00
Rp 6,500,000.00 Rp 13,000,000.00
Rp 3,000,000.00 Rp 6,000,000.00
Rp 85,500,000.00
Rp 318,188,100.00
Rp 318,000,000.00